Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

Green Line Extension Station Design Meetings Set posted on Apr 27

Green Line Extension Station Design Meetings Set

MassDOT and the MBTA are hosting two public meetings this spring to provide an update on the design of four stations as part of the Green Line Extension project.  The meetings and stations in discussion are as follows: Thursday, May 14, 6:00 – 8:00 PM:   …Continue Reading Green Line Extension Station Design Meetings Set

MBTA Green Line First Countdown Signs Live in Newton posted on Apr 25

MBTA Green Line First Countdown Signs Live in Newton

Transportation Secretary Stephanie Pollack announced that the MBTA Green Line’s first countdown signs have been activated at Newton Centre and Newton Highlands Stations on the D branch. “These signs provide customers with additional information that they haven’t had before, making customers’ commutes more predictable,” said Secretary   …Continue Reading MBTA Green Line First Countdown Signs Live in Newton

Massachusetts Walk and Bike to School Day: May 6th posted on Apr 23

Massachusetts Walk and Bike to School Day: May 6th

The day is approaching quickly! On Wednesday, May 6th, thousands of elementary and middle school students will participate in hundreds of events within Massachusetts communities as they walk and bike to school. Massachusetts Walk and Bike to School Day is a statewide event through the   …Continue Reading Massachusetts Walk and Bike to School Day: May 6th