Post Content

Burns Bridge Demolished, May 29, 2014A Patrick Administration Accelerated Bridge Program “mega project” has reached another milestone in June.   As of the week of June 2, demolition of the old Kenneth F. Burns Memorial Bridge in Worcester-Shrewsbury is complete and construction of the second half of its replacement is underway.

Work over the next several weeks into summer 2014 will include completion of new sidewalks and landscaping, driving 36-inch pipe piles at two piers, and forming and pouring concrete for the west abutment. Remaining shallow spots from the old bridge will be dredged.

As of early March, traffic completely shifted to the first half of the new Kenneth F. Burns Memorial Bridge, four months ahead of schedule. All traffic is riding on the new bridge’s concrete deck. A permanent asphalt surface will be installed prior to project completion.

With the old bridge demolished, the second half of the new one will be built in the same approximate location. When complete, the new Kenneth F. Burns Bridge will offer three lanes in both directions and dedicated turning lanes, along with improved bicycle and pedestrian accommodations.

The Kenneth F. Burns Memorial Bridge is one of the Accelerated Bridge Program projects in the eight-year, $3 billion effort to reduce the number of structurally deficient bridges in Massachusetts.  For more information, please visit the project website, www.mass.gov/massdot/kenburnsbridge.

 

Written By:

Recent Posts

All Electronic Tolling Update: Travel Times, Next Phase Work posted on Dec 7

All Electronic Tolling Update: Travel Times, Next Phase Work

MassDOT is pleased to announce that it is continuing the process of road reconstruction and toll plaza infrastructure demolition activities following the implementation of the All Electronic Tolling (AET) program on October 28 on I-90 between New York to Boston. “All Phase One toll plaza   …Continue Reading All Electronic Tolling Update: Travel Times, Next Phase Work

MassDOT: Plan Ahead During Winter Driving Season posted on Dec 7

MassDOT: Plan Ahead During Winter Driving Season

MassDOT advises travelers to drive safely and plan ahead as Winter driving season is now in full swing. Drivers are encouraged to lower their speeds during inclement weather and use the appropriate resources to make an informed decision regarding their travel plans. MassDOT strongly urges   …Continue Reading MassDOT: Plan Ahead During Winter Driving Season

Medford: Green Line Extension Public Meeting December 14 posted on Dec 5

Medford: Green Line Extension Public Meeting December 14

The Green Line Extension Project Interim Program Management Team will host a public meeting as follows: Wednesday, December 14, 6:30 to 8:30 PM, Medford City Hall, Council Chambers, 85 George P. Hassett Drive The purpose of the meeting will be to present a general update   …Continue Reading Medford: Green Line Extension Public Meeting December 14