Post Content

Holyoke Lyman Street Bridge, September 27, 2010 The Lyman Street Bridge over the Second Level Canal in Holyoke reopened to traffic Monday, on budget and nearly two years earlier than originally scheduled. 

The $4.8 million project by MassDOT-hired contractor Daniel O'Connell & Sons of Holyoke began in spring 2009.  The work included a new reinforced concrete deck and steel beam superstructure, along with new sidewalks, guardrail, traffic signals, and approaching roadway. 

The original completion date of June 2012 was set to allow for bridge reconstruction in two phases to maintain pedestrian access.  However, MassDOT working with the City of Holyoke, contractors, and other partners designed a plan to use an already-planned utility bridge for pedestrian access.  This allowed the bridge to close during construction, speeding the work.  The Lyman Street Bridge opened this week, 21 months ahead of schedule.

The Holyoke bridge is another example of MassDOT completing more road and bridge projects safely and faster than ever.  The number of projects completed on time this year is up 53%, while the average time for advertising a project to the Notice to proceed from 422 days in 2007 to just 124 days this year.

The positive outcomes are happening even as at least 385 separate projects representing $1.085 billion in investment are repairing roads and deficient bridges and putting thousands of people to work across the Commonwealth in 2010. 

Written By:

Recent Posts

MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2 posted on Jul 29

MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2

The MBTA has scheduled necessary track maintenance activities on the Orange Line for this weekend, Saturday, August 1st and Sunday, August 2nd. Weekend service will be suspended between Forest Hills and Ruggles Stations. During the suspension of service, work crews will remove and replace rail   …Continue Reading MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2

Longfellow Bridge: August Closures Update posted on Jul 29

Longfellow Bridge: August Closures Update

The Longfellow Bridge Rehabilitation Project moves forward with demolition work that will require bridge closures. MassDOT’s contractor, White-Skanska-Consigli JV (WSC), will periodically close the Longfellow Bridge to all vehicular traffic beginning on Saturday, August 1 through Friday, August 21. The closures are necessary to safely   …Continue Reading Longfellow Bridge: August Closures Update

Green Line Extension Community Outreach Event posted on Jul 29

Green Line Extension Community Outreach Event

The Green Line Extension Project team including contractor Barletta Heavy Division this week participated in a touch-a-truck event with the Power Kids summer enrichment program in Medford. Approximately 60 youth from the Power Kids program grades K-11 had an up close view of the construction   …Continue Reading Green Line Extension Community Outreach Event