Post Content

Lexington, Governor Patrick, Route 2 Bridges Groundbreaking, July 8, 2014Governor Deval Patrick today joined MassDOT Secretary and CEO Richard A. Davey along with state and local officials to celebrate the groundbreaking for the Route 2 Bridge Replacement project in Lexington. The $50.3 million project will replace two structurally deficient bridges that carry traffic on the busy Route 2 corridor over Interstate 95.

The work will be performed using accelerated bridge construction to complete the project more quickly and with less impact on the public, and will increase access to local economic development opportunities and area businesses.

“Rebuilding our roads, bridges and other public infrastructure across the Commonwealth is critical,” said Governor Patrick. “As we make these investments, we are making travel safer and more convenient while building the foundation for a growing economy.”

The project includes two new bridges providing three travel lanes and one auxiliary lane in each direction. The work also includes realignment of portions of Route 2 to improve clearance over I-95, along with reconstruction and resurfacing of a two-mile section of I-95.

“The Lexington Route 2 Bridges project is a perfect example of making a critical investment and doing it the right way,” said Secretary Davey. “We are replacing 50-year old deficient bridges and doing so using a streamlined design-build contract that will accelerate the timeline and deliver new bridges sooner to the tens of thousands of people traveling Route 2 each day.”

This design-build project will allow for construction to begin almost immediately on critical elements of a project, even as final design elements are being approved. The bridge and highway designs are scheduled to be completed in early 2015 with construction complete by November 2016. MassDOT issued the notice to proceed with the project on April 22 following the passage of the Transportation Bond Bill. During construction, a minimum of two travel lanes and one auxiliary lane will be maintained in each direction on Route 2. A minimum of four travel lanes and one auxiliary lane in each direction will be maintained on I-95 during peak travel times.

Route 2 is one of the main routes used by east-west travelers to reach the Greater Boston area and carries approximately 67,000 vehicles per day. The bridges carrying Route 2 over I-95 were built in 1960 and are functionally obsolete with substandard vertical clearance over I-95.

Written By:

Recent Posts

Methuen Rotary I-93 Project Update posted on Mar 4

Methuen Rotary I-93 Project Update

MassDOT’s $66.4 million Methuen Rotary Reconstruction Project on I-93 at Routes 110 and 113 is moving forward during winter 2015. During the month of March, the following activities will continue on the I-93 at Routes 110 and 113 Interchange Reconstruction – Methuen Rotary project:     …Continue Reading Methuen Rotary I-93 Project Update

MassDOT Aeronautics: 2015 Aviation Art Contest Winners posted on Mar 3

MassDOT Aeronautics: 2015 Aviation Art Contest Winners

The MassDOT Aeronautics Division held the Massachusetts State level judging of the 2015 International Aviation Art Contest, with this year’s theme, “World Air Games”. The World Air Games will be held in Dubai in 2015. During 12 days, spectators will see world class competitions and   …Continue Reading MassDOT Aeronautics: 2015 Aviation Art Contest Winners

Boston: Massachusetts Avenue Bridge Public Hearing Set posted on Mar 2

Boston: Massachusetts Avenue Bridge Public Hearing Set

MassDOT has scheduled a Design Public Hearing for the proposed Massachusetts Avenue Bridge over Commonwealth Avenue Project in Boston as follows: Boston Central Library, Commonwealth Salon, 700 Boylston Street, Wednesday, March 25, 2015, 6:30PM-8:00PM The purpose of this hearing is to provide the public with   …Continue Reading Boston: Massachusetts Avenue Bridge Public Hearing Set