Post Content

Milton ABP Ponkapoag Trail Bridge

In keeping with its “Laboratory of Innovation” approach to the Accelerated Bridge Program, the Massachusetts Highway Department has announced a new plan to compress the schedule for rehabilitating the Ponkapoag Trail bridge project in Milton ten months earlier than originally scheduled.  MassHighway, the contractor and town officials agreed to close the bridge to traffic from July 1 to December 24, allowing the contractor to complete the project by June 30, 2010, rather than the original April 2011 date.

MassHighway encourages its employees, contractors and designers who participate in the historic eight-year, $3 billion Accelerated Bridge Program to bring forward plans to reduce design, contracting and construction schedules and cut costs. The Ponkapoag Trail bridge project was originally designed for three stages of construction with one lane open northbound and southbound at all times. During the preconstruction phase of the project, RDA Construction proposed the single-stage project acceleration.

The Ponkapoag Trail bridge is one of several projects moving forward more quickly than first scheduled.

  • Earlier this month, another Accelerated Bridge Program project, the Pleasant Street Bridge in Grafton, opened to traffic months earlier than the normal construction timeframe, thanks to an innovative Design/Build streamlined construction process.
  • The Route 28 bridge over Route 213 in Methuen will be completed by spring 2010 in one year instead of the originally-scheduled two years, after MassHighway identified the opportunity to construct two temporary bridges instead of one because of a change in utility relocation.  

A total of 543 MassHighway and DCR bridges were structurally deficient at the onset of the Accelerated Bridge Program. That number was to have increased to nearly 700 by 2016.  The Accelerated Bridge Program will instead reduce the number of structurally-deficient bridges to approximately 450 while creating thousands of engineering and construction jobs and delivering long-term savings in avoided inflation and deferred maintenance costs.

   
Visit the Accelerated Bridge Program website.

Written By:

Recent Posts

Route 79/Braga Bridge Project Traffic Update posted on Oct 30

Route 79/Braga Bridge Project Traffic Update

MassDOT will begin implementing traffic changes for the next stage of construction for the Route 79/Braga Bridge Project on Wednesday, November 12. The following changes will be implemented in a phased approach through the middle of December: Vehicles on Route 79/138 (Broadway) bound for Interstate   …Continue Reading Route 79/Braga Bridge Project Traffic Update

RMV: Promise to Customers posted on Oct 28

RMV: Promise to Customers

Today, MassDOT Secretary & CEO Richard A. Davey and MassDOT Registrar of Motor Vehicles Celia J. Blue offered a 10 point promise to RMV customers. The reimagining effort comprises current, ongoing and future initiatives that the RMV has in development to better the Registry experience.   …Continue Reading RMV: Promise to Customers

November E-ZPass Sign Up: Chelsea, Everett posted on Oct 28

November E-ZPass Sign Up: Chelsea, Everett

MassDOT is encouraging motorists to join E-ZPass with All-Electronic Tolling now in place on the Tobin Bridge and expanding statewide within the next two years. The E-ZPass Street Team will be enrolling new customers in the E-ZPass throughout the Fall season. The E-ZPass Van schedule   …Continue Reading November E-ZPass Sign Up: Chelsea, Everett