Post Content

Shoukry Headshot Mar2010
Posted by Shoukry Elnahal, Deputy Chief Engineer for Bridges and Tunnels

Route 9 and Cedar Street were quietly reopened to traffic on Monday morning, almost twelve hours before they were scheduled to be open. A few onlookers watched as some of the first cars travelled under Route 9, and a few drivers sounded their horns and waved appreciatively at the workers. Onlookers stopped by the site throughout the weekend to watch the work rapidly progress. Over a hundred people stood by as the bridge moved—ahead of schedule— down Route 9.

The secret to the incredibly fast bridge replacement was the strategy used by MassDOT and its engineers and builders, which was aimed firmly on a single goal: to provide the best possible customer service to road users and the community by building a long-lasting bridge, safely, efficiently, economically, and with the least possible impact to traffic and the community. To accomplish that, MassDOT pre-constructed the replacement bridge superstructure in a cloverleaf near the old bridge. Doing so kept a vast majority of the work outside of the roadway, nearly eliminating traffic impacts to Route 9.

As shown in the short movie below, once the new bridge superstructure was ready, MassDOT needed to demolish the old bridge and install new portions of the center pier and abutments. On Sunday morning, all preparations were complete. At 5:00 AM, four multi-axle machines called Self-Propelled Modular Transporters (or SPMTs) rumbled to life from their position underneath the new bridge superstructure. They moved in unison, carrying the 530-ton bridge from the cloverleaf onto the Cedar Street ramp. Then, at 8:15, the SPMTs’ many wheels rotated 90 degrees, and the bridge moved smoothly down the ramp onto Route 9 as the crowd watched, amazed. The wheels rotated again, and the bridge moved down Route 9, arriving at the pier and abutments at 9:30. The SPMTs held the bridge above the substructure until the early afternoon, when it was lowered into place.

Crews worked throughout the night to prepare to reopen the bridge. Temporary lane markings are in place and one sidewalk is open for pedestrians. Crews will continue to put the finishing touches on the bridge throughout the month, during off-peak hours. This work includes installing architectural pilasters, final paving and lane marking, completion of sidewalks, and installing signs.

 

Written By:

Recent Posts

Boston: Plan Ahead for I-90 Lane Restrictions posted on Jul 23

Boston: Plan Ahead for I-90 Lane Restrictions

MassDOT on Sunday, July 27 at 9:00pm will begin work to improve the median and Commonwealth Avenue Bridge substructure on Interstate 90 in Boston. Beginning Sunday night at 9:00pm and lasting for approximately six months, the left lanes in both Eastbound and Westbound directions on   …Continue Reading Boston: Plan Ahead for I-90 Lane Restrictions

Methuen Rotary Project: Travel Impacts posted on Jul 22

Methuen Rotary Project: Travel Impacts

MassDOT has scheduled upcoming lane closures as part of the Methuen Rotary Reconstruction Project.  Beginning on Monday, July 28, 2014 until further notice, the I-93 breakdown lane will be closed from Exit 46 – Routes 110/113 to Exit 47 – Pelham St. on I-93 Northbound   …Continue Reading Methuen Rotary Project: Travel Impacts

Tobin Bridge: All-Electronic Tolling Begins Monday, July 21 posted on Jul 18

Tobin Bridge: All-Electronic Tolling Begins Monday, July 21

Effective Monday, July 21, prior to the morning commute, tolling on the Tobin Bridge will convert to the all-electronic format. The new toll system will eliminate the need for customers to pay the toll in cash. The system is equipped to read E-ZPass transponders for   …Continue Reading Tobin Bridge: All-Electronic Tolling Begins Monday, July 21