Post Content

Fairhaven Bridge, March 14, 2013MassDOT today detailed plans to replace the bridge decks that carry I-195 over River Avenue in Fairhaven near the New Bedford line, in four weekends within a six week period beginning on March 22.  

The rapid bridge construction technique using eight prefabricated bridge units will allow MassDOT to limit traffic disruptions and replace the deteriorated bridge decks before the busy spring and summer travel season begins.

“This replacement is part of the Accelerated Bridge Program that has allowed MassDOT to reduce the backlog of structurally deficient bridges statewide by 20%,” said MassDOT Highway Administrator Frank DePaola. “Here in Fairhaven, we are pleased to be able to address the structural issues and also improve the customer experience by drastically reducing both the construction schedule and traffic delays.”

At no time during construction will I-195 be closed completely to traffic. Drivers will follow a lane shift through the work zone, similar to the 93Fast14 project that allowed MassDOT to replace 14 I-93 bridges in ten weekends during the summer of 2011.

The deck replacement work will be performed in two phases. During the first phase, (I-195 Westbound work), two lanes of traffic will be maintained in both directions. During phase two (I-195 Eastbound work), there will be one travel lane heading eastbound with restricted access from Route 18 and Washburn Street during the weekend deck replacement. Ramp detours will be in place.  Two lanes of westbound traffic will remain open during phase two.

Using traditional construction methods and overnight roadway closures to replace the superstructure, the project would take 12 to 18 months to complete. The project cost is approximately $5 million.

The deck replacements are scheduled to be completed by April 29th with a project completion of June 14th, with the exact schedule weather dependent.

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour