Post Content

Boston, Dorchester Avenue, Peabody Square, December 3, 2010 Sq1 With spring approaching, MassDOT contractors are ready to resume work starting Monday, February 28 at several locations as part of the $15.6 million Dorchester Avenue project in Boston, funded by the American Recovery and Reinvestment Act (ARRA). 

The Dorchester Avenue project began in spring 2010 and will be completed in fall 2012, improving safety and mobility at four major intersections along the Dorchester Avenue corridor: Andrew Square, Glover's Corner, Fields Corner and Peabody Square. An additional 11 intersections will receive traffic signal equipment upgrades and interconnection and hardwire control to the City of Boston Traffic Management Center. All intersections will see accessibility and bicycle accommodation improvements.

The work schedule beginning Monday, February 28 through March 11, 7am-3pm weekdays, includes installation of traffic conduit and planter walls in the Gibson Street, Park Street, and Andrew Square locations.  Watch for lane closures or detours in those areas.

As always, parking is not allowed in the work zones between 7am and 4pm. 

Learn more at the MassDOT Dorchester Avenue Project on the web.  An update is sent via email to the community and added to project website every two weeks highlighting a general description of work locations, activities and hours.

Written By:

Recent Posts

Casey Arborway Project Public Meeting Set posted on Jun 24

Casey Arborway Project Public Meeting Set

MassDOT has scheduled a fourth Casey Arborway Project Construction Update Meeting as follows: Wednesday, June 29, 6:30-8:30 PM, Boston English High School Auditorium 144 McBride Street, Jamaica Plain The purpose of this meeting will be to provide the community with an update on the progress   …Continue Reading Casey Arborway Project Public Meeting Set

Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration posted on Jun 23

Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration

MassDOT announced that the restoration of the iconic “salt and pepper” towers of the historic Longfellow Bridge will be complete in late July. The downstream towers have been replaced on the bridge, and barges are transporting the last stones for installation on them. The capstones   …Continue Reading Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration

New Tunnels Gantry Infrastructure to be Installed posted on Jun 22

New Tunnels Gantry Infrastructure to be Installed

MassDOT has announced that new infrastructure for two vertical gantry supports on the East Boston sides of the Sumner and Callahan Tunnels will begin to be installed late tonight, June 22.  Installation work will continue during off-peak hours during the next several days with gantries   …Continue Reading New Tunnels Gantry Infrastructure to be Installed