Post Content

Shoukry Headshot Mar2010
Posted by Shoukry Elnahal, Deputy Chief Engineer for Bridges and Tunnels

Route 9 and Cedar Street were quietly reopened to traffic on Monday morning, almost twelve hours before they were scheduled to be open. A few onlookers watched as some of the first cars travelled under Route 9, and a few drivers sounded their horns and waved appreciatively at the workers. Onlookers stopped by the site throughout the weekend to watch the work rapidly progress. Over a hundred people stood by as the bridge moved—ahead of schedule— down Route 9.

The secret to the incredibly fast bridge replacement was the strategy used by MassDOT and its engineers and builders, which was aimed firmly on a single goal: to provide the best possible customer service to road users and the community by building a long-lasting bridge, safely, efficiently, economically, and with the least possible impact to traffic and the community. To accomplish that, MassDOT pre-constructed the replacement bridge superstructure in a cloverleaf near the old bridge. Doing so kept a vast majority of the work outside of the roadway, nearly eliminating traffic impacts to Route 9.

As shown in the short movie below, once the new bridge superstructure was ready, MassDOT needed to demolish the old bridge and install new portions of the center pier and abutments. On Sunday morning, all preparations were complete. At 5:00 AM, four multi-axle machines called Self-Propelled Modular Transporters (or SPMTs) rumbled to life from their position underneath the new bridge superstructure. They moved in unison, carrying the 530-ton bridge from the cloverleaf onto the Cedar Street ramp. Then, at 8:15, the SPMTs’ many wheels rotated 90 degrees, and the bridge moved smoothly down the ramp onto Route 9 as the crowd watched, amazed. The wheels rotated again, and the bridge moved down Route 9, arriving at the pier and abutments at 9:30. The SPMTs held the bridge above the substructure until the early afternoon, when it was lowered into place.

Crews worked throughout the night to prepare to reopen the bridge. Temporary lane markings are in place and one sidewalk is open for pedestrians. Crews will continue to put the finishing touches on the bridge throughout the month, during off-peak hours. This work includes installing architectural pilasters, final paving and lane marking, completion of sidewalks, and installing signs.

 

Written By:

Recent Posts

RMV: Boston Haymarket Center Opening Celebrated posted on Sep 23

RMV: Boston Haymarket Center Opening Celebrated

Transportation Secretary & CEO Richard A. Davey and Registrar of Motor Vehicles Celia J. Blue joined fellow MassDOT leaders, along with state and local officials, to celebrate the opening of the Commonwealth’s new flagship Registry of Motor Vehicles branch in Boston, Haymarket Center. “MassDOT is   …Continue Reading RMV: Boston Haymarket Center Opening Celebrated

MBTA Map Crowdsourcing Cited for Planning Innovation posted on Sep 23

MBTA Map Crowdsourcing Cited for Planning Innovation

The MBTA crowdsourcing contest to invite graphic designers to help redesign the T System Map is currently featured as the lead Innovative Project by the U.S. Department of Transportation’s Transportation Planning Capacity Building Program. The Transportation Planning Capacity Building Program assists decision makers and transportation   …Continue Reading MBTA Map Crowdsourcing Cited for Planning Innovation

Springfield I-91 Viaduct Project Moves Forward posted on Sep 23

Springfield I-91 Viaduct Project Moves Forward

MassDOT announced that the project to rehabilitate the bridge deck on the elevated portion of Interstate 91 in Springfield is moving forward and being advertised for bids. The I-91 Viaduct Rehabilitation Project will replace the existing deck of the bridge, which is in poor condition.   …Continue Reading Springfield I-91 Viaduct Project Moves Forward