Post Content

Holyoke Lyman Street Bridge, September 27, 2010 The Lyman Street Bridge over the Second Level Canal in Holyoke reopened to traffic Monday, on budget and nearly two years earlier than originally scheduled. 

The $4.8 million project by MassDOT-hired contractor Daniel O'Connell & Sons of Holyoke began in spring 2009.  The work included a new reinforced concrete deck and steel beam superstructure, along with new sidewalks, guardrail, traffic signals, and approaching roadway. 

The original completion date of June 2012 was set to allow for bridge reconstruction in two phases to maintain pedestrian access.  However, MassDOT working with the City of Holyoke, contractors, and other partners designed a plan to use an already-planned utility bridge for pedestrian access.  This allowed the bridge to close during construction, speeding the work.  The Lyman Street Bridge opened this week, 21 months ahead of schedule.

The Holyoke bridge is another example of MassDOT completing more road and bridge projects safely and faster than ever.  The number of projects completed on time this year is up 53%, while the average time for advertising a project to the Notice to proceed from 422 days in 2007 to just 124 days this year.

The positive outcomes are happening even as at least 385 separate projects representing $1.085 billion in investment are repairing roads and deficient bridges and putting thousands of people to work across the Commonwealth in 2010. 

Written By:

Recent Posts

Route 79/Braga Bridge Project Traffic Update posted on Oct 30

Route 79/Braga Bridge Project Traffic Update

MassDOT will begin implementing traffic changes for the next stage of construction for the Route 79/Braga Bridge Project on Wednesday, November 12. The following changes will be implemented in a phased approach through the middle of December: Vehicles on Route 79/138 (Broadway) bound for Interstate   …Continue Reading Route 79/Braga Bridge Project Traffic Update

RMV: Promise to Customers posted on Oct 28

RMV: Promise to Customers

Today, MassDOT Secretary & CEO Richard A. Davey and MassDOT Registrar of Motor Vehicles Celia J. Blue offered a 10 point promise to RMV customers. The reimagining effort comprises current, ongoing and future initiatives that the RMV has in development to better the Registry experience.   …Continue Reading RMV: Promise to Customers

November E-ZPass Sign Up: Chelsea, Everett posted on Oct 28

November E-ZPass Sign Up: Chelsea, Everett

MassDOT is encouraging motorists to join E-ZPass with All-Electronic Tolling now in place on the Tobin Bridge and expanding statewide within the next two years. The E-ZPass Street Team will be enrolling new customers in the E-ZPass throughout the Fall season. The E-ZPass Van schedule   …Continue Reading November E-ZPass Sign Up: Chelsea, Everett