Post Content

Littleton Route 119 Flood Pumping March 29, 2010 MassDOT crews have worked around the clock since last Wednesday to replace a collapsed culvert under Route 119 in Littleton.  The road is closed.  The culvert drains Spectacle Pond.  The collapse blocked water flow from the Pond, causing the water to rise.

MassDOT estimates Route 119 will remain closed until at least mid-next week while crews work to replace the culvert, which is 20 feet under the roadway. 

As of Monday morning, MassDOT was pumping approximately 20,000 gallons per minute, left, with five pumps to alleviate flooding conditions and prevent the road from being undermined.  By the end of today, with two additional pumps from Michigan expected to arrive, MassDOT will be pumping 64,000 gallons per minute.

The flooding is having the most impact on the Town of Ayer’s water supply, with one of its wells located next to Spectacle Pond and impacted by the flooding.  Voluntary evacuations were ordered in Littleton on Sunday for 12 houses in the area due to flooding.

MassDOT has been coordinating very closely with town officials since Wednesday.  MassDOT Highway Administrator Luisa Paiewonsky was on-site Monday morning meeting with town emergency officials to assess the situation and check on the hard work ongoing by MassDOT crews.

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour