Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

MassDOT Highlights Bicycle and Pedestrian Statewide Accomplishments posted on Feb 20

MassDOT Highlights Bicycle and Pedestrian Statewide Accomplishments

Throughout 2017, MassDOT worked to improve and increase the infrastructure for bicycle and pedestrian travel across the state, and those efforts were recognized nationally. In November, Massachusetts ranked the fourth most bicycle-friendly state in the nation by the League of American Bicyclists.  The report card   …Continue Reading MassDOT Highlights Bicycle and Pedestrian Statewide Accomplishments

MassDOT Innovation & Tech Transfer Exchange: April 10-11 posted on Feb 20

MassDOT Innovation & Tech Transfer Exchange: April 10-11

MassDOT’s annual Innovation & Tech Transfer Exchange transportation conference is set for April 10-11, DCU Center, Worcester. The Exchange is the largest Innovation and Mobility Exchange in Massachusetts. The 2018 event will include the Massachusetts Community Transportation Coordination Conference and feature a full-scale indoor Complete   …Continue Reading MassDOT Innovation & Tech Transfer Exchange: April 10-11

MassDOT Encourages Presidents’ Day Travelers to Plan Ahead posted on Feb 15

MassDOT Encourages Presidents' Day Travelers to Plan Ahead

MassDOT advises Presidents’ Day holiday travelers to plan ahead, review MassDOT travel “real time” tools and consider using public transportation if possible to travel between destinations. The public should note that on Monday, February 19, state offices are closed, Registry of Motor Vehicles service locations   …Continue Reading MassDOT Encourages Presidents’ Day Travelers to Plan Ahead