Post Content

Boston River Street Heavy Lift 2, April 14, 2012MassDOT this past weekend successfully completed the latest "Heavy Lift" project as part of the Patrick-Murray Administration's Accelerated Bridge Program to rebuild structurally-deficient bridges across the Commonwealth. 

Demolition work on the former River Street Bridge carrying traffic over the MBTA and CSX Railroad in Boston's Hyde Park neighborhood, seen at left, began late on Friday, April 13.  MassDOT crews then moved a pre-constructed new bridge superstructure into place using specialized heavy lifting equipment, Self-Propelled Modular Transporters. 

Boston River Street Heavy Lift 4, April 15, 2012The transporters lifted the new superstructure, moved it along the railroad tracks below the bridge, and lowered it into position, below left.  Workers paved the approaches to the bridge, and River Street reopened to traffic ahead of the already aggressive weekend schedule at 11:45pm, Monday, April 16.

By using accelerated bridge construction methods on this project, MassDOT avoided more than two years of lane restrictions and reduced the period of night work.  MassDOT has successfully used the "heavy lift" technique to replace bridges in Phillipston, Wellesley and Boston.

To learn more about the project, visit the project website, www.mass.gov/massdot/hydeparkheavylift

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour