Post Content

Fore River Bridge, Quincy Tower, August 29, 2013The Fore River Bridge Replacement Project construction continues into fall 2013 with installation of the permanent bridge foundation components moving ahead. At the Quincy tower location, drilled shafts have been completed and concrete pier caps set in place. Work continues on drilled shaft production for the Weymouth tower, sent at left, with 6 of the 12 drilled shafts placed and crews advancing the remaining 6.

A third shift added to the project in late July putting the worksite into 24-hour operation enhanced the production time line for Weymouth tower drilled shafts.  The third shift should conclude during the last week of September and project work hours will return to 7:00 am-11:00 pm.

Area residents are reminded that worker parking has been provided at 40 Cleverly Court, in the Fore River shipyard or elsewhere within the MassDOT right-of-way or easements and will not impact public streets at any point during the project.

Motorists should expect partial, offpeak lane closures later this fall for the excavation of test pits to locate subsurface utilities. This work is a required step to prepare for work in spring 2014.  Road approach wall renovations will begin late this year or in early 2014 but will not impact traffic on Route 3A.  There may be minor impacts on the frontage roads to either side of existing approach walls.

The Fore River Bridge Replacement Project is taking place under the Patrick Administration’s historic Accelerated Bridge Program to repair or replace structurally deficient bridges across Massachusetts.  To view Fore River Bridge Replacement Project updates, visit the project website.

Written By:

Recent Posts

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th posted on Jul 26

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

This is a reminder that the 2017 Construction Shutdown for the Commonwealth Avenue Bridge Replacement Project is beginning at 9:00 PM today, Wednesday July 26, and will continue through 5:00 AM on Monday, August 14. Please note the construction-related impacts below: For Pedestrians and Bicyclists:   …Continue Reading Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

Springfield: I-91 Viaduct Rehabilitation Progress Continues posted on Jul 24

Springfield: I-91 Viaduct Rehabilitation Progress Continues

MassDOT and its contractor, the Joint Venture of White-Schiavone (JV), continue to make progress on rehabilitation of the Interstate 91 Viaduct (I-91) through Springfield. The contractor completed reconstruction of the center lanes of the highway last fall, and began Stage 2 of construction in November   …Continue Reading Springfield: I-91 Viaduct Rehabilitation Progress Continues

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts posted on Jul 23

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts

MassDOT is reminding the public that travel impacts will begin next week throughout the Boston University/Saint Paul Street neighborhood of Boston along Commonwealth Avenue due to the Commonwealth Avenue Bridge Replacement Project. Drivers on Commonwealth Avenue, the BU Bridge and I-90 will see lane closings   …Continue Reading Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts