Post Content

Holyoke Lyman Street Bridge, September 27, 2010 The Lyman Street Bridge over the Second Level Canal in Holyoke reopened to traffic Monday, on budget and nearly two years earlier than originally scheduled. 

The $4.8 million project by MassDOT-hired contractor Daniel O'Connell & Sons of Holyoke began in spring 2009.  The work included a new reinforced concrete deck and steel beam superstructure, along with new sidewalks, guardrail, traffic signals, and approaching roadway. 

The original completion date of June 2012 was set to allow for bridge reconstruction in two phases to maintain pedestrian access.  However, MassDOT working with the City of Holyoke, contractors, and other partners designed a plan to use an already-planned utility bridge for pedestrian access.  This allowed the bridge to close during construction, speeding the work.  The Lyman Street Bridge opened this week, 21 months ahead of schedule.

The Holyoke bridge is another example of MassDOT completing more road and bridge projects safely and faster than ever.  The number of projects completed on time this year is up 53%, while the average time for advertising a project to the Notice to proceed from 422 days in 2007 to just 124 days this year.

The positive outcomes are happening even as at least 385 separate projects representing $1.085 billion in investment are repairing roads and deficient bridges and putting thousands of people to work across the Commonwealth in 2010. 

Written By:

Recent Posts

NHTSA Safety Reminder: Never Leave a Child Alone in a Car posted on Jul 31

NHTSA Safety Reminder: Never Leave a Child Alone in a Car

The National Highway Traffic Safety Administration and partners today are raising awareness about heatstroke, one of the leading causes of death among children. The NHTSA says at least 17 children have already died this year from vehicular heatstroke. Heatstroke is the leading cause of non-crash   …Continue Reading NHTSA Safety Reminder: Never Leave a Child Alone in a Car

Fore River Bridge Project Milestone posted on Jul 29

Fore River Bridge Project Milestone

The Fore River Bridge Replacement Project in Quincy-Weymouth continues during the summer of 2014 with installation of the permanent bridge components along with a new milestone: arrival of the new bridge steel sections. The view above shows the progress made at the Quincy tower location.   …Continue Reading Fore River Bridge Project Milestone

Green Line Extension: Public Meeting July 31 posted on Jul 28

Green Line Extension: Public Meeting July 31

A City of Somerville and MBTA Green Line Extension Public Meeting regarding Medford Street Bridge construction has been scheduled for the following: Thursday, July 31, 6:00pm, Public Safety Building, 220 Washington Street, Somerville. Green Line Extension construction is underway and will involve periodic traffic impacts   …Continue Reading Green Line Extension: Public Meeting July 31