Post Content

Boston, Chelsea Street Bridge 1, March 15, 2012Construction crews are in the final phase of work in the Chelsea Street bridge replacement project. The bridge was closed to traffic in June 2011 to allow crews to demolish the existing bridge and install the remaining portions of the new bridge. 

The $125.3 million project will improve the efficiency and operation of the bridge for vehicle traffic while significantly enhancing safe navigation of the Chelsea River channel by maritime vessels.

Recent work includes removing the existing piers and protective fender system and installing the new bridge joints and safety barrier.  MassDOT expanded the work to construct new bulkheads on the sides of the channel to prepare the area for the Army Corp of Engineers to widen the channel. 

The work taking place requires coordination with the use of the channel by the vessels that supply a significant portion of heating oil, gasoline and jet fuel throughout New England. 

The current work must be completed while the bridge is closed to vehicular traffic.  To minimize impacts, MassDOT and project stakeholders extended the closure of the bridge so that the work could occur on a continuous basis.  Crews are working double shifts, seven days a week. 

The new bridge is expected to be ready to reopen to vehicular traffic in late April.

Written By:

Recent Posts

Fore River Bridge Project Milestone posted on Jul 29

Fore River Bridge Project Milestone

The Fore River Bridge Replacement Project in Quincy-Weymouth continues during the summer of 2014 with installation of the permanent bridge components along with a new milestone: arrival of the new bridge steel sections. The view above shows the progress made at the Quincy tower location.   …Continue Reading Fore River Bridge Project Milestone

Green Line Extension: Public Meeting July 31 posted on Jul 28

Green Line Extension: Public Meeting July 31

A City of Somerville and MBTA Green Line Extension Public Meeting regarding Medford Street Bridge construction has been scheduled for the following: Thursday, July 31, 6:00pm, Public Safety Building, 220 Washington Street, Somerville. Green Line Extension construction is underway and will involve periodic traffic impacts   …Continue Reading Green Line Extension: Public Meeting July 31

MBTA: New WiFi System Announced posted on Jul 24

MBTA: New WiFi System Announced

Under a new license agreement signed today by MBTA General Manager Beverly Scott, a state-of-the-art WiFi system will be installed throughout the MBTA’s sprawling network of fourteen Commuter Rail lines. At no cost to the MBTA or its customers, inMOTION Wireless, Inc. will build a   …Continue Reading MBTA: New WiFi System Announced