Post Content

Fore River Bridge, Quincy Tower, August 29, 2013The Fore River Bridge Replacement Project construction continues into fall 2013 with installation of the permanent bridge foundation components moving ahead. At the Quincy tower location, drilled shafts have been completed and concrete pier caps set in place. Work continues on drilled shaft production for the Weymouth tower, sent at left, with 6 of the 12 drilled shafts placed and crews advancing the remaining 6.

A third shift added to the project in late July putting the worksite into 24-hour operation enhanced the production time line for Weymouth tower drilled shafts.  The third shift should conclude during the last week of September and project work hours will return to 7:00 am-11:00 pm.

Area residents are reminded that worker parking has been provided at 40 Cleverly Court, in the Fore River shipyard or elsewhere within the MassDOT right-of-way or easements and will not impact public streets at any point during the project.

Motorists should expect partial, offpeak lane closures later this fall for the excavation of test pits to locate subsurface utilities. This work is a required step to prepare for work in spring 2014.  Road approach wall renovations will begin late this year or in early 2014 but will not impact traffic on Route 3A.  There may be minor impacts on the frontage roads to either side of existing approach walls.

The Fore River Bridge Replacement Project is taking place under the Patrick Administration’s historic Accelerated Bridge Program to repair or replace structurally deficient bridges across Massachusetts.  To view Fore River Bridge Replacement Project updates, visit the project website.

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour