Longfellow Bridge 2Beginning on July 20, MassDOT will begin major construction activity on the Longfellow Bridge connecting Boston and Cambridge over the Charles River.  As part of the rehabilitation project, the bridge will be closed for vehicular travel in the Cambridge-bound direction.

One vehicle travel lane to Boston, MBTA Red Line service inbound and outbound, emergency response, and bicycle and pedestrian access will be maintained throughout construction.

Effective July 20, 2013 through September 2014, one lane of traffic will carry vehicles into Boston (using the current Cambridge-bound lane) and Cambridge-bound traffic will be detoured using a signed route from Charles Circle to Land Boulevard using Leverett Circle and Monsignor O’Brien Highway.

Subsequent to September 2014, the Boston-bound travel lane will shift its position on the bridge while keeping the Cambridge-bound detour in place.

Preliminary work to prepare for construction and the traffic shift began in April 2013 and will be completed by July 20. Traffic signal timing changes, lane restriping, and curb modifications at five area intersections will accommodate the traffic management plan. Overhead highway signs on I-93 and I-90 and portable variable message boards on local roads will provide advance notice of traffic pattern changes. Traffic conditions will be monitored at key locations and through the use of traffic cameras installed as part of the project.

The three and a half year project will rehabilitate the iconic “Salt and Pepper” Bridge to improve safety, structural integrity, capacity, and meet modern codes including ADA accessibility.

A public meeting to present details on this detour route is scheduled for Wednesday, July 10, 7 to 9 PM, MIT, Building E 25, Room 111 (E25-111), 45 Carleton Street, Cambridge.

The Longfellow Bridge Rehabilitation Project is part of the Patrick Administration’s $3 billion Accelerated Bridge Program. For more information on the project and traffic management plans, visit the Longfellow Bridge project website. For questions or to report issues and concerns related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us to be added to the project distribution list and receive project updates and meeting notices.

Written By:

Recent Posts

Commonwealth Avenue Bridge Replacement Project Impacts: July 26 through August 11 posted on Apr 23

Commonwealth Avenue Bridge Replacement Project Impacts: July 26 through August 11

MassDOT today announced that it will conduct intensive construction operations to replace the westbound side of the Commonwealth Avenue Bridge over 15 ½ days from Thursday, July 26 through Saturday, August 11, as part of the ongoing $110 million bridge placement project. These types of construction operations   …Continue Reading Commonwealth Avenue Bridge Replacement Project Impacts: July 26 through August 11

MassDOT: Second Annual Holyoke-South Hadley Connecticut River Roll and Stroll posted on Apr 23

MassDOT: Second Annual Holyoke-South Hadley Connecticut River Roll and Stroll

MassDOT is pleased to announce that the second annual Connecticut River Roll and Stroll Street Festival will take place on Sunday, May 6, 2018 marking the official kickoff of MassDOT-sponsored outdoor events this season aimed at promoting healthy transportation. The Connecticut River Roll and Stroll   …Continue Reading MassDOT: Second Annual Holyoke-South Hadley Connecticut River Roll and Stroll

MassDOT: Tobin Bridge Project Updated Impacts posted on Apr 20

MassDOT: Tobin Bridge Project Updated Impacts

MassDOT has announced an updated schedule for traffic impacts for the Tobin Bridge Repair project. The sequence of work and corresponding impacts have been updated to better accommodate and optimize travel throughout the region as MassDOT is carrying out several major infrastructure projects this construction   …Continue Reading MassDOT: Tobin Bridge Project Updated Impacts