Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

MBTA: Weekend Service on 3 Commuter Rail Lines Begins December 27 posted on Dec 19

MBTA: Weekend Service on 3 Commuter Rail Lines Begins December 27

The restoration of weekend Commuter Rail service on three lines will begin next Saturday, December 27. The Kingston/Plymouth and Greenbush lines will see the return of Saturday and Sunday service and the Needham Line will resume Saturday service after a two year absence. “MassDOT is   …Continue Reading MBTA: Weekend Service on 3 Commuter Rail Lines Begins December 27

Fairhaven Bike Train Program Recognized posted on Dec 18

Fairhaven Bike Train Program Recognized

The Town of Fairhaven was recognized alongside the Massachusetts Safe Routes to School (SRTS) Program by Cape Cod’s NPR station, WCAI, for their bike train program. A bike train is a fun way for elementary and middle school students to get to school while being   …Continue Reading Fairhaven Bike Train Program Recognized

South Station Expansion: DEIR Comment Period Through December 24 posted on Dec 17

South Station Expansion: DEIR Comment Period Through December 24

Posted by:  Matthew Ciborowski, South Station Project Manager, MassDOT Office of Transportation Planning I was pleased to meet with more than 60 people who participated in an Open House and Hearing on the Draft Environmental Impact Report (DEIR) for the South Station Expansion project on   …Continue Reading South Station Expansion: DEIR Comment Period Through December 24