Post Content

Lexington, Governor Patrick, Route 2 Bridges Groundbreaking, July 8, 2014Governor Deval Patrick today joined MassDOT Secretary and CEO Richard A. Davey along with state and local officials to celebrate the groundbreaking for the Route 2 Bridge Replacement project in Lexington. The $50.3 million project will replace two structurally deficient bridges that carry traffic on the busy Route 2 corridor over Interstate 95.

The work will be performed using accelerated bridge construction to complete the project more quickly and with less impact on the public, and will increase access to local economic development opportunities and area businesses.

“Rebuilding our roads, bridges and other public infrastructure across the Commonwealth is critical,” said Governor Patrick. “As we make these investments, we are making travel safer and more convenient while building the foundation for a growing economy.”

The project includes two new bridges providing three travel lanes and one auxiliary lane in each direction. The work also includes realignment of portions of Route 2 to improve clearance over I-95, along with reconstruction and resurfacing of a two-mile section of I-95.

“The Lexington Route 2 Bridges project is a perfect example of making a critical investment and doing it the right way,” said Secretary Davey. “We are replacing 50-year old deficient bridges and doing so using a streamlined design-build contract that will accelerate the timeline and deliver new bridges sooner to the tens of thousands of people traveling Route 2 each day.”

This design-build project will allow for construction to begin almost immediately on critical elements of a project, even as final design elements are being approved. The bridge and highway designs are scheduled to be completed in early 2015 with construction complete by November 2016. MassDOT issued the notice to proceed with the project on April 22 following the passage of the Transportation Bond Bill. During construction, a minimum of two travel lanes and one auxiliary lane will be maintained in each direction on Route 2. A minimum of four travel lanes and one auxiliary lane in each direction will be maintained on I-95 during peak travel times.

Route 2 is one of the main routes used by east-west travelers to reach the Greater Boston area and carries approximately 67,000 vehicles per day. The bridges carrying Route 2 over I-95 were built in 1960 and are functionally obsolete with substandard vertical clearance over I-95.

Written By:

Recent Posts

MBTA Silver Line vehicles will test ramp from South Boston to I-90 East posted on Aug 23

MBTA Silver Line vehicles will test ramp from South Boston to I-90 East

MassDOT and the MBTA today announced that there will be a limited test of MBTA Silver Line buses using a ramp from MassPort’s Haul Road in South Boston’s Seaport District to I-90 eastbound. The three-day test will take place during afternoon peak travel periods to   …Continue Reading MBTA Silver Line vehicles will test ramp from South Boston to I-90 East

Tobin Bridge/Chelsea Curves Rehabilitation Project Update posted on Aug 15

Tobin Bridge/Chelsea Curves Rehabilitation Project Update

MassDOT has announced that the lane closures and roadway configuration on Route 1 northbound in Chelsea will shift on Monday, August 19 so that the center lane on this section of highway will be closed 24/7. Both the right and left travel lanes will be   …Continue Reading Tobin Bridge/Chelsea Curves Rehabilitation Project Update

First New MBTA Orange Line Cars Enter Passenger Service posted on Aug 14

First New MBTA Orange Line Cars Enter Passenger Service

Governor Charlie Baker, MassDOT Secretary and CEO Stephanie Pollack, and MBTA General Manager Steve Poftak today introduced the first new Orange Line train comprised of six brand new cars into regular service from Wellington Station. These six new cars entering passenger service today are the   …Continue Reading First New MBTA Orange Line Cars Enter Passenger Service