Post Content

longfellow_LgMore than 100 years after the last stone was set on the “salt and pepper” towers of the Longfellow Bridge, MassDOT will begin dismantling the towers for storage, cleaning, and repair as part of the Longfellow Bridge Rehabilitation Project.  The work is anticipated to begin later this week, and is weather dependent.

The tower dismantling work will take place using a barge-mounted crane on the Charles River. On Thursday, March 6, MassDOT’s contractor, White-Skanska-Consigli JV, will begin preparations by moving into place the crane via barge from the staging area in Charlestown to the upstream side of the bridge.  An ice-breaker will precede the barge to provide an unobstructed path.  Once the crane is in position at the Cambridge tower the granite stones will be removed and loaded on a barge. The stones will be taken to the contractor’s staging area for cleaning, storage, and repair. 

The towers will be dismantled to sidewalk level only.  All remaining pier granite below the sidewalk will be restored in place.  During stone removal, waterway access will be partially restricted through span 7  immediately adjacent to the tower.  Booms and lighting will be deployed in accordance with US Coast Guard requirements for boater safety.

Along with the tower granite removal, the contractor will demolish a concrete liner to expose the inner face of the tower stonework. The concrete demolition work will take place from staging set within the towers and will not be visible to pedestrians from street level. Once the Cambridge-side tower is dismantled, the contractor will start work on the adjacent upstream Boston tower, Pier 5. The two downstream towers will be dismantled and restored when that side of the bridge is rehabilitated during the final phase of construction, which is planned to begin in fall 2015. 

As conditions dictate, the uppermost stones comprising the tower roof may need to be removed using a mobile crane situated on the bridge deck. In this case, the work will be done at night, during MBTA Red Line non-service hours.

The contractor plans to rebuild the iconic towers after seismic reinforcement construction is completed within the bridge tower piers. The fully restored upstream “salt and pepper” tower stonework is planned to be reassembled on the bridge later this year.

To learn about the Longfellow Bridge Rehabilitation Project and construction process, view this animation. For more information on the project, visit the website: www.mass.gov/massdot/longfellowbridge

Written By:

Recent Posts

MBTA: Weekend Service on 3 Commuter Rail Lines Begins December 27 posted on Dec 19

MBTA: Weekend Service on 3 Commuter Rail Lines Begins December 27

The restoration of weekend Commuter Rail service on three lines will begin next Saturday, December 27. The Kingston/Plymouth and Greenbush lines will see the return of Saturday and Sunday service and the Needham Line will resume Saturday service after a two year absence. “MassDOT is   …Continue Reading MBTA: Weekend Service on 3 Commuter Rail Lines Begins December 27

Fairhaven Bike Train Program Recognized posted on Dec 18

Fairhaven Bike Train Program Recognized

The Town of Fairhaven was recognized alongside the Massachusetts Safe Routes to School (SRTS) Program by Cape Cod’s NPR station, WCAI, for their bike train program. A bike train is a fun way for elementary and middle school students to get to school while being   …Continue Reading Fairhaven Bike Train Program Recognized

South Station Expansion: DEIR Comment Period Through December 24 posted on Dec 17

South Station Expansion: DEIR Comment Period Through December 24

Posted by:  Matthew Ciborowski, South Station Project Manager, MassDOT Office of Transportation Planning I was pleased to meet with more than 60 people who participated in an Open House and Hearing on the Draft Environmental Impact Report (DEIR) for the South Station Expansion project on   …Continue Reading South Station Expansion: DEIR Comment Period Through December 24