The Massachusetts Department of Transportation has announced that highway reconstruction activities are on schedule to be completed by the end of the year following the demolition of toll plazas on I-90 at 23 locations between New York and Boston.

One year ago, on the evening of October 28, 2016, manual toll collections ended and the Commonwealth transitioned to its All Electronic Tolling Program on I-90 (the Massachusetts Turnpike). Since last year, the AET system has processed approximately half a billion tolling transactions, with approximately 86% of trips occurring with customers using an E-ZPassMA transponder and receiving a toll discount in doing so.

toll-reconstruction-interchange-4-west-springfield-complete-october-2017

I-90 Interchange 4 in West Springfield

“Years of planning and design, the cooperation of the public, and strategic implementation of logistics at 23 work zones led to a successful transition in removing toll plaza infrastructure and activating electronic tolling,” said Transportation Secretary and CEO Stephanie Pollack. “We are already seeing time savings for drivers on areas of I-90 because removing toll plazas and redesigning the highway at these locations has meant that vehicles are not forced to slow down, jockey for position to pay tolls and then accelerate again. All Electronic Tolling was also implemented in order to increase safety and reduce harmful environmental emissions, and we believe these benefits are already being realized with this project.”

toll-reconstruction-allston-brighton-complete-october-27-2017

I-90 Interchange 18 in Allston/Brighton

“Thanks to the hard work of our MassDOT crews and contractors, toll demolition and road reconstruction work along I-90 is wrapping up just one year after construction operations began on October 28, 2016,” said Highway Administrator Jonathan Gulliver. “This transformative project was made possible by the hard work of many MassDOT engineers, planners, designers, crews, and contractors, and law enforcement officers, and we appreciate their efforts at improving and modernizing our highway in order to encourage safe and reliable travel.”

The status of each former toll plaza location is as follows:

Interchange 1 in West Stockbridge: All work is completed.

Interchange 2 in Lee: All work is completed.

Interchange 3 in Westfield: The Full Beneficial Use milestone has been reached. Landscaping work is ongoing and will be finished by early November 2017.

Interchange 4 in West Springfield: The Full Beneficial Use milestone has been reached and only punch-list items such as minor landscaping activities, site restoration, and cleanup remain.

Interchange 5 in Chicopee: The Full Beneficial Use milestone has been reached. Landscaping work is ongoing and expected to be finished by November 3, 2017.

Interchange 6 in Chicopee: Next week crews will install pavement markings. The Full Beneficial Use milestone is expected to be reached by November 3, 2017.

Interchange 7 in Ludlow: Next week crews will install pavement markings. The Full Beneficial Use milestone is expected to be reached by November 3, 2017.

Interchange 8 in Palmer: The Full Beneficial Use milestone has been reached and only punch-list items remain.

Interchange 9 in Sturbridge: All work is complete with the exception of highway lighting and landscaping.

Interchange 10 in Auburn: All work is complete with the exception of highway lighting and landscaping.

Interchange 10A in Millbury: All work is complete with the exception of highway lighting and landscaping.

Interchange 11 in Millbury/Worcester: All work is complete with the exception of highway lighting and landscaping.

Interchange 11A in Hopkinton: All work is complete with the exception of highway lighting and landscaping.

Interchange 12 in Framingham: All work is complete with the exception of highway lighting and landscaping.

Interchange 13 in Natick: All work is complete with the exception of highway lighting and landscaping.

Interchange 14 in Weston: The Full Beneficial Use milestone has been reached and only punch-list items remain.

Interchange 15 in Weston: The Full Beneficial Use milestone has been reached and only punch-list items remain.

Interchange 18 in Allston/Brighton: The Full Beneficial Use milestone has been reached and only punch-list items remain.

Interchange 30 at the Sumner Tunnel: At the request of key stakeholders and the local community, MassDOT updated its original design for this former toll plaza and separated it from the larger AET project by beginning construction operations in the spring of 2017. All reconstruction work is expected to be completed by summer 2018.

Interchange 31 at the Ted Williams Tunnel: Paving operations are ongoing and work is expected to be completed by November 10, 2017.

Interchange 37 at the Ted Williams Tunnel: Paving operations are ongoing and work is expected to be completed by November 10, 2017.

Written By:

Tags:

Recent Posts

MassDOT Announces almost $3 Million in Industrial Rail Access Program (IRAP) Grants posted on Sep 17

MassDOT Announces almost $3 Million in Industrial Rail Access Program (IRAP) Grants

The Massachusetts Department of Transportation (MassDOT) today announced seven grants totaling almost $3 million in awards from the Industrial Rail Access Program (IRAP) to enhance rail and freight access, economic opportunity, and job growth.

MassDOT Announces Eighth Annual Safe Streets Smart Trips High School Video Contest posted on Sep 14

MassDOT Announces Eighth Annual Safe Streets Smart Trips High School Video Contest

For immediate release: September 10, 2021 MassDOT Announces Eighth Annual Safe Streets Smart Trips High School Video Contest Applications need to be submitted by 5:00 p.m., on Wednesday, October 20, 2021 BOSTON – The Massachusetts Department of Transportation (MassDOT) is pleased to announce entries are   …Continue Reading MassDOT Announces Eighth Annual Safe Streets Smart Trips High School Video Contest

Statewide Exit Renumbering Work Complete posted on Sep 8

Statewide Exit Renumbering Work Complete

The Massachusetts Department of Transportation (MassDOT) is announcing it has completed converting all exit numbers on freeways to a milepost-based numbering system, per Federal Highway Administration (FHWA) requirements. Freeways in Massachusetts previously utilized a sequential exit numbering method.