Post Content

Shoukry Headshot Mar2010
Posted by Shoukry Elnahal, Deputy Chief Engineer for Bridges and Tunnels

Route 9 and Cedar Street were quietly reopened to traffic on Monday morning, almost twelve hours before they were scheduled to be open. A few onlookers watched as some of the first cars travelled under Route 9, and a few drivers sounded their horns and waved appreciatively at the workers. Onlookers stopped by the site throughout the weekend to watch the work rapidly progress. Over a hundred people stood by as the bridge moved—ahead of schedule— down Route 9.

The secret to the incredibly fast bridge replacement was the strategy used by MassDOT and its engineers and builders, which was aimed firmly on a single goal: to provide the best possible customer service to road users and the community by building a long-lasting bridge, safely, efficiently, economically, and with the least possible impact to traffic and the community. To accomplish that, MassDOT pre-constructed the replacement bridge superstructure in a cloverleaf near the old bridge. Doing so kept a vast majority of the work outside of the roadway, nearly eliminating traffic impacts to Route 9.

As shown in the short movie below, once the new bridge superstructure was ready, MassDOT needed to demolish the old bridge and install new portions of the center pier and abutments. On Sunday morning, all preparations were complete. At 5:00 AM, four multi-axle machines called Self-Propelled Modular Transporters (or SPMTs) rumbled to life from their position underneath the new bridge superstructure. They moved in unison, carrying the 530-ton bridge from the cloverleaf onto the Cedar Street ramp. Then, at 8:15, the SPMTs’ many wheels rotated 90 degrees, and the bridge moved smoothly down the ramp onto Route 9 as the crowd watched, amazed. The wheels rotated again, and the bridge moved down Route 9, arriving at the pier and abutments at 9:30. The SPMTs held the bridge above the substructure until the early afternoon, when it was lowered into place.

Crews worked throughout the night to prepare to reopen the bridge. Temporary lane markings are in place and one sidewalk is open for pedestrians. Crews will continue to put the finishing touches on the bridge throughout the month, during off-peak hours. This work includes installing architectural pilasters, final paving and lane marking, completion of sidewalks, and installing signs.

 

Written By:

Recent Posts

MassDOT Aeronautics: 2015 Aviation Art Contest Winners posted on Mar 3

MassDOT Aeronautics: 2015 Aviation Art Contest Winners

The MassDOT Aeronautics Division held the Massachusetts State level judging of the 2015 International Aviation Art Contest, with this year’s theme, “World Air Games”. The World Air Games will be held in Dubai in 2015. During 12 days, spectators will see world class competitions and   …Continue Reading MassDOT Aeronautics: 2015 Aviation Art Contest Winners

Boston: Massachusetts Avenue Bridge Public Hearing Set posted on Mar 2

Boston: Massachusetts Avenue Bridge Public Hearing Set

MassDOT has scheduled a Design Public Hearing for the proposed Massachusetts Avenue Bridge over Commonwealth Avenue Project in Boston as follows: Boston Central Library, Commonwealth Salon, 700 Boylston Street, Wednesday, March 25, 2015, 6:30PM-8:00PM The purpose of this hearing is to provide the public with   …Continue Reading Boston: Massachusetts Avenue Bridge Public Hearing Set

Remembering the Fall River Line posted on Feb 28

Remembering the Fall River Line

South Coast Rail will transport passengers to Boston from Fall River and New Bedford. Both South Coast cities have rich histories, including Fall River’s stint as a gateway to the mid-Atlantic. Until about 80 years ago, the most direct route to New York City from   …Continue Reading Remembering the Fall River Line