Post Content

Fore River Bridge, Quincy, June 4, 2013Beginning during the week of June 24, a third shift will be added to the Fore River Bridge replacement project running from 11:00 PM to 7:00 AM, putting the project into 24-hour operation. The third shift is expected to last for approximately two weeks.

A third shift will address slower-than expected drilled shaft production combined with engineering requirements. To maintain shaft integrity and safely complete this important phase of construction, the third shift to allow work to continue uninterrupted. As has been noted during the outreach for the project to date, certain critical aspects of the bridge replacement project require 24-hour operation.

Work during the third shift will consist of operating the recirculating drill in the drilled shafts set in the bed of the Fore River. The drill will be situated on the temporary work trestles extending from the Weymouth and Quincy banks of the river. No other work is scheduled for the third shift and as such, noise levels will be below what abutters experience during the first and second shifts in accordance with the project’s noise control plan. The recirculating drill is a stationary piece of equipment and will be isolated to the temporary trestles; therefore motorists moving through the area will experience no traffic impacts. No additional trucks are required for the operation of the recirculating drill.

For questions or concerns regarding third shift or other construction at the Fore River Bridge site, please call 617-504-2924. This telephone number is operated by the White-Skanska design/build team and is live at all times when construction activities are underway.

Replacement of the Fore River Bridge is taking place under the Patrick-Murray Administration’s historic Accelerated Bridge Program to replace structurally deficient bridges throughout the Commonwealth. For more information, please contact Donald Dailey, donny.dailey@state.ma.us or 857-368-8902.  Visit the Fore River Bridge Replacement Project on the web: www.mass.gov/massdot/foreriverbridge.

Written By:

Recent Posts

Route 79/Braga Bridge Project Traffic Update posted on Oct 30

Route 79/Braga Bridge Project Traffic Update

MassDOT will begin implementing traffic changes for the next stage of construction for the Route 79/Braga Bridge Project on Wednesday, November 12. The following changes will be implemented in a phased approach through the middle of December: Vehicles on Route 79/138 (Broadway) bound for Interstate   …Continue Reading Route 79/Braga Bridge Project Traffic Update

RMV: Promise to Customers posted on Oct 28

RMV: Promise to Customers

Today, MassDOT Secretary & CEO Richard A. Davey and MassDOT Registrar of Motor Vehicles Celia J. Blue offered a 10 point promise to RMV customers. The reimagining effort comprises current, ongoing and future initiatives that the RMV has in development to better the Registry experience.   …Continue Reading RMV: Promise to Customers

November E-ZPass Sign Up: Chelsea, Everett posted on Oct 28

November E-ZPass Sign Up: Chelsea, Everett

MassDOT is encouraging motorists to join E-ZPass with All-Electronic Tolling now in place on the Tobin Bridge and expanding statewide within the next two years. The E-ZPass Street Team will be enrolling new customers in the E-ZPass throughout the Fall season. The E-ZPass Van schedule   …Continue Reading November E-ZPass Sign Up: Chelsea, Everett