Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

MassDOT, MAPFRE/Commerce Insurance Observe Teen Driver Safety Week posted on Oct 23

MassDOT, MAPFRE/Commerce Insurance Observe Teen Driver Safety Week

  Guest Blog Written By Patrick McDonald, CPCU, AIM, AIS Executive Vice President – Business & Clients MAPFRE | Commerce Insurance At MAPFRE | Commerce Insurance, we recognize that Massachusetts teen drivers are at risk and need extra care, support and guidance before getting behind   …Continue Reading MassDOT, MAPFRE/Commerce Insurance Observe Teen Driver Safety Week

I-90 Allston Interchange Project Public Meeting November 5 posted on Oct 23

I-90 Allston Interchange Project Public Meeting November 5

The MassDOT I-90 Allston Interchange Improvement Project task force has scheduled a public meeting to review the latest information about the project: Wednesday, November 5, 6pm, Fiorentino Community Center, 123 Antwerp Street, Allston The I-90 Allston viaduct is nearing the end of its useful lifespan   …Continue Reading I-90 Allston Interchange Project Public Meeting November 5

Governor Patrick: Recommendation to Build MBTA Subway Cars in Massachusetts posted on Oct 21

Governor Patrick: Recommendation to Build MBTA Subway Cars in Massachusetts

Governor Deval Patrick today announced that the MBTA will present to the MassDOT Board of Directors the recommended company to manufacture and deliver 284 new subway cars for the Red and Orange Lines, replacing decades-old vehicles. Joined by MassDOT Secretary & CEO Richard A. Davey   …Continue Reading Governor Patrick: Recommendation to Build MBTA Subway Cars in Massachusetts