Post Content

Craigie Bridge, Boston, January 17, 2011 Work continues through the winter on the Craigie Drawbridge Rehabilitation project, funded by the Patrick-Murray Administration's historic Accelerated Bridge Program to repair and replace structurally-deficient bridges across the Commonwealth.

During the past weekend, workers used a barge to deliver large pieces of the bridge and erected two of the bascule leafs using the crane seen at left. The crew was undeterred by cold and snowy conditions.

During January, the contractor is removing the temporary bridges and installing the new prefabricated bascule leaf.  Prefabricated sections of the bridge are moved onto the barge from an assembly and staging area upriver.  The same process will continue through February. 

To allow for the work, MassDOT on January 8 closed all inbound travel lanes on Route 28 southbound at the intersection of Land Boulevard for approximately 12 weeks.  The Craigie Drawbridge carries McGrath O’Brien Highway (Route 28) between Land Blvd. in Cambridge and Leverett Circle in Boston.

Traffic trying to access I-93 and Storrow Drive is  detoured east over the Gilmore (Prison Point) Bridge towards Bunker Hill Community College/City Square. Traffic heading to I-93 Northbound is directed left through Sullivan Square, while traffic trying to access I-93 Southbound and Route 1 via the Tobin Bridge is directed to turn right. Traffic traveling to the Charles Circle Area is detoured westbound down Land Boulevard to the Longfellow Bridge to cross the Charles River. Outbound traffic leaving Boston through Leverett Circle will be unaffected during this period. For more information on the Craigie Drawbridge Rehabilitation project, please see www.mass.gov/massdot/charlesriverbridges.

Written By:

Recent Posts

Fore River Bridge Project Milestone posted on Jul 29

Fore River Bridge Project Milestone

The Fore River Bridge Replacement Project in Quincy-Weymouth continues during the summer of 2014 with installation of the permanent bridge components along with a new milestone: arrival of the new bridge steel sections. The view above shows the progress made at the Quincy tower location.   …Continue Reading Fore River Bridge Project Milestone

Green Line Extension: Public Meeting July 31 posted on Jul 28

Green Line Extension: Public Meeting July 31

A City of Somerville and MBTA Green Line Extension Public Meeting regarding Medford Street Bridge construction has been scheduled for the following: Thursday, July 31, 6:00pm, Public Safety Building, 220 Washington Street, Somerville. Green Line Extension construction is underway and will involve periodic traffic impacts   …Continue Reading Green Line Extension: Public Meeting July 31

MBTA: New WiFi System Announced posted on Jul 24

MBTA: New WiFi System Announced

Under a new license agreement signed today by MBTA General Manager Beverly Scott, a state-of-the-art WiFi system will be installed throughout the MBTA’s sprawling network of fourteen Commuter Rail lines. At no cost to the MBTA or its customers, inMOTION Wireless, Inc. will build a   …Continue Reading MBTA: New WiFi System Announced