Longfellow Bridge August 2016MassDOT has announced the implementation of a plan to re-sequence construction as part of the Longfellow Bridge Project by combining Stage 4 and 6 construction, a measure which the contractor White-Skanska-Consigli (WSC) assures will result in faster completion of the project, and bring full beneficial use 3 months earlier, in June 2018.

This announcement follows a robust public process which included a stakeholder briefing and two public meetings in Boston and Cambridge that took place in August.  MassDOT has begun the multimodal shifts to accommodate the combined stages

Under this plan, WSC will simultaneously rehabilitate the bridge under the MBTA outbound track (Stage 4) and reconstruct the downstream roadway and sidewalk (previously planned for Stage 6). With this modification, the contractor anticipates having all modes of travel in their final configuration by June 2018. Stage 5 will be performed after the combined Stages 4 & 6.

This plan, which will shorten the schedule by three months from September 2018, builds on other time saving measures that succeeded in pulling in the schedule by three months from December 2018. ,

MassDOT Highway Administrator Thomas J. Tinlin said of the consolidation, “It’s no secret that the rehabilitation of this historic bridge posed significant challenges in the early stages of construction, but by working with and challenging our contractor to think creatively, we are happy to see a significant time savings and bring this project to completion sooner.  This response to challenges faced demonstrates MassDOT’s commitment to delivering the highest quality projects that respond to the needs of all modes and types of travelers.”

Representative Jay Livingstone said, “I’m pleased that MassDOT and its contractors continue to look for ways to shorten the reconstruction of the Longfellow Bridge.  I fully support MassDOT’s newest plan, which will again shorten the reconstruction by months.  MassDOT’s willingness to keep all critical stakeholders fully informed has been extremely helpful throughout the entire process”

Representative Toomey said, “MassDOT and the Longfellow Bridge contractor are clearly working hard to get the project completed at an earlier date. I appreciate their efforts to consistently provide residents and stakeholders with the latest information about the project, and they’ve been doing a great job at coming back to the community on a regular basis to provide updates and answer questions.”

To accommodate this time saving work, all modes of travel will use the upstream side of the bridge.

  • Pedestrians will use the upstream sidewalk for travel in both directions.
  • Inbound bicyclists will use the new 5-foot wide designated bike lane on the upstream roadway.
  • Outbound bicyclists will share the upstream sidewalk with pedestrians. The new upstream sidewalk is 8 feet 9 inches wide and can accommodate one bike lane and pedestrians.
  • While outbound cyclists may ride their bikes on the sidewalk, MassDOT asks that cyclists and pedestrians use caution and respect the rights of everyone to use public infrastructure in this temporary shared configuration.
  • MBTA and emergency response access across the bridge will be maintained at all times.

Visit the project website to learn more about the Stage 4 & 6 bike routes and to view the bike route maps for the Boston Approach and the Cambridge Approach.

The Cambridge-bound detour remains in place using the existing signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway (Route 28)/Charles River Dam Road and Land Boulevard.

Learn more about Stage 4 & 6 .

The Longfellow Bridge restoration project began in 2013. White-Skanska-Consigli Joint Venture is the contractor for the project.

Written By:

Tags: ,

Recent Posts

Holiday Weekend Travel, Services Advisory posted on Jan 17

Holiday Weekend Travel, Services Advisory

During the Martin Luther King Jr. holiday weekend, MassDOT is reminding the public to be alert while traveling, aware of holiday work restrictions and mindful of roadway conditions. “Drivers traveling throughout this holiday weekend are reminded to focus on getting to their destinations safely,” said   …Continue Reading Holiday Weekend Travel, Services Advisory

MassDOT Announces New Online Resources and Additional Public Meetings for Statewide Exit Renumbering Project posted on Jan 10

MassDOT Announces New Online Resources and Additional Public Meetings for Statewide Exit Renumbering Project

MassDOT is announcing new online resources on the project website for the Statewide Exit Renumbering Project, including an informational video on the project and an online meeting. Visit NewMassExits.com to access these new online tools, learn about the project, and ask the project team questions.   …Continue Reading MassDOT Announces New Online Resources and Additional Public Meetings for Statewide Exit Renumbering Project

Baker-Polito Administration Announces Additional Local Road and Bridge Funds posted on Jan 6

Baker-Polito Administration Announces Additional Local Road and Bridge Funds

The Baker-Polito Administration is announcing that $20 million in additional funding will be provided to cities and towns in Fiscal Year 2020 (FY20) for road construction and transportation improvement projects.  This funding was included in a supplemental budget signed by Governor Charlie Baker on Friday,   …Continue Reading Baker-Polito Administration Announces Additional Local Road and Bridge Funds