Post Content

longfellow_LgMore than 100 years after the last stone was set on the “salt and pepper” towers of the Longfellow Bridge, MassDOT will begin dismantling the towers for storage, cleaning, and repair as part of the Longfellow Bridge Rehabilitation Project.  The work is anticipated to begin later this week, and is weather dependent.

The tower dismantling work will take place using a barge-mounted crane on the Charles River. On Thursday, March 6, MassDOT’s contractor, White-Skanska-Consigli JV, will begin preparations by moving into place the crane via barge from the staging area in Charlestown to the upstream side of the bridge.  An ice-breaker will precede the barge to provide an unobstructed path.  Once the crane is in position at the Cambridge tower the granite stones will be removed and loaded on a barge. The stones will be taken to the contractor’s staging area for cleaning, storage, and repair. 

The towers will be dismantled to sidewalk level only.  All remaining pier granite below the sidewalk will be restored in place.  During stone removal, waterway access will be partially restricted through span 7  immediately adjacent to the tower.  Booms and lighting will be deployed in accordance with US Coast Guard requirements for boater safety.

Along with the tower granite removal, the contractor will demolish a concrete liner to expose the inner face of the tower stonework. The concrete demolition work will take place from staging set within the towers and will not be visible to pedestrians from street level. Once the Cambridge-side tower is dismantled, the contractor will start work on the adjacent upstream Boston tower, Pier 5. The two downstream towers will be dismantled and restored when that side of the bridge is rehabilitated during the final phase of construction, which is planned to begin in fall 2015. 

As conditions dictate, the uppermost stones comprising the tower roof may need to be removed using a mobile crane situated on the bridge deck. In this case, the work will be done at night, during MBTA Red Line non-service hours.

The contractor plans to rebuild the iconic towers after seismic reinforcement construction is completed within the bridge tower piers. The fully restored upstream “salt and pepper” tower stonework is planned to be reassembled on the bridge later this year.

To learn about the Longfellow Bridge Rehabilitation Project and construction process, view this animation. For more information on the project, visit the website: www.mass.gov/massdot/longfellowbridge

Written By:

Recent Posts

Nantucket Multi-Use Path Completed posted on Nov 22

Nantucket Multi-Use Path Completed

MassDOT Highway Division District 5 has announced that the multi-use pedestrian and bicycle path project, from Washington Street to Orange Street, on Nantucket is now complete. The path was constructed along an abandoned railroad berm between Goose Pond and Nantucket Harbor. The $2.4 million project   …Continue Reading Nantucket Multi-Use Path Completed

Governor Baker Urges Holiday Travel Caution, Highlights Road Safety Initiatives posted on Nov 21

Governor Baker Urges Holiday Travel Caution, Highlights Road Safety Initiatives

In advance of the Thanksgiving Holiday and travel period, Governor Charlie Baker today joined Transportation Secretary and CEO Stephanie Pollack to highlight a package of new and existing legislative proposals to promote safety on Massachusetts roadways, including support for pending legislation to reduce distracted and impaired   …Continue Reading Governor Baker Urges Holiday Travel Caution, Highlights Road Safety Initiatives

Thanksgiving Travel: Plan Ahead posted on Nov 21

Thanksgiving Travel: Plan Ahead

The Massachusetts Department of Transportation is reminding members of the public to plan ahead for Thanksgiving holiday travel, use the appropriate technology resources to make informed decisions, and consider public transportation if traveling to locations such as Logan airport. “We know from previous years that   …Continue Reading Thanksgiving Travel: Plan Ahead