haverhill-495-bridges-project-piledriving-1-november-2018Work is underway this fall on the $102 million project to replace the bridges that carry traffic on I-495 over the Merrimack River in Haverhill.

Early construction activities included clearing and erosion controls along I-495 including the median and areas adjacent to the I-495 northbound bridge and slopes.

Current construction activities for the new I-495 northbound bridge include in-water work, which consists of driving piles for the temporary access trestle and drilling shafts for the bridge foundation.

Construction of the I-495 northbound bridge is expected to be completed by 2020. The new I-495 southbound bridge will be constructed beginning in 2020. The full project is expected to be completed in 2022.

The project also includes widening and reconstructing ramps, realigning the roadway, improving the roadway drainage system, constructing pier protection barriers for existing bridge piers at the River Street (Exit 49) and Route 125 Connector (Exit 48) overpasses, and improving signage and pavement markings.

In order to minimize the impacts on the traveling public and the local community, MassDOT will maintain three lanes of travel in each direction on I-495 north and southbound during peak commuting hours throughout construction.

For more information, please visit the project website.

Written By:

Tags:

Recent Posts

Green Line Extension to Reopen Two Major Bridges in Somerville posted on May 28

Green Line Extension to Reopen Two Major Bridges in Somerville

The MBTA announced that the Green Line Extension (GLX) project will permanently reopen the Washington Street Bridge/Underpass near McGrath Highway in East Somerville on May 31. Following this major project milestone, the Broadway Bridge in Ball Square is scheduled to reopen the during the first   …Continue Reading Green Line Extension to Reopen Two Major Bridges in Somerville

Baker-Polito Administration Highlights Accelerated MBTA Blue Line Work posted on May 27

Baker-Polito Administration Highlights Accelerated MBTA Blue Line Work

Governor Charlie Baker, Transportation Secretary and CEO Stephanie Pollack, General Manager Steve Poftak, and other officials toured ongoing accelerated infrastructure work taking place on the Blue Line at Maverick Station. A full closure of the Blue Line between Bowdoin and Airport Stations began Monday, May   …Continue Reading Baker-Polito Administration Highlights Accelerated MBTA Blue Line Work

Registry of Motor Vehicles Implements Further Extensions to Expiring Licenses, Learner’s Permits, and Plate Registrations posted on May 26

Registry of Motor Vehicles Implements Further Extensions to Expiring Licenses, Learner's Permits, and Plate Registrations

The Massachusetts Registry of Motor Vehicles (RMV) is announcing it will be implementing further extensions to the renewal timelines for expiring motor vehicle inspection stickers, passenger plate registrations, professional credentials, and driver’s licenses and learner’s permits, including Commercial Driver’s Licenses and Commercial Learner’s Permits (CDLs   …Continue Reading Registry of Motor Vehicles Implements Further Extensions to Expiring Licenses, Learner’s Permits, and Plate Registrations