Post Content

The 646-kw solar farm at the Salisbury Depot achieved mechanical completion on Dec 27, 2016 after 6 weeks of intensive construction.

The 646-kw solar farm at the Salisbury Depot achieved mechanical completion on Dec 27, 2016 after 6 weeks of intensive construction.

Two new ground-mount solar fields are approaching mechanical completion at MassDOT Highway D4 Salisbury Depot and an underutilized area adjacent to I-90 Exit 1.

Visitors to MassDOT’s new Research and Material Lab at Hopkinton may have also noticed the solar canopy foundations at the facility’s parking lots. The three solar PV systems, with an aggregated capacity of about 1,800 kW, are the second group of solar projects that MassDOT has contracted out to be built along the state highways under a Master License Agreement executed in the fall of 2014.  Combined with the five solar farms that have been in commercial operation since the fall of 2015, MassDOT will soon have approximately 4,300 kW of solar power generation capacity on six highway Right-of-Way parcels and at two facilities.

These projects are part of MassDOT’s ongoing efforts to reduce greenhouse gas emissions and reduce energy costs.

Donald Pettey from the Chief Engineer’s Office discusses construction progress with the contractor’s site manager during a visit to the I-90 Exit 1 solar site.

Donald Pettey from the Chief Engineer’s Office discusses construction progress with the contractor’s site manager during a visit to the I-90 Exit 1 solar site.

Intensive construction activities at the Salisbury Depot and I-90 Exit 1 solar sites have been taking place since the beginning of October, 2016.  In order to meet the qualification deadline for Massachusetts’ solar renewable energy credits, the construction team must meet mechanical completion milestones of the two facilities by January 8, 2017.  Each site has its unique logistic challenge: for Salisbury Depot, late fall is typically a busy time as the Depot staff prepares for the upcoming snow and ice season; while at I-90 Exit 1, solar construction has coincided with the toll booth demolition and the exit reconfiguration.  Seamless coordination and space sharing are required at both sites.

“We have been challenged with extremely tight construction schedule and needed to double work effort and accelerate the process.  The district staff we have been working with has been simply fabulous to assist us anyway they can to achieve the aggressive construction schedule. Without their strong support, it would have not been possible to achieve mechanical completion within 8 weeks.” said the contractor’s on-site manager.

Thanks to the hard work of the workers on the ground and the support of the MassDOT staff involved in all aspects of the solar initiative, the two ground-mount solar facilities are expected to enter full commercial operation in the spring of 2017, once utility work is completed.  The Hopkinton solar canopy construction is anticipated to pick up speed in late February, 2017, when the steel manufacturer delivers the supporting structures.

Written By:

Tags: , ,

Recent Posts

MassDOT, MAPFRE Insurance: Tips for Night Time Driving posted on Jan 21

MassDOT, MAPFRE Insurance: Tips for Night Time Driving

Winter driving is not only challenging due to icy and snowy conditions. It is also dark for more hours of the day than it is light. With up to nearly 15 hours per day in darkness, it’s dark during part of the morning and evening   …Continue Reading MassDOT, MAPFRE Insurance: Tips for Night Time Driving

Weekend Winter Weather Advisory posted on Jan 18

Weekend Winter Weather Advisory

MassDOT is advising the public that the National Weather Service is predicting that snow will develop across the state from west to east on Saturday afternoon. Snowfall is expected to be heaviest across the northwestern part of the state, where several inches are possible. The   …Continue Reading Weekend Winter Weather Advisory

Holiday Weekend Travel, Services Advisory posted on Jan 17

Holiday Weekend Travel, Services Advisory

During the Martin Luther King Jr. holiday weekend, MassDOT is reminding the public to be alert while traveling, aware of holiday work restrictions and mindful of roadway conditions. “Drivers traveling throughout this holiday weekend are reminded to focus on getting to their destinations safely,” said   …Continue Reading Holiday Weekend Travel, Services Advisory