Whittier Bridge 3The Patrick-Murray Administration’s Whittier Bridge Project on Interstate 95 in Salisbury, Newburyport and Amesbury is among 14 infrastructure projects nationwide selected by the Obama Administration for an expedited permitting and environmental review process designed to move projects as quickly as possible from concept to construction and completion.

The estimated $285 million design-build project is one of the largest in the Patrick-Murray Administration’s historic Accelerated Bridge Program to repair or replace structurally deficient bridges.  

The project will replace the existing 57-year old six-lane bridge over the Merrimack River with a new eight-lane structure that will also include bicycle and pedestrian lanes.

The Obama Administration announcement calls for accelerated permit review and approval within six months for the Whittier Bridge project.  Following an extensive public outreach process, MassDOT submitted the required Environmental Assessment/Draft Environmental Impact Report to the Federal Highway Administration (FHWA) for review in June 2011. 

The expedited review process is expected to allow the project to be advertised for bid in spring 2012. 

The Whittier Bridge project will also include extensive roadway widening construction.  A minimum of three lanes in each direction will be maintained during the peak traffic hours. The project will be designed to minimize right-of-way and environmental impacts.

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour