Post Content

Lowell Morton Street Bridge Reopens, July 9, 2010 A successful working partnership between MassDOT and its contractor and an innovative approach to the work have delivered the ultimate positive result: a bridge reconstructed and reopened 21 months ahead of schedule and under budget.

MassDOT and project contractor MAS Building and Bridges of Franklin began construction in April 2009 to replace the Morton Street bridge over the B&M Railroad in Lowell.  The project with an original budget of $2.65 million proposed closing the bridge to vehicles during reconstruction but maintaining pedestrian access to local schools and neighborhoods by doing the work in two phases.  The completion date was originally scheduled for March 2012.

During the early stages of the project, the contractor MAS Building and Bridges proposed and MassDOT approved placing a temporary pedestrian bridge next to the existing bridge to allow reconstruction to be completed in a single phase.  The temporary bridge costs were borne by the contractor.

MAS Building and Bridges and Project Superintendent Ed McInnis worked cooperatively and seamlessly with MassDOT's Construction Staff led by Resident Engineer Dan Boland and his assistant, Desire Manirakiza, to complete the project smoothly, swiftly and under the original budget.  The bridge reopened to traffic on July 9. 

Local constituent John Mullen of Lowell praised the contractors and MassDOT teamwork and hard work, saying,

"They and the state engineers on the project did everything they could to make the ten households effected feel as comfortable and informed as possible. I can't remember a day that they were not on the job and working. Shoveling snow on the weekends so the pedestrian access was walkable to being there when the weather was downright miserable. They were always there working. They truly deserve some recognition for a job well done."

Congratulations to the contractor, workers, and MassDOT staff members.

Written By:

Recent Posts

Methuen Rotary I-93 Project Update posted on Mar 4

Methuen Rotary I-93 Project Update

MassDOT’s $66.4 million Methuen Rotary Reconstruction Project on I-93 at Routes 110 and 113 is moving forward during winter 2015. During the month of March, the following activities will continue on the I-93 at Routes 110 and 113 Interchange Reconstruction – Methuen Rotary project:     …Continue Reading Methuen Rotary I-93 Project Update

MassDOT Aeronautics: 2015 Aviation Art Contest Winners posted on Mar 3

MassDOT Aeronautics: 2015 Aviation Art Contest Winners

The MassDOT Aeronautics Division held the Massachusetts State level judging of the 2015 International Aviation Art Contest, with this year’s theme, “World Air Games”. The World Air Games will be held in Dubai in 2015. During 12 days, spectators will see world class competitions and   …Continue Reading MassDOT Aeronautics: 2015 Aviation Art Contest Winners

Boston: Massachusetts Avenue Bridge Public Hearing Set posted on Mar 2

Boston: Massachusetts Avenue Bridge Public Hearing Set

MassDOT has scheduled a Design Public Hearing for the proposed Massachusetts Avenue Bridge over Commonwealth Avenue Project in Boston as follows: Boston Central Library, Commonwealth Salon, 700 Boylston Street, Wednesday, March 25, 2015, 6:30PM-8:00PM The purpose of this hearing is to provide the public with   …Continue Reading Boston: Massachusetts Avenue Bridge Public Hearing Set