Post Content

Shoukry Headshot Mar2010
Posted by Shoukry Elnahal, Deputy Chief Engineer for Bridges and Tunnels

Route 9 and Cedar Street were quietly reopened to traffic on Monday morning, almost twelve hours before they were scheduled to be open. A few onlookers watched as some of the first cars travelled under Route 9, and a few drivers sounded their horns and waved appreciatively at the workers. Onlookers stopped by the site throughout the weekend to watch the work rapidly progress. Over a hundred people stood by as the bridge moved—ahead of schedule— down Route 9.

The secret to the incredibly fast bridge replacement was the strategy used by MassDOT and its engineers and builders, which was aimed firmly on a single goal: to provide the best possible customer service to road users and the community by building a long-lasting bridge, safely, efficiently, economically, and with the least possible impact to traffic and the community. To accomplish that, MassDOT pre-constructed the replacement bridge superstructure in a cloverleaf near the old bridge. Doing so kept a vast majority of the work outside of the roadway, nearly eliminating traffic impacts to Route 9.

As shown in the short movie below, once the new bridge superstructure was ready, MassDOT needed to demolish the old bridge and install new portions of the center pier and abutments. On Sunday morning, all preparations were complete. At 5:00 AM, four multi-axle machines called Self-Propelled Modular Transporters (or SPMTs) rumbled to life from their position underneath the new bridge superstructure. They moved in unison, carrying the 530-ton bridge from the cloverleaf onto the Cedar Street ramp. Then, at 8:15, the SPMTs’ many wheels rotated 90 degrees, and the bridge moved smoothly down the ramp onto Route 9 as the crowd watched, amazed. The wheels rotated again, and the bridge moved down Route 9, arriving at the pier and abutments at 9:30. The SPMTs held the bridge above the substructure until the early afternoon, when it was lowered into place.

Crews worked throughout the night to prepare to reopen the bridge. Temporary lane markings are in place and one sidewalk is open for pedestrians. Crews will continue to put the finishing touches on the bridge throughout the month, during off-peak hours. This work includes installing architectural pilasters, final paving and lane marking, completion of sidewalks, and installing signs.

 

Written By:

Recent Posts

Route 79/Braga Bridge Project Traffic Update posted on Oct 30

Route 79/Braga Bridge Project Traffic Update

MassDOT will begin implementing traffic changes for the next stage of construction for the Route 79/Braga Bridge Project on Wednesday, November 12. The following changes will be implemented in a phased approach through the middle of December: Vehicles on Route 79/138 (Broadway) bound for Interstate   …Continue Reading Route 79/Braga Bridge Project Traffic Update

RMV: Promise to Customers posted on Oct 28

RMV: Promise to Customers

Today, MassDOT Secretary & CEO Richard A. Davey and MassDOT Registrar of Motor Vehicles Celia J. Blue offered a 10 point promise to RMV customers. The reimagining effort comprises current, ongoing and future initiatives that the RMV has in development to better the Registry experience.   …Continue Reading RMV: Promise to Customers

November E-ZPass Sign Up: Chelsea, Everett posted on Oct 28

November E-ZPass Sign Up: Chelsea, Everett

MassDOT is encouraging motorists to join E-ZPass with All-Electronic Tolling now in place on the Tobin Bridge and expanding statewide within the next two years. The E-ZPass Street Team will be enrolling new customers in the E-ZPass throughout the Fall season. The E-ZPass Van schedule   …Continue Reading November E-ZPass Sign Up: Chelsea, Everett