Freetown Route 24 Exit 8B, January 2012MassDOT's Fall River- Freetown Route 24 Interchange 8B project and the TranSystems firm received the 2012 Gold Award for Outstanding Design Excellence by ACEC, the American Council of Engineering Companies of Massachusetts.

The $35 million project completed and opened in January 2012 created a new exit and interchange, 8B, between the existing exits 8 and 9 on Route 24 in Freetown, funded by the federal American Recovery and Reinvestment Act (ARRA).

The project will reduce congestion at exits 8, 9 and South Main Street while providing access to the new Fall River Executive Park.

The project work began in early 2010 and was completed on schedule in less than two years. To speed construction and minimize the disruption to the traveling public, MassDOT used an expedited design/build approach to construction management. 

In addition, MassDOT's 2011 Accelerated Bridge Program project, 93Fast14, and the Tetra Tech firm received the ACEC Grand Conceptor Award.  The project replaced 14 bridge superstructures along I-93 in Medford during just 10 summer weekends in 2011.

 

Written By:

Recent Posts

Fore River Bridge Project Milestone posted on Jul 29

Fore River Bridge Project Milestone

The Fore River Bridge Replacement Project in Quincy-Weymouth continues during the summer of 2014 with installation of the permanent bridge components along with a new milestone: arrival of the new bridge steel sections. The view above shows the progress made at the Quincy tower location.   …Continue Reading Fore River Bridge Project Milestone

Green Line Extension: Public Meeting July 31 posted on Jul 28

Green Line Extension: Public Meeting July 31

A City of Somerville and MBTA Green Line Extension Public Meeting regarding Medford Street Bridge construction has been scheduled for the following: Thursday, July 31, 6:00pm, Public Safety Building, 220 Washington Street, Somerville. Green Line Extension construction is underway and will involve periodic traffic impacts   …Continue Reading Green Line Extension: Public Meeting July 31

MBTA: New WiFi System Announced posted on Jul 24

MBTA: New WiFi System Announced

Under a new license agreement signed today by MBTA General Manager Beverly Scott, a state-of-the-art WiFi system will be installed throughout the MBTA’s sprawling network of fourteen Commuter Rail lines. At no cost to the MBTA or its customers, inMOTION Wireless, Inc. will build a   …Continue Reading MBTA: New WiFi System Announced