Post Content

Holyoke Lyman Street Bridge, September 27, 2010 The Lyman Street Bridge over the Second Level Canal in Holyoke reopened to traffic Monday, on budget and nearly two years earlier than originally scheduled. 

The $4.8 million project by MassDOT-hired contractor Daniel O'Connell & Sons of Holyoke began in spring 2009.  The work included a new reinforced concrete deck and steel beam superstructure, along with new sidewalks, guardrail, traffic signals, and approaching roadway. 

The original completion date of June 2012 was set to allow for bridge reconstruction in two phases to maintain pedestrian access.  However, MassDOT working with the City of Holyoke, contractors, and other partners designed a plan to use an already-planned utility bridge for pedestrian access.  This allowed the bridge to close during construction, speeding the work.  The Lyman Street Bridge opened this week, 21 months ahead of schedule.

The Holyoke bridge is another example of MassDOT completing more road and bridge projects safely and faster than ever.  The number of projects completed on time this year is up 53%, while the average time for advertising a project to the Notice to proceed from 422 days in 2007 to just 124 days this year.

The positive outcomes are happening even as at least 385 separate projects representing $1.085 billion in investment are repairing roads and deficient bridges and putting thousands of people to work across the Commonwealth in 2010. 

Written By:

Recent Posts

I-495/I-90 Interchange Improvements Public Meetings Set posted on Jul 16

I-495/I-90 Interchange Improvements Public Meetings Set

MassDOT will be holding public information meetings for residents of nearby cities and towns to become acquainted with the current stage of the I-495/I-90 Interchange Improvements Project. The meetings are scheduled as follows: Hopkinton- Thursday, July 25, 6:30-8:30pm, Town Hall, Basement, 18 Main Street Hudson-   …Continue Reading I-495/I-90 Interchange Improvements Public Meetings Set

Tobin Bridge/Chelsea Curves Project Update posted on Jul 15

Tobin Bridge/Chelsea Curves Project Update

MassDOT reminds members of the public that construction operations and traffic impacts for the Tobin Bridge/Chelsea Curves Rehabilitation Project continue in July and August. Beginning Monday, July 15, the Fourth Street Off-ramp will be closed for 2-3 months for steel repairs, structural rehabilitation, safety improvements,   …Continue Reading Tobin Bridge/Chelsea Curves Project Update

Allston Multimodal Project Public Meetings Set posted on Jul 11

Allston Multimodal Project Public Meetings Set

MassDOT has scheduled Allston Multimodal Project Public Information Meetings as follows: Framingham: Thursday, July 18, 2019, 6:30 p.m. – 8:30 p.m., Framingham City Hall (Memorial Building), Blumer Room , 150 Concord Street. Worcester: Wednesday, August 14, 2019, 6:30 p.m. – 8:30 p.m., Worcester Technical High   …Continue Reading Allston Multimodal Project Public Meetings Set