Post Content

Medford I-93 1st Weekend Complete, June 5, 2011 The first I-93 rapid bridge superstructure replacements in Medford as part of the 93Fast14 project were completed successfully and well ahead of schedule late Sunday, June 5. 

The first location on I-93 north over Riverside Avenue is seen at left as of 7:00pm Sunday, with the new superstructure in place and being prepared to reopen to traffic.  A permanent barrier to replace the temporary barriers seen at the location will be completed in the coming weeks.

I-93 was completely reopened to traffic just before 10:00 PM, seven hours ahead of schedule.

To see more photos of the project on the web, visit the project gallery.

Check out the new interactive project website with maps, video, project updates, and helpful links at www.mass.gov/massdot/93fast14.

During the upcoming weekend of June 10-13, two bridge superstructures will be replaced carrying I-93 northbound over Salem Street/Route 60.  At 8:00 PM on June 10, northbound traffic on I-93 will cross over onto the opposite side of the highway.  Both roads will fully reopen at 5:00 AM on Monday, June 13.

As the 93Fast14 project continues on weekends in June, July and August except for the July 4th weekend, MassDOT strongly advises drivers to plan their travel routes and times carefully and to use alternate routes or public transportation to avoid this area if possible.  MassDOT recommends drivers that do not have a destination in the Medford/Downtown Boston area use alternate routes [I-495, I-95 (Route 128), Route 1 and I-90] to avoid the construction area.

The $98.1 million project to replace the fourteen bridge superstructures in Medford is funded through the Patrick-Murray Administration’s historic Accelerated Bridge Program to reduce the Commonwealth’s backlog of structurally-deficient bridges.

Written By:

Recent Posts

July 4th Holiday Services Update posted on Jun 30

July 4th Holiday Services Update

MassDOT encourages safe travel during the upcoming July 4 holiday weekend.  Before you drive, check our live Traffic Cameras web page to view current conditions. Traffic is especially heavy at the I-84 interchange at Exit 9 in Sturbridge on the day before the holiday and   …Continue Reading July 4th Holiday Services Update

MassDOT Board Approves Contract for 325 New MBTA Buses posted on Jun 29

MassDOT Board Approves Contract for 325 New MBTA Buses

The MassDOT Board of Directors today approved a contract for the manufacture and delivery of 325 new state-of-the-art replacement buses for the MBTA fleet. “This is a major step in the process in modernizing the MBTA’s bus fleet and provides an important resource for millions   …Continue Reading MassDOT Board Approves Contract for 325 New MBTA Buses

Medford Cradock Bridge: I-93 Route 16 Westbound Ramp Closure posted on Jun 26

MassDOT is scheduled to close the I-93 Route 16 Westbound off ramp on Monday, June 29, at 7:00 AM to begin construction on the Cradock Bridge Project in Medford. The off ramp is scheduled to be closed for the duration of the project through approximately   …Continue Reading Medford Cradock Bridge: I-93 Route 16 Westbound Ramp Closure