Post Content

Shoukry Headshot Mar2010
Posted by Shoukry Elnahal, Deputy Chief Engineer for Bridges and Tunnels

Route 9 and Cedar Street were quietly reopened to traffic on Monday morning, almost twelve hours before they were scheduled to be open. A few onlookers watched as some of the first cars travelled under Route 9, and a few drivers sounded their horns and waved appreciatively at the workers. Onlookers stopped by the site throughout the weekend to watch the work rapidly progress. Over a hundred people stood by as the bridge moved—ahead of schedule— down Route 9.

The secret to the incredibly fast bridge replacement was the strategy used by MassDOT and its engineers and builders, which was aimed firmly on a single goal: to provide the best possible customer service to road users and the community by building a long-lasting bridge, safely, efficiently, economically, and with the least possible impact to traffic and the community. To accomplish that, MassDOT pre-constructed the replacement bridge superstructure in a cloverleaf near the old bridge. Doing so kept a vast majority of the work outside of the roadway, nearly eliminating traffic impacts to Route 9.

As shown in the short movie below, once the new bridge superstructure was ready, MassDOT needed to demolish the old bridge and install new portions of the center pier and abutments. On Sunday morning, all preparations were complete. At 5:00 AM, four multi-axle machines called Self-Propelled Modular Transporters (or SPMTs) rumbled to life from their position underneath the new bridge superstructure. They moved in unison, carrying the 530-ton bridge from the cloverleaf onto the Cedar Street ramp. Then, at 8:15, the SPMTs’ many wheels rotated 90 degrees, and the bridge moved smoothly down the ramp onto Route 9 as the crowd watched, amazed. The wheels rotated again, and the bridge moved down Route 9, arriving at the pier and abutments at 9:30. The SPMTs held the bridge above the substructure until the early afternoon, when it was lowered into place.

Crews worked throughout the night to prepare to reopen the bridge. Temporary lane markings are in place and one sidewalk is open for pedestrians. Crews will continue to put the finishing touches on the bridge throughout the month, during off-peak hours. This work includes installing architectural pilasters, final paving and lane marking, completion of sidewalks, and installing signs.

 

Written By:

Recent Posts

MBTA: Fitchburg Line Weekend Service Suspension posted on Mar 27

MBTA: Fitchburg Line Weekend Service Suspension

The MBTA has issued a Service Alert:  No Weekend Service on the commuter rail Fitchburg Main Line for the period from April 25th, 2015 through November 22nd, 2015. The suspension of weekend service will allow construction of major improvements on the Fitchburg Main Line to   …Continue Reading MBTA: Fitchburg Line Weekend Service Suspension

Employers Honored for Excellence in Commuter Options posted on Mar 26

Employers Honored for Excellence in Commuter Options

The efforts of more than 170 Massachusetts businesses, colleges, and universities, who promote active, healthy, and sustainable commute options, were celebrated today for helping Massachusetts to reduce traffic congestion, to promote healthy lifestyles, and benefit the environment. The Massachusetts Excellence in Commuter Options (ECO) Awards   …Continue Reading Employers Honored for Excellence in Commuter Options

Longfellow Bridge: “Salt and Pepper” Towers Work posted on Mar 26

Longfellow Bridge: “Salt and Pepper” Towers Work

MassDOT on Saturday, March 28 will begin preparing to dismantle the downstream “salt and pepper” towers as part of the Longfellow Bridge Restoration Project. MassDOT’s contractor, White-Skanska-Consigli JV (WSC), coordinated with the cities of Cambridge and Boston as well as the MBTA to begin dismantling   …Continue Reading Longfellow Bridge: “Salt and Pepper” Towers Work