Post Content

Bates Bridge, Haverhill-Groveland, March 2011 The ongoing work to build a new Bates Bridge over the Merrimack River in Haverhill and Groveland will be making visible progress in spring 2011.

The $49.7 million project is building a new bridge located approximately 60 feet downstream from the existing bridge.  The existing bridge carrying Routes 97/113 over the river remains open during construction. The replacement bridge will have a movable span similar to the existing bridge.  In addition to the new bridge, the project will move and reconstruct the approach roadways in Haverhill and Groveland, including traffic signal and other improvements in both communities.

In recent days and weeks, the contractor working from two barges installed cofferdams to allow for work in building the new bridge drilled shaft foundations and concrete piers.  A cofferdam is an enclosure within the water area constructed to allow water to be pumped out to create a dry work environment. In addition to the bridge foundation work, which will become visible in the coming months, overhead and underground utility relocation work also continues.

The major MassDOT bridge project is scheduled for completion in early 2014. 

Written By:

Recent Posts

Fore River Bridge Project Milestone posted on Jul 29

Fore River Bridge Project Milestone

The Fore River Bridge Replacement Project in Quincy-Weymouth continues during the summer of 2014 with installation of the permanent bridge components along with a new milestone: arrival of the new bridge steel sections. The view above shows the progress made at the Quincy tower location.   …Continue Reading Fore River Bridge Project Milestone

Green Line Extension: Public Meeting July 31 posted on Jul 28

Green Line Extension: Public Meeting July 31

A City of Somerville and MBTA Green Line Extension Public Meeting regarding Medford Street Bridge construction has been scheduled for the following: Thursday, July 31, 6:00pm, Public Safety Building, 220 Washington Street, Somerville. Green Line Extension construction is underway and will involve periodic traffic impacts   …Continue Reading Green Line Extension: Public Meeting July 31

MBTA: New WiFi System Announced posted on Jul 24

MBTA: New WiFi System Announced

Under a new license agreement signed today by MBTA General Manager Beverly Scott, a state-of-the-art WiFi system will be installed throughout the MBTA’s sprawling network of fourteen Commuter Rail lines. At no cost to the MBTA or its customers, inMOTION Wireless, Inc. will build a   …Continue Reading MBTA: New WiFi System Announced