Post Content

Mode Shift Graphic
Secretary and CEO Richard Davey in October announced MassDOTs mode shift goal to triple the distance traveled by our customers through bicycling, transit and walking.  That goal now joins other goals incorporated into MassDOT's GreenDOT Implementation Plan with tasks and indicators.   

MassDOT established the goal to build a more efficient transportation system where fewer of our customers depend on driving alone to get where they are going.  We want to reduce greenhouse gas emissions from the transportation system and support better public health outcomes by working to give our customers more healthy travel options.

MassDOT will measure our progress on this ambitious mode shift goal using Personal Miles Traveled-distances traveled by all our customers for bicycling, driving, transit and walking in a one year period.  It also measures all the trips taken by our customers, not just work trips which are often the focus in transportation planning.  Measuring the distance traveled by each mode allows MassDOT to see strategic opportunities to improve the travel options for our customers, strengthen the relationship between land use and transportation planning, and draw a link to greenhouse gas emissions.  Goal numbers are listed below.

Year                    Bicycling PMT    Transit PMT    Walking PMT    Total
2010 (baseline)         150.4m                1.83b                101.1m            2.08b
2020 (benchmark)    330.0m                3.99b                223.9m            4.55b
2030 (goal year)        516.m                 5.93b                333.6m            6.78b

Personal Miles Traveled as the goal measurement is effective and maximizes resources available to MassDOT by using data that is already collected from the Federal Highway Administration’s Highway Performance Management System, Federal Transit Administration’s National Transit Database, and an estimation of bicycling and walking using data from the US Census Bureau’s American Community Survey. 
Check out MassDOT’s GreenDOT web page for the Implementation Plan and more information.

Written By:

Recent Posts

Casey Arborway Project Public Meeting Set posted on Jun 24

Casey Arborway Project Public Meeting Set

MassDOT has scheduled a fourth Casey Arborway Project Construction Update Meeting as follows: Wednesday, June 29, 6:30-8:30 PM, Boston English High School Auditorium 144 McBride Street, Jamaica Plain The purpose of this meeting will be to provide the community with an update on the progress   …Continue Reading Casey Arborway Project Public Meeting Set

Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration posted on Jun 23

Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration

MassDOT announced that the restoration of the iconic “salt and pepper” towers of the historic Longfellow Bridge will be complete in late July. The downstream towers have been replaced on the bridge, and barges are transporting the last stones for installation on them. The capstones   …Continue Reading Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration

New Tunnels Gantry Infrastructure to be Installed posted on Jun 22

New Tunnels Gantry Infrastructure to be Installed

MassDOT has announced that new infrastructure for two vertical gantry supports on the East Boston sides of the Sumner and Callahan Tunnels will begin to be installed late tonight, June 22.  Installation work will continue during off-peak hours during the next several days with gantries   …Continue Reading New Tunnels Gantry Infrastructure to be Installed