Post Content

CommAve_MsthdThe Massachusetts Department of Transportation has announced that there will be various overnight impacts including lane closures on I-90 east and westbound as well as short-term detours of Commonwealth Avenue east and westbound in the area of the Commonwealth Avenue Bridge and the Boston University Bridge from Monday, July 22 through Saturday, August 10.

These impacts will take place during overnight hours only and will allow crews to safely and effectively conduct scheduled construction operations on the Commonwealth Avenue Bridge. The impacts will vary depending upon the work being conducted, but in general, the I-90 lane closures will take place from approximately 9 p.m. through 4:30 a.m., and the Commonwealth Avenue detours will take place from 1:30 a.m. to 4:30 a.m.

As always, work is being conducted in ways that minimize impacts on the traveling public and local community. For example, operations are being conducted during overnight hours to prevent travel disruptions.

These impacts are associated with the larger bridge replacement project and are necessary to conduct final scheduled construction activities per project plans. People traveling through the impacted areas should be mindful of delays, reduce speed, and use caution.

Signage and messaging will be in place to notify drivers of these impacts. The schedule for this work is weather dependent and subject to change without notice.

Written By:

Tags:

Recent Posts

Allston Multimodal Project Next Step: “Notice of Intent” to initiate NEPA process posted on Oct 18

Allston Multimodal Project Next Step: “Notice of Intent” to initiate NEPA process

MassDOT is announcing that the Federal Highway Administration today published in the Federal Register the “Notice of Intent” for the Allston Multimodal Project. This action initiates the National Environmental Policy Act (NEPA) process via a Draft Environmental Impact Statement (DEIS) under the One Federal Decision,   …Continue Reading Allston Multimodal Project Next Step: “Notice of Intent” to initiate NEPA process

MBTA Commuter Rail Weekday Service Pilot Between Boston and Foxborough Begins October 21 posted on Oct 18

MBTA Commuter Rail Weekday Service Pilot Between Boston and Foxborough Begins October 21

On Monday, October 21, the weekday Commuter Rail service pilot between Boston and Foxboro Station and a reverse commute fare will begin. This one-year service pilot offers ten round-trip weekday trains between Foxborough and Boston via the Fairmount and Franklin Lines. The service and special   …Continue Reading MBTA Commuter Rail Weekday Service Pilot Between Boston and Foxborough Begins October 21

Somerville: Washington Street Bridge/Underpass to Remain Closed through Winter posted on Oct 10

Somerville: Washington Street Bridge/Underpass to Remain Closed through Winter

The MBTA announced a schedule change for the Washington Street Bridge/Underpass that will extend the closure through the winter but will accelerate the permanent reopening of the underpass by five months. Original closure plans for the Washington Street Bridge/Underpass near McGrath Highway in East Somerville   …Continue Reading Somerville: Washington Street Bridge/Underpass to Remain Closed through Winter