Post Content

Chelsea Street Bridge 2012The new bridge carrying Chelsea Street over the Chelsea Creek at the Boston/Chelsea line is scheduled to reopen to traffic on Saturday, May 12. 

Construction crews are completing the last of the major work items necessary to allow the opening of the new bridge.  On March 15th, MassDOT projected the bridge would be ready for reopening in late April.  As final work continued, crews encountered unforeseen conditions associated with the complex underwater operations.  In addition, the schedule for the related channel dredging work being completed by the Army Corp of Engineers was delayed by the need to remove an abandoned sewer line beneath the bottom of the channel.

Final work items will continue after the bridge is opened to traffic on May 12, requiring overnight closures during May and early June that will not affect weekday commuter traffic.  Additional work will be completed during the day after the morning commute with at least one lane of traffic open in each direction. 

The historic $125.3 million project will improve the efficiency and operation of the bridge for vehicle traffic and for critical maritime vessels to safely navigate the channel.

MassDOT appreciates the continued patience that those affected by the closure of the bridge and the construction activities have shown throughout the duration of the project.

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour