OLYMPUS DIGITAL CAMERAOne of the Patrick Administration’s Accelerated Bridge Program “mega projects” continues to advance ahead of schedule in Worcester-Shrewsbury. As of early March, traffic has been completely shifted to the first half of the new Kenneth F. Burns Memorial Bridge. This milestone was reached four months ahead of schedule. All traffic is riding on the new bridge’s concrete deck. A permanent asphalt surface will be installed prior to project completion.

Demolition of the old Burns Bridge is currently underway and anticipated to last approximately four months. Pedestrians are reminded that the old bridge is now part of the project work zone and no longer provides a safe crossing between Worcester and Shrewsbury. Pedestirans should use the south sidewalk on the new bridge.

Once the old bridge has been demolished, the second half of the new one will be built in the same approximate location. When complete, the new Kenneth F. Burns Bridge will offer three lanes in both directions and dedicated turning lanes, along with improved bicycle and pedestrian accommodations.

The Kenneth F. Burns Memorial Bridge is one of the Accelerated Bridge Program projects in the eight-year, $3 billion effort to reduce the number of structurally deficient bridges in Massachusetts.  For more information, please visit the project website, www.mass.gov/massdot/kenburnsbridge.

Written By:

Recent Posts

MassDOT, Boston Harbor Now Present Proposed Ferry Site Short List to Seaport Economic Council posted on Dec 11

MassDOT, Boston Harbor Now Present Proposed Ferry Site Short List to Seaport Economic Council

Members of the Seaport Economic Council convened today and were briefed on a dozen sites which have been identified by stakeholders as having the best potential for new or expanded ferry service.  As part of the ongoing Boston Harbor Water Transportation Study, routes between these   …Continue Reading MassDOT, Boston Harbor Now Present Proposed Ferry Site Short List to Seaport Economic Council

RMV New Steps: More Customers Eligible for Online Transactions posted on Dec 11

RMV New Steps: More Customers Eligible for Online Transactions

The Massachusetts Registry of Motor Vehicles (RMV) is taking steps to allow more customers the opportunity to renew a driver’s license or ID card online. The RMV has extended the length of time a customer can use a license photo from 9 years to 14   …Continue Reading RMV New Steps: More Customers Eligible for Online Transactions

MassDOT Continuing Snow and Ice Operations posted on Dec 9

MassDOT Continuing Snow and Ice Operations

MassDOT is continuing its snow and ice removal operations throughout Saturday evening and into the overnight hours and is continuing to remind members of the public to minimize travel if possible, exercise safe driving behavior, and make safe and informed decisions before heading out onto   …Continue Reading MassDOT Continuing Snow and Ice Operations