Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour