Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

Route 79/Braga Bridge Project Public Meeting Set posted on Apr 17

Route 79/Braga Bridge Project Public Meeting Set

Please join MassDOT at a public meeting for an update on construction progress on the Route 79/Braga Bridge Improvements Project, as follows: Wednesday, April 30, 6:30 pm to 8:30 pm, Heritage State Park Auditorium, 200 Davol Street, Fall River The meeting will include an opportunity   …Continue Reading Route 79/Braga Bridge Project Public Meeting Set

MBTA: New Locomotive Now in Service posted on Apr 16

MBTA: New Locomotive Now in Service

MBTA General Manager Dr. Beverly Scott today at Boston North Station welcomed the first of 40 new Commuter Rail locomotives as it was placed into service on the Haverhill Line.   To replace existing locomotives between 35 and 40 years old, the MBTA is procuring forty   …Continue Reading MBTA: New Locomotive Now in Service

Plan Ahead: Holiday Weekend Travel posted on Apr 16

Plan Ahead: Holiday Weekend Travel

MassDOT encourages travelers to plan ahead, travel safely, and use public transportation where possible during the upcoming holiday weekend. Heavy traffic is expected due to Easter Sunday observances and Patriot’s Day/Marathon Monday, April 21. The heaviest traffic congestion on I-90 during busy holiday weekends is   …Continue Reading Plan Ahead: Holiday Weekend Travel