Post Content

Lowell Morton Street Bridge Reopens, July 9, 2010 A successful working partnership between MassDOT and its contractor and an innovative approach to the work have delivered the ultimate positive result: a bridge reconstructed and reopened 21 months ahead of schedule and under budget.

MassDOT and project contractor MAS Building and Bridges of Franklin began construction in April 2009 to replace the Morton Street bridge over the B&M Railroad in Lowell.  The project with an original budget of $2.65 million proposed closing the bridge to vehicles during reconstruction but maintaining pedestrian access to local schools and neighborhoods by doing the work in two phases.  The completion date was originally scheduled for March 2012.

During the early stages of the project, the contractor MAS Building and Bridges proposed and MassDOT approved placing a temporary pedestrian bridge next to the existing bridge to allow reconstruction to be completed in a single phase.  The temporary bridge costs were borne by the contractor.

MAS Building and Bridges and Project Superintendent Ed McInnis worked cooperatively and seamlessly with MassDOT's Construction Staff led by Resident Engineer Dan Boland and his assistant, Desire Manirakiza, to complete the project smoothly, swiftly and under the original budget.  The bridge reopened to traffic on July 9. 

Local constituent John Mullen of Lowell praised the contractors and MassDOT teamwork and hard work, saying,

"They and the state engineers on the project did everything they could to make the ten households effected feel as comfortable and informed as possible. I can't remember a day that they were not on the job and working. Shoveling snow on the weekends so the pedestrian access was walkable to being there when the weather was downright miserable. They were always there working. They truly deserve some recognition for a job well done."

Congratulations to the contractor, workers, and MassDOT staff members.

Written By:

Recent Posts

Commonwealth Avenue Bridge Replacement Project Impacts: July 26 through August 11 posted on Apr 23

Commonwealth Avenue Bridge Replacement Project Impacts: July 26 through August 11

MassDOT today announced that it will conduct intensive construction operations to replace the westbound side of the Commonwealth Avenue Bridge over 15 ½ days from Thursday, July 26 through Saturday, August 11, as part of the ongoing $110 million bridge placement project. These types of construction operations   …Continue Reading Commonwealth Avenue Bridge Replacement Project Impacts: July 26 through August 11

MassDOT: Second Annual Holyoke-South Hadley Connecticut River Roll and Stroll posted on Apr 23

MassDOT: Second Annual Holyoke-South Hadley Connecticut River Roll and Stroll

MassDOT is pleased to announce that the second annual Connecticut River Roll and Stroll Street Festival will take place on Sunday, May 6, 2018 marking the official kickoff of MassDOT-sponsored outdoor events this season aimed at promoting healthy transportation. The Connecticut River Roll and Stroll   …Continue Reading MassDOT: Second Annual Holyoke-South Hadley Connecticut River Roll and Stroll

MassDOT: Tobin Bridge Project Updated Impacts posted on Apr 20

MassDOT: Tobin Bridge Project Updated Impacts

MassDOT has announced an updated schedule for traffic impacts for the Tobin Bridge Repair project. The sequence of work and corresponding impacts have been updated to better accommodate and optimize travel throughout the region as MassDOT is carrying out several major infrastructure projects this construction   …Continue Reading MassDOT: Tobin Bridge Project Updated Impacts