Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

MassDOT, MAPFRE: Highway Assistance Patrol posted on Aug 29

MassDOT, MAPFRE: Highway Assistance Patrol

Posted by: Patrick McDonald, CPCU, AIM, AIS, Executive Vice President – Business & Clients, MAPFRE Insurance MAPFRE Insurance sponsors the MassDOT Highway Assistance Patrol (HAP) program and reminds motorists that during Labor Day weekend many Massachusetts drivers will be taking their last vacations of the   …Continue Reading MassDOT, MAPFRE: Highway Assistance Patrol

A First in the State: MassDOT Uses New Construction Technique on Route 2/I-95 Project posted on Aug 28

A First in the State: MassDOT Uses New Construction Technique on Route 2/I-95 Project

From smaller projects to the largest, MassDOT uses the latest, proven innovative techniques. For the first time in the state, MassDOT is using precast, modular concrete abutments on the Route 2/I-95 Bridge Replacement Project. Accelerated Bridge Construction technologies, such as this one, reduce project duration   …Continue Reading A First in the State: MassDOT Uses New Construction Technique on Route 2/I-95 Project

Route 107 Corridor Public Meetings Scheduled posted on Aug 26

Route 107 Corridor Public Meetings Scheduled

Public Information Meetings for the Route 107 Corridor Study have been scheduled as follows: Wednesday, September 7, 6:00 PM to 8:00 PM, Lynn English High School, Auditorium, 50 Goodridge Street Tuesday, September 13, 6:00 PM to 8:00 PM, Collins Middle School, Auditorium, 29 Highland Avenue,   …Continue Reading Route 107 Corridor Public Meetings Scheduled