Post Content

longfellow_LgMore than 100 years after the last stone was set on the “salt and pepper” towers of the Longfellow Bridge, MassDOT will begin dismantling the towers for storage, cleaning, and repair as part of the Longfellow Bridge Rehabilitation Project.  The work is anticipated to begin later this week, and is weather dependent.

The tower dismantling work will take place using a barge-mounted crane on the Charles River. On Thursday, March 6, MassDOT’s contractor, White-Skanska-Consigli JV, will begin preparations by moving into place the crane via barge from the staging area in Charlestown to the upstream side of the bridge.  An ice-breaker will precede the barge to provide an unobstructed path.  Once the crane is in position at the Cambridge tower the granite stones will be removed and loaded on a barge. The stones will be taken to the contractor’s staging area for cleaning, storage, and repair. 

The towers will be dismantled to sidewalk level only.  All remaining pier granite below the sidewalk will be restored in place.  During stone removal, waterway access will be partially restricted through span 7  immediately adjacent to the tower.  Booms and lighting will be deployed in accordance with US Coast Guard requirements for boater safety.

Along with the tower granite removal, the contractor will demolish a concrete liner to expose the inner face of the tower stonework. The concrete demolition work will take place from staging set within the towers and will not be visible to pedestrians from street level. Once the Cambridge-side tower is dismantled, the contractor will start work on the adjacent upstream Boston tower, Pier 5. The two downstream towers will be dismantled and restored when that side of the bridge is rehabilitated during the final phase of construction, which is planned to begin in fall 2015. 

As conditions dictate, the uppermost stones comprising the tower roof may need to be removed using a mobile crane situated on the bridge deck. In this case, the work will be done at night, during MBTA Red Line non-service hours.

The contractor plans to rebuild the iconic towers after seismic reinforcement construction is completed within the bridge tower piers. The fully restored upstream “salt and pepper” tower stonework is planned to be reassembled on the bridge later this year.

To learn about the Longfellow Bridge Rehabilitation Project and construction process, view this animation. For more information on the project, visit the website: www.mass.gov/massdot/longfellowbridge

Written By:

Recent Posts

MBTA Silver Line vehicles will test ramp from South Boston to I-90 East posted on Aug 23

MBTA Silver Line vehicles will test ramp from South Boston to I-90 East

MassDOT and the MBTA today announced that there will be a limited test of MBTA Silver Line buses using a ramp from MassPort’s Haul Road in South Boston’s Seaport District to I-90 eastbound. The three-day test will take place during afternoon peak travel periods to   …Continue Reading MBTA Silver Line vehicles will test ramp from South Boston to I-90 East

Tobin Bridge/Chelsea Curves Rehabilitation Project Update posted on Aug 15

Tobin Bridge/Chelsea Curves Rehabilitation Project Update

MassDOT has announced that the lane closures and roadway configuration on Route 1 northbound in Chelsea will shift on Monday, August 19 so that the center lane on this section of highway will be closed 24/7. Both the right and left travel lanes will be   …Continue Reading Tobin Bridge/Chelsea Curves Rehabilitation Project Update

First New MBTA Orange Line Cars Enter Passenger Service posted on Aug 14

First New MBTA Orange Line Cars Enter Passenger Service

Governor Charlie Baker, MassDOT Secretary and CEO Stephanie Pollack, and MBTA General Manager Steve Poftak today introduced the first new Orange Line train comprised of six brand new cars into regular service from Wellington Station. These six new cars entering passenger service today are the   …Continue Reading First New MBTA Orange Line Cars Enter Passenger Service