Fitchburg, Bridge-in-a-Backpack, June 9, 2011 Governor Deval Patrick today joined administration officials, local legislators and construction workers at the Scott Reservoir Outlet bridge project in Fitchburg to highlight the use of innovative "Bridge-in-a-Backpack" construction technology.

This site is the first in Massachusetts to use the innovative technique and Massachusetts is the second state in the country to see it deployed. The bridge project is funded by the the Patrick-Murray Administration's historic Accelerated Bridge Program to repair or replace structurally-deficient bridges across the Commonwealth.

The project achieved a major milestone this week when the structural arches of the replacement bridge were installed. The arches, made of ultra-light composite material, were carried into place by a group of five workers without the help of expensive and potentially dangerous machinery.

MassDOT contractors anticipate substantial completion of the project by late July, just 70 days after the original closing of the bridge. The bridge will be re-opened to traffic no later than July 26th.

The "Bridge-in-a-Backpack" construction methodology has been proven to be safe for workers and cost efficient. Completed bridges are highly durable and weather resistant due to the unique materials used in construction.

The Accelerated Bridge Program is an unprecedented 8-year, $3 billion investment in the Commonwealth's bridges and workers. Already, the program has helped reduce the number of structurally deficient bridges by more than 15 percent.  In calendar year 2010, MassDOT projects created or sustained an estimated 30,000 jobs, a trend expected to continue throughout 2011.

Written By:

Recent Posts

Grafton, Millbury: I-90 Resurfacing Project Moves Forward posted on Apr 25

Grafton, Millbury: I-90 Resurfacing Project Moves Forward

MassDOT is continuing to move forward with a $13.6 million project to resurface and repair an 8-mile section of I-90 (the Massachusetts Turnpike) on both the eastbound and westbound sides in Millbury and Grafton. This project will have work completed in two phases: during the   …Continue Reading Grafton, Millbury: I-90 Resurfacing Project Moves Forward

MBTA: Strategic Plan Adopted posted on Apr 24

MBTA: Strategic Plan Adopted

The MBTA’s Fiscal and Management Control Board (FMCB) today approved an MBTA Strategic Plan, a document that fulfills the FMCB requirement in its enabling legislation that required development of such a plan. This plan serves as a blueprint for institutionalizing the objectives and strategies needed   …Continue Reading MBTA: Strategic Plan Adopted

Sumner Tunnel Toll Demolition Moving Forward posted on Apr 24

Sumner Tunnel Toll Demolition Moving Forward

MassDOT is moving forward with toll demolition and road reconstruction operations at the existing toll plaza at the entrance to the Sumner Tunnel in East Boston. Work-related logistical activities at the Sumner Tunnel began last week including marking utilities and installing temporary signage and the   …Continue Reading Sumner Tunnel Toll Demolition Moving Forward