Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

MassDOT Launches Two Improved Traffic Websites posted on Jul 1

MassDOT Launches Two Improved Traffic Websites

MassDOT today announced the relaunch of two improved live traffic websites to provide motorists with better access to real-time traffic information, including access to more than 350 live streaming traffic cameras across the Commonwealth. The enhancements are part of MassDOT’s effort to provide drivers with information   …Continue Reading MassDOT Launches Two Improved Traffic Websites

Fall River Milestone: New Route 79 Southbound Roadway Open posted on Jul 1

Fall River Milestone: New Route 79 Southbound Roadway Open

MassDOT contractors in Fall River have reached another milestone with the opening of the new Route 79 southbound roadway. The temporary off-ramp from Route 79 South to South Davol Street has been closed. Southbound traffic from Davol Street will continue to use South Davol Street   …Continue Reading Fall River Milestone: New Route 79 Southbound Roadway Open

Plan Ahead for July 4 Travel posted on Jun 29

Plan Ahead for July 4 Travel

MassDOT encourages the public to travel safely on the 4th of July holiday weekend, drive during lower volume times on major roadways, and use public transportation where possible. MassDOT suspends all construction work on major arterial roadways from 12 p.m., Friday, July 1, through the   …Continue Reading Plan Ahead for July 4 Travel