Post Content

Holyoke Lyman Street Bridge, September 27, 2010 The Lyman Street Bridge over the Second Level Canal in Holyoke reopened to traffic Monday, on budget and nearly two years earlier than originally scheduled. 

The $4.8 million project by MassDOT-hired contractor Daniel O'Connell & Sons of Holyoke began in spring 2009.  The work included a new reinforced concrete deck and steel beam superstructure, along with new sidewalks, guardrail, traffic signals, and approaching roadway. 

The original completion date of June 2012 was set to allow for bridge reconstruction in two phases to maintain pedestrian access.  However, MassDOT working with the City of Holyoke, contractors, and other partners designed a plan to use an already-planned utility bridge for pedestrian access.  This allowed the bridge to close during construction, speeding the work.  The Lyman Street Bridge opened this week, 21 months ahead of schedule.

The Holyoke bridge is another example of MassDOT completing more road and bridge projects safely and faster than ever.  The number of projects completed on time this year is up 53%, while the average time for advertising a project to the Notice to proceed from 422 days in 2007 to just 124 days this year.

The positive outcomes are happening even as at least 385 separate projects representing $1.085 billion in investment are repairing roads and deficient bridges and putting thousands of people to work across the Commonwealth in 2010. 

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour