Post Content

Medford I-93 1st Weekend Complete, June 5, 2011 The first I-93 rapid bridge superstructure replacements in Medford as part of the 93Fast14 project were completed successfully and well ahead of schedule late Sunday, June 5. 

The first location on I-93 north over Riverside Avenue is seen at left as of 7:00pm Sunday, with the new superstructure in place and being prepared to reopen to traffic.  A permanent barrier to replace the temporary barriers seen at the location will be completed in the coming weeks.

I-93 was completely reopened to traffic just before 10:00 PM, seven hours ahead of schedule.

To see more photos of the project on the web, visit the project gallery.

Check out the new interactive project website with maps, video, project updates, and helpful links at www.mass.gov/massdot/93fast14.

During the upcoming weekend of June 10-13, two bridge superstructures will be replaced carrying I-93 northbound over Salem Street/Route 60.  At 8:00 PM on June 10, northbound traffic on I-93 will cross over onto the opposite side of the highway.  Both roads will fully reopen at 5:00 AM on Monday, June 13.

As the 93Fast14 project continues on weekends in June, July and August except for the July 4th weekend, MassDOT strongly advises drivers to plan their travel routes and times carefully and to use alternate routes or public transportation to avoid this area if possible.  MassDOT recommends drivers that do not have a destination in the Medford/Downtown Boston area use alternate routes [I-495, I-95 (Route 128), Route 1 and I-90] to avoid the construction area.

The $98.1 million project to replace the fourteen bridge superstructures in Medford is funded through the Patrick-Murray Administration’s historic Accelerated Bridge Program to reduce the Commonwealth’s backlog of structurally-deficient bridges.

Written By:

Recent Posts

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th posted on Jul 26

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

This is a reminder that the 2017 Construction Shutdown for the Commonwealth Avenue Bridge Replacement Project is beginning at 9:00 PM today, Wednesday July 26, and will continue through 5:00 AM on Monday, August 14. Please note the construction-related impacts below: For Pedestrians and Bicyclists:   …Continue Reading Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

Springfield: I-91 Viaduct Rehabilitation Progress Continues posted on Jul 24

Springfield: I-91 Viaduct Rehabilitation Progress Continues

MassDOT and its contractor, the Joint Venture of White-Schiavone (JV), continue to make progress on rehabilitation of the Interstate 91 Viaduct (I-91) through Springfield. The contractor completed reconstruction of the center lanes of the highway last fall, and began Stage 2 of construction in November   …Continue Reading Springfield: I-91 Viaduct Rehabilitation Progress Continues

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts posted on Jul 23

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts

MassDOT is reminding the public that travel impacts will begin next week throughout the Boston University/Saint Paul Street neighborhood of Boston along Commonwealth Avenue due to the Commonwealth Avenue Bridge Replacement Project. Drivers on Commonwealth Avenue, the BU Bridge and I-90 will see lane closings   …Continue Reading Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts