Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2 posted on Jul 29

MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2

The MBTA has scheduled necessary track maintenance activities on the Orange Line for this weekend, Saturday, August 1st and Sunday, August 2nd. Weekend service will be suspended between Forest Hills and Ruggles Stations. During the suspension of service, work crews will remove and replace rail   …Continue Reading MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2

Longfellow Bridge: August Closures Update posted on Jul 29

Longfellow Bridge: August Closures Update

The Longfellow Bridge Rehabilitation Project moves forward with demolition work that will require bridge closures. MassDOT’s contractor, White-Skanska-Consigli JV (WSC), will periodically close the Longfellow Bridge to all vehicular traffic beginning on Saturday, August 1 through Friday, August 21. The closures are necessary to safely   …Continue Reading Longfellow Bridge: August Closures Update

Green Line Extension Community Outreach Event posted on Jul 29

Green Line Extension Community Outreach Event

The Green Line Extension Project team including contractor Barletta Heavy Division this week participated in a touch-a-truck event with the Power Kids summer enrichment program in Medford. Approximately 60 youth from the Power Kids program grades K-11 had an up close view of the construction   …Continue Reading Green Line Extension Community Outreach Event