Post Content

Milton ABP Ponkapoag Trail Bridge

In keeping with its “Laboratory of Innovation” approach to the Accelerated Bridge Program, the Massachusetts Highway Department has announced a new plan to compress the schedule for rehabilitating the Ponkapoag Trail bridge project in Milton ten months earlier than originally scheduled.  MassHighway, the contractor and town officials agreed to close the bridge to traffic from July 1 to December 24, allowing the contractor to complete the project by June 30, 2010, rather than the original April 2011 date.

MassHighway encourages its employees, contractors and designers who participate in the historic eight-year, $3 billion Accelerated Bridge Program to bring forward plans to reduce design, contracting and construction schedules and cut costs. The Ponkapoag Trail bridge project was originally designed for three stages of construction with one lane open northbound and southbound at all times. During the preconstruction phase of the project, RDA Construction proposed the single-stage project acceleration.

The Ponkapoag Trail bridge is one of several projects moving forward more quickly than first scheduled.

  • Earlier this month, another Accelerated Bridge Program project, the Pleasant Street Bridge in Grafton, opened to traffic months earlier than the normal construction timeframe, thanks to an innovative Design/Build streamlined construction process.
  • The Route 28 bridge over Route 213 in Methuen will be completed by spring 2010 in one year instead of the originally-scheduled two years, after MassHighway identified the opportunity to construct two temporary bridges instead of one because of a change in utility relocation.  

A total of 543 MassHighway and DCR bridges were structurally deficient at the onset of the Accelerated Bridge Program. That number was to have increased to nearly 700 by 2016.  The Accelerated Bridge Program will instead reduce the number of structurally-deficient bridges to approximately 450 while creating thousands of engineering and construction jobs and delivering long-term savings in avoided inflation and deferred maintenance costs.

   
Visit the Accelerated Bridge Program website.

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour