Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

Green Line Extension Public Meeting Set posted on Sep 2

Green Line Extension Public Meeting Set

The MBTA will hold a public meeting to discuss early construction elements of the Green Line Extension project that will begin this fall. The meeting is scheduled as follows: Thursday, September 18, 6:00-8:00pm, Holiday Inn, 30 Washington Street, Somerville Green Line Extension construction will be   …Continue Reading Green Line Extension Public Meeting Set

RMV: New Boston Branch Location, Low Number Lottery Drawing posted on Aug 28

RMV: New Boston Branch Location, Low Number Lottery Drawing

MassDOT Registrar of Motor Vehicles Celia J. Blue announced the annual low number license plate lottery drawing will be held on September 10 at the RMV’s soon-to-open new Boston branch, Haymarket Center at 136 Blackstone Street. “As we move our operations to a new Boston   …Continue Reading RMV: New Boston Branch Location, Low Number Lottery Drawing

Labor Day Weekend Travel: Plan Ahead! posted on Aug 27

Labor Day Weekend Travel: Plan Ahead!

MassDOT encourages motorists to plan ahead for safe travel during the upcoming Labor Day holiday weekend. Heaviest Labor Day traffic on I-90 is expected Thursday and Friday westbound and Monday afternoon-evening eastbound.  The number of toll transactions on the Turnpike from Weston to the New   …Continue Reading Labor Day Weekend Travel: Plan Ahead!