Post Content

Bates Bridge, Haverhill-Groveland, March 2011 The ongoing work to build a new Bates Bridge over the Merrimack River in Haverhill and Groveland will be making visible progress in spring 2011.

The $49.7 million project is building a new bridge located approximately 60 feet downstream from the existing bridge.  The existing bridge carrying Routes 97/113 over the river remains open during construction. The replacement bridge will have a movable span similar to the existing bridge.  In addition to the new bridge, the project will move and reconstruct the approach roadways in Haverhill and Groveland, including traffic signal and other improvements in both communities.

In recent days and weeks, the contractor working from two barges installed cofferdams to allow for work in building the new bridge drilled shaft foundations and concrete piers.  A cofferdam is an enclosure within the water area constructed to allow water to be pumped out to create a dry work environment. In addition to the bridge foundation work, which will become visible in the coming months, overhead and underground utility relocation work also continues.

The major MassDOT bridge project is scheduled for completion in early 2014. 

Written By:

Recent Posts

July 4th Holiday Services Update posted on Jun 30

July 4th Holiday Services Update

MassDOT encourages safe travel during the upcoming July 4 holiday weekend.  Before you drive, check our live Traffic Cameras web page to view current conditions. Traffic is especially heavy at the I-84 interchange at Exit 9 in Sturbridge on the day before the holiday and   …Continue Reading July 4th Holiday Services Update

MassDOT Board Approves Contract for 325 New MBTA Buses posted on Jun 29

MassDOT Board Approves Contract for 325 New MBTA Buses

The MassDOT Board of Directors today approved a contract for the manufacture and delivery of 325 new state-of-the-art replacement buses for the MBTA fleet. “This is a major step in the process in modernizing the MBTA’s bus fleet and provides an important resource for millions   …Continue Reading MassDOT Board Approves Contract for 325 New MBTA Buses

Medford Cradock Bridge: I-93 Route 16 Westbound Ramp Closure posted on Jun 26

MassDOT is scheduled to close the I-93 Route 16 Westbound off ramp on Monday, June 29, at 7:00 AM to begin construction on the Cradock Bridge Project in Medford. The off ramp is scheduled to be closed for the duration of the project through approximately   …Continue Reading Medford Cradock Bridge: I-93 Route 16 Westbound Ramp Closure