Post Content

Chelsea Street Bridge 2012The new bridge carrying Chelsea Street over the Chelsea Creek at the Boston/Chelsea line is scheduled to reopen to traffic on Saturday, May 12. 

Construction crews are completing the last of the major work items necessary to allow the opening of the new bridge.  On March 15th, MassDOT projected the bridge would be ready for reopening in late April.  As final work continued, crews encountered unforeseen conditions associated with the complex underwater operations.  In addition, the schedule for the related channel dredging work being completed by the Army Corp of Engineers was delayed by the need to remove an abandoned sewer line beneath the bottom of the channel.

Final work items will continue after the bridge is opened to traffic on May 12, requiring overnight closures during May and early June that will not affect weekday commuter traffic.  Additional work will be completed during the day after the morning commute with at least one lane of traffic open in each direction. 

The historic $125.3 million project will improve the efficiency and operation of the bridge for vehicle traffic and for critical maritime vessels to safely navigate the channel.

MassDOT appreciates the continued patience that those affected by the closure of the bridge and the construction activities have shown throughout the duration of the project.

Written By:

Recent Posts

MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2 posted on Jul 29

MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2

The MBTA has scheduled necessary track maintenance activities on the Orange Line for this weekend, Saturday, August 1st and Sunday, August 2nd. Weekend service will be suspended between Forest Hills and Ruggles Stations. During the suspension of service, work crews will remove and replace rail   …Continue Reading MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2

Longfellow Bridge: August Closures Update posted on Jul 29

Longfellow Bridge: August Closures Update

The Longfellow Bridge Rehabilitation Project moves forward with demolition work that will require bridge closures. MassDOT’s contractor, White-Skanska-Consigli JV (WSC), will periodically close the Longfellow Bridge to all vehicular traffic beginning on Saturday, August 1 through Friday, August 21. The closures are necessary to safely   …Continue Reading Longfellow Bridge: August Closures Update

Green Line Extension Community Outreach Event posted on Jul 29

Green Line Extension Community Outreach Event

The Green Line Extension Project team including contractor Barletta Heavy Division this week participated in a touch-a-truck event with the Power Kids summer enrichment program in Medford. Approximately 60 youth from the Power Kids program grades K-11 had an up close view of the construction   …Continue Reading Green Line Extension Community Outreach Event