Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

MBTA: Next Phase of Red Line Winter Resiliency Improvements Approved posted on Jul 25

MBTA: Next Phase of Red Line Winter Resiliency Improvements Approved

The MBTA Fiscal and Management Control Board (FMCB) today unanimously approved the awarding of a $18.5 million construction contract for the next phase of Red Line Winter Resiliency improvements announced by the Baker-Polito Administration last year, amounting to $30.4 million total for infrastructure upgrades in   …Continue Reading MBTA: Next Phase of Red Line Winter Resiliency Improvements Approved

Methuen Rotary: New I-93 Northbound Ramp Opens July 30 posted on Jul 25

Methuen Rotary: New I-93 Northbound Ramp Opens July 30

MassDOT’s Methuen Rotary Interchange Reconstruction Project reaches a major milestone on Saturday, July 30, when the first new ramp of the reconstructed interchange opens to traffic. The new I-93 northbound on-ramp is located approximately 400 feet east of the current ramp. A new signal will   …Continue Reading Methuen Rotary: New I-93 Northbound Ramp Opens July 30

Longfellow Bridge: Next Stage of Construction to Begin in August posted on Jul 22

Longfellow Bridge: Next Stage of Construction to Begin in August

MassDOT’s contractor is scheduled to begin the next stage of construction on the Longfellow Bridge in August 2016 now that the MBTA Red Line trains have been moved to their new locations. In this stage, bridge rehabilitation work will occur under the MBTA outbound track.   …Continue Reading Longfellow Bridge: Next Stage of Construction to Begin in August