Post Content

Milton ABP Ponkapoag Trail Bridge

In keeping with its “Laboratory of Innovation” approach to the Accelerated Bridge Program, the Massachusetts Highway Department has announced a new plan to compress the schedule for rehabilitating the Ponkapoag Trail bridge project in Milton ten months earlier than originally scheduled.  MassHighway, the contractor and town officials agreed to close the bridge to traffic from July 1 to December 24, allowing the contractor to complete the project by June 30, 2010, rather than the original April 2011 date.

MassHighway encourages its employees, contractors and designers who participate in the historic eight-year, $3 billion Accelerated Bridge Program to bring forward plans to reduce design, contracting and construction schedules and cut costs. The Ponkapoag Trail bridge project was originally designed for three stages of construction with one lane open northbound and southbound at all times. During the preconstruction phase of the project, RDA Construction proposed the single-stage project acceleration.

The Ponkapoag Trail bridge is one of several projects moving forward more quickly than first scheduled.

  • Earlier this month, another Accelerated Bridge Program project, the Pleasant Street Bridge in Grafton, opened to traffic months earlier than the normal construction timeframe, thanks to an innovative Design/Build streamlined construction process.
  • The Route 28 bridge over Route 213 in Methuen will be completed by spring 2010 in one year instead of the originally-scheduled two years, after MassHighway identified the opportunity to construct two temporary bridges instead of one because of a change in utility relocation.  

A total of 543 MassHighway and DCR bridges were structurally deficient at the onset of the Accelerated Bridge Program. That number was to have increased to nearly 700 by 2016.  The Accelerated Bridge Program will instead reduce the number of structurally-deficient bridges to approximately 450 while creating thousands of engineering and construction jobs and delivering long-term savings in avoided inflation and deferred maintenance costs.

   
Visit the Accelerated Bridge Program website.

Written By:

Recent Posts

Methuen Rotary I-93 Project Update posted on Mar 4

Methuen Rotary I-93 Project Update

MassDOT’s $66.4 million Methuen Rotary Reconstruction Project on I-93 at Routes 110 and 113 is moving forward during winter 2015. During the month of March, the following activities will continue on the I-93 at Routes 110 and 113 Interchange Reconstruction – Methuen Rotary project:     …Continue Reading Methuen Rotary I-93 Project Update

MassDOT Aeronautics: 2015 Aviation Art Contest Winners posted on Mar 3

MassDOT Aeronautics: 2015 Aviation Art Contest Winners

The MassDOT Aeronautics Division held the Massachusetts State level judging of the 2015 International Aviation Art Contest, with this year’s theme, “World Air Games”. The World Air Games will be held in Dubai in 2015. During 12 days, spectators will see world class competitions and   …Continue Reading MassDOT Aeronautics: 2015 Aviation Art Contest Winners

Boston: Massachusetts Avenue Bridge Public Hearing Set posted on Mar 2

Boston: Massachusetts Avenue Bridge Public Hearing Set

MassDOT has scheduled a Design Public Hearing for the proposed Massachusetts Avenue Bridge over Commonwealth Avenue Project in Boston as follows: Boston Central Library, Commonwealth Salon, 700 Boylston Street, Wednesday, March 25, 2015, 6:30PM-8:00PM The purpose of this hearing is to provide the public with   …Continue Reading Boston: Massachusetts Avenue Bridge Public Hearing Set