Post Content

Boston, Chelsea Street Bridge 2, February 17, 2012The Chelsea Street Bridge project continues in early 2012 with the new vertical lift structures and concrete bridge deck now completed and in place.  Current work, seen at left, includes demolition of piers from the old bridge under the new structure. 

To allow for the final work on this historic $125 million MassDOT project, the Chelsea Street Bridge over Chelsea Creek at the Boston/Chelsea line remains closed with detours in place.

The Chelsea Street Bridge project involves the replacement of a truss-type structure that spans 450 feet and will provide 175 feet of vertical clearance when raised.  The new bridge will include four lanes of traffic and two pedestrian sidewalks. 

This is the largest permanent lift bridge built in Massachusetts to date.  To accommodate the massive size and tight space constraints in the bridge area, MassDOT contractors used an innovative technique of launching the truss across the river.  The launching sequence of the truss bridge across the channel was carefully designed to minimize disruption of the navigation channel below.  This launch process was completed in November 2011.

After the launch was successfully completed, the project moved to the concrete pours of the 450 foot long bridge deck, which required the project to enclose and heat the bridge structure because of colder early winter weather.  The concrete pours were completed in late December 2011.

Project work now includes removing the old bridge piers below the new bridge.  The contractor is making significant progress and working seven days a week and 24 hours a day to remove the 5 piers, which include segments up to 40 feet below the river bottom. Work on the bridge itself includes installation of bridge joints, barrier, and other safety items. 

It is anticipated that all required work will be complete and allow a bridge opening to traffic by the end of April.  MassDOT will announce publicly an exact opening date in advance.

Written By:

Recent Posts

Community Transit Grant Applications Show Significant Increase posted on Mar 5

Community Transit Grant Applications Show Significant Increase

The MassDOT Rail & Transit Division’s Community Transit Grant Program for Fiscal Year 2016 has received more than 90 applications, a 50% increase compared to last year. Applications were due on March 2. The Community Transit Grant Program provides financial assistance through the Federal Transit   …Continue Reading Community Transit Grant Applications Show Significant Increase

Methuen Rotary I-93 Project Update posted on Mar 4

Methuen Rotary I-93 Project Update

MassDOT’s $66.4 million Methuen Rotary Reconstruction Project on I-93 at Routes 110 and 113 is moving forward during winter 2015. During the month of March, the following activities will continue on I-93 at Routes 110 and 113:   Removal of contaminated soil at mitigation area   …Continue Reading Methuen Rotary I-93 Project Update

MassDOT Aeronautics: 2015 Aviation Art Contest Winners posted on Mar 3

MassDOT Aeronautics: 2015 Aviation Art Contest Winners

The MassDOT Aeronautics Division held the Massachusetts State level judging of the 2015 International Aviation Art Contest, with this year’s theme, “World Air Games”. The World Air Games will be held in Dubai in 2015. During 12 days, spectators will see world class competitions and   …Continue Reading MassDOT Aeronautics: 2015 Aviation Art Contest Winners