Post Content

longfellow_LgMore than 100 years after the last stone was set on the “salt and pepper” towers of the Longfellow Bridge, MassDOT will begin dismantling the towers for storage, cleaning, and repair as part of the Longfellow Bridge Rehabilitation Project.  The work is anticipated to begin later this week, and is weather dependent.

The tower dismantling work will take place using a barge-mounted crane on the Charles River. On Thursday, March 6, MassDOT’s contractor, White-Skanska-Consigli JV, will begin preparations by moving into place the crane via barge from the staging area in Charlestown to the upstream side of the bridge.  An ice-breaker will precede the barge to provide an unobstructed path.  Once the crane is in position at the Cambridge tower the granite stones will be removed and loaded on a barge. The stones will be taken to the contractor’s staging area for cleaning, storage, and repair. 

The towers will be dismantled to sidewalk level only.  All remaining pier granite below the sidewalk will be restored in place.  During stone removal, waterway access will be partially restricted through span 7  immediately adjacent to the tower.  Booms and lighting will be deployed in accordance with US Coast Guard requirements for boater safety.

Along with the tower granite removal, the contractor will demolish a concrete liner to expose the inner face of the tower stonework. The concrete demolition work will take place from staging set within the towers and will not be visible to pedestrians from street level. Once the Cambridge-side tower is dismantled, the contractor will start work on the adjacent upstream Boston tower, Pier 5. The two downstream towers will be dismantled and restored when that side of the bridge is rehabilitated during the final phase of construction, which is planned to begin in fall 2015. 

As conditions dictate, the uppermost stones comprising the tower roof may need to be removed using a mobile crane situated on the bridge deck. In this case, the work will be done at night, during MBTA Red Line non-service hours.

The contractor plans to rebuild the iconic towers after seismic reinforcement construction is completed within the bridge tower piers. The fully restored upstream “salt and pepper” tower stonework is planned to be reassembled on the bridge later this year.

To learn about the Longfellow Bridge Rehabilitation Project and construction process, view this animation. For more information on the project, visit the website: www.mass.gov/massdot/longfellowbridge

Written By:

Recent Posts

Natick: MassDOT Breaks Ground on Marion Street Bridge posted on May 4

Natick: MassDOT Breaks Ground on Marion Street Bridge

MassDOT today broke ground on a new bridge that will carry Marion Street over railroad tracks in Natick. The new bridge will feature a single superstructure with steel beams, concrete deck with asphalt surface on existing abutments, and a 6-foot wide sidewalk. Pedestrian access will   …Continue Reading Natick: MassDOT Breaks Ground on Marion Street Bridge

MBTA Projects 12.8% Reduction in Energy Costs posted on May 4

MBTA Projects 12.8% Reduction in Energy Costs

The MBTA projects a 12.8 percent reduction in energy costs for the 2017 Fiscal Year, and expects to see additional savings during the next three years, according to a presentation made recently to the MBTA’s Fiscal and Management Control Board. The cost savings are the   …Continue Reading MBTA Projects 12.8% Reduction in Energy Costs

MassDOT Launches “Go-Time” Real-Time Traffic Information posted on May 3

MassDOT Launches “Go-Time” Real-Time Traffic Information

MassDOT announced the first activation of the Commonwealth’s Real-Time Traffic Information System (Go-Time) set to expand statewide by the end of the year. Three new Real-Time Traffic displays were launched in the area of Rt. 140 in Taunton. These displays include travel times from Rt.   …Continue Reading MassDOT Launches “Go-Time” Real-Time Traffic Information