Post Content

Milton ABP Ponkapoag Trail Bridge

In keeping with its “Laboratory of Innovation” approach to the Accelerated Bridge Program, the Massachusetts Highway Department has announced a new plan to compress the schedule for rehabilitating the Ponkapoag Trail bridge project in Milton ten months earlier than originally scheduled.  MassHighway, the contractor and town officials agreed to close the bridge to traffic from July 1 to December 24, allowing the contractor to complete the project by June 30, 2010, rather than the original April 2011 date.

MassHighway encourages its employees, contractors and designers who participate in the historic eight-year, $3 billion Accelerated Bridge Program to bring forward plans to reduce design, contracting and construction schedules and cut costs. The Ponkapoag Trail bridge project was originally designed for three stages of construction with one lane open northbound and southbound at all times. During the preconstruction phase of the project, RDA Construction proposed the single-stage project acceleration.

The Ponkapoag Trail bridge is one of several projects moving forward more quickly than first scheduled.

  • Earlier this month, another Accelerated Bridge Program project, the Pleasant Street Bridge in Grafton, opened to traffic months earlier than the normal construction timeframe, thanks to an innovative Design/Build streamlined construction process.
  • The Route 28 bridge over Route 213 in Methuen will be completed by spring 2010 in one year instead of the originally-scheduled two years, after MassHighway identified the opportunity to construct two temporary bridges instead of one because of a change in utility relocation.  

A total of 543 MassHighway and DCR bridges were structurally deficient at the onset of the Accelerated Bridge Program. That number was to have increased to nearly 700 by 2016.  The Accelerated Bridge Program will instead reduce the number of structurally-deficient bridges to approximately 450 while creating thousands of engineering and construction jobs and delivering long-term savings in avoided inflation and deferred maintenance costs.

   
Visit the Accelerated Bridge Program website.

Written By:

Recent Posts

MBTA: New WiFi System Announced posted on Jul 24

MBTA: New WiFi System Announced

Under a new license agreement signed today by MBTA General Manager Beverly Scott, a state-of-the-art WiFi system will be installed throughout the MBTA’s sprawling network of fourteen Commuter Rail lines. At no cost to the MBTA or its customers, inMOTION Wireless, Inc. will build a   …Continue Reading MBTA: New WiFi System Announced

Boston: Plan Ahead for I-90 Lane Restrictions posted on Jul 23

Boston: Plan Ahead for I-90 Lane Restrictions

MassDOT on Sunday, July 27 at 9:00pm will begin work to improve the median and Commonwealth Avenue Bridge substructure on Interstate 90 in Boston. Beginning Sunday night at 9:00pm and lasting for approximately six months, the left lanes in both Eastbound and Westbound directions on   …Continue Reading Boston: Plan Ahead for I-90 Lane Restrictions

Methuen Rotary Project: Travel Impacts posted on Jul 22

Methuen Rotary Project: Travel Impacts

MassDOT has scheduled upcoming lane closures as part of the Methuen Rotary Reconstruction Project.  Beginning on Monday, July 28, 2014 until further notice, the I-93 breakdown lane will be closed from Exit 46 – Routes 110/113 to Exit 47 – Pelham St. on I-93 Northbound   …Continue Reading Methuen Rotary Project: Travel Impacts