Post Content

I-90 Median Project Asphalt Removal, August 25, 2014MassDOT contractors in August and September continue the preparation work to improve the median and Commonwealth Avenue Bridge substructure on Interstate 90 in Boston.

The left lanes in both Eastbound and Westbound directions on I-90 from west of the Prudential tunnel to the Commonwealth Avenue Bridge are closed to traffic in order to create work zones for substructure rehabilitation work and to reconstruct the I-90 median. Closure of the right lanes in both directions to complete the substructure work for the Commonwealth Avenue Bridge project will follow the reopening of the left lanesTo ensure safe merging distance on I-90 Eastbound leading up to the lane closure, one lane of the on-ramp is closed from Interchange 20.

Three lanes of traffic will be maintained in each direction on I-90 Eastbound and Westbound during peak hours. Short-term nighttime and weekend closures of an additional lane on I-90 Eastbound and Westbound will take place nightly.

Work to be performed throughout this project will include rehabilitation of the east and west abutments, as well as major rehabilitation of the east and west piers and reconstruction of the I-90 median.

Work to date in August includes installation of temporary barrier and digging test pits associated with the construction of the new foundation for the Commonwealth Avenue bridge.  Additional work includes removal of guardrail and median along with pavement saw-cutting adjacent to the temporary barrier, excavation of the existing asphalt down to the top of the footing of the existing piers as shown above, and preparation for installation of the temporary earth support needed for the shoring towers that will be used to support the bridge deck.

Work in the next few weeks will include installation of earth support on the eastbound side of I-90. The current work prepares the subsurface for the shoring towers and a jacking system to keep the bridge deck in place to allow foundation work to be done without affecting the street above.  Expect to see the shoring and jacking system set up in the closed travel lane.

The project-required lane closures causing congestion in the I-90 Allston/Brighton tolls area and at the Interchange 20 on-ramp to I-90 eastbound are the result of traffic management plans that take into account area constraints with the physical, available right-of-way and close proximity to the commuter rail lines. The closures allow the project to be completed safely and on schedule. MassDOT will continue to monitor traffic impacts and make adjustments as necessary that continue to ensure safe travel in the work area.

The project will be ongoing throughout the next twelve months leading to the replacement of the Commonwealth Avenue Bridge deck over I-90 which is scheduled to begin in late 2015.

Written By:

Recent Posts

Take the Clean Air Challenge! Join Us September 22-26 posted on Sep 18

Take the Clean Air Challenge! Join Us September 22-26

Massachusetts travelers will improve air-quality by choosing more sustainable transportation options during the Massachusetts Clean Air Challenge (formerly Car-Free Week). This year, Massachusetts challenges you to explore your commuting options and Shift Your Mode from September 22nd-26th. By trying greener modes including carpooling, vanpooling, bicycling,   …Continue Reading Take the Clean Air Challenge! Join Us September 22-26

MBTA Silver Line to Chelsea Approved posted on Sep 17

MBTA Silver Line to Chelsea Approved

The MassDOT Board of Directors today approved a construction contract to extend the MBTA’s increasingly popular Silver Line from East Boston to Chelsea. A project funded entirely by Governor Deval Patrick’s 2013 Transportation Finance Plan, the Silver Line will be extended past the Seaport to   …Continue Reading MBTA Silver Line to Chelsea Approved

2014 Moving Together Conference: Register Today! posted on Sep 17

2014 Moving Together Conference: Register Today!

MassDOT’s 2014 Moving Together Conference will bring together leaders working to advance healthy transportation. Are you part of the conversation that will determine the future of transportation in Massachusetts? Please join us and let your voice be heard.  The conference is scheduled as follows: Thursday,   …Continue Reading 2014 Moving Together Conference: Register Today!