Post Content

Boston, Chelsea Street Bridge 1, March 15, 2012Construction crews are in the final phase of work in the Chelsea Street bridge replacement project. The bridge was closed to traffic in June 2011 to allow crews to demolish the existing bridge and install the remaining portions of the new bridge. 

The $125.3 million project will improve the efficiency and operation of the bridge for vehicle traffic while significantly enhancing safe navigation of the Chelsea River channel by maritime vessels.

Recent work includes removing the existing piers and protective fender system and installing the new bridge joints and safety barrier.  MassDOT expanded the work to construct new bulkheads on the sides of the channel to prepare the area for the Army Corp of Engineers to widen the channel. 

The work taking place requires coordination with the use of the channel by the vessels that supply a significant portion of heating oil, gasoline and jet fuel throughout New England. 

The current work must be completed while the bridge is closed to vehicular traffic.  To minimize impacts, MassDOT and project stakeholders extended the closure of the bridge so that the work could occur on a continuous basis.  Crews are working double shifts, seven days a week. 

The new bridge is expected to be ready to reopen to vehicular traffic in late April.

Written By:

Recent Posts

South Coast Rail “Notice of Project Change” Public Meeting Scheduled posted on Apr 28

South Coast Rail "Notice of Project Change" Public Meeting Scheduled

MassDOT will hold a public meeting on the South Coast Rail “Notice of Project Change” as follows: Thursday, May 11, 6:30 p.m. Taunton High School auditorium, 50 Williams Street, Taunton. MassDOT filed an SCR Notice of Project Change (NPC) on March 15, 2017, to adopt   …Continue Reading South Coast Rail “Notice of Project Change” Public Meeting Scheduled

MBTA: Discover the Fairmount Commuter Rail Line May 8-21 posted on Apr 27

MBTA: Discover the Fairmount Commuter Rail Line May 8-21

Customers of the Fairmont Commuter Rail Line will travel free of charge for a two-week period in May. Customers will be able to board at station stops from Readville to South Stations and not pay a fare between Monday, May 8, and Friday, May 21.   …Continue Reading MBTA: Discover the Fairmount Commuter Rail Line May 8-21

MassDOT Proposed Capital Investment Plan Public Meetings Set posted on Apr 27

MassDOT Proposed Capital Investment Plan Public Meetings Set

MassDOT has announced a schedule of 12 public meetings in locations across the state to present and discuss the draft MassDOT Five-Year Capital Investment Plan (CIP) Update.  Public input received at the meetings from May 15 to May 24 will be considered before the CIP   …Continue Reading MassDOT Proposed Capital Investment Plan Public Meetings Set