Post Content

burns-bridge-apta-award-presented-january-23-2017MassDOT today was presented with the American Public Works Association’s (APWA) Public Works Project of the Year Award for the Kenneth F. Burns Memorial Bridge Replacement Project.  The $144 million project fully replaced the old Burns Bridge over Lake Quinsigamond and links Shrewsbury to Worcester.

The award was presented to MassDOT Secretary and CEO Stephanie Pollack and Highway Administrator Thomas Tinlin by the New England Chapter APWA, the regional chapter that nominated the project, at the Joint Meeting of the MassDOT Board of Directors and the Fiscal Management Control Board.

“We would like to thank the American Public Works Association for recognizing this signature project,” said Transportation Secretary and CEO Stephanie Pollack.  “The Kenneth F. Burns Memorial Bridge is an example of how MassDOT approaches new construction with the priority of building projects that encompass all modes of transportation and address the needs of the surrounding communities.  The people who use our infrastructure, whether by walking, cycling, or driving are the central focus of how we are building our infrastructure.”

The bridge project was completed four months ahead of the scheduled completion date of January 2016 and $5 million under the original $110 million budget. The new Burns Bridge replaced a 100-year old structurally deficient bridge.

The Burns Bridge project began in late June 2012 and was officially completed in August 2015. The contractor was Middlesex Corporation. The new five span steel deck arch structure provides three travel lanes in both directions on Route 9 with exclusive left and right-turn lanes on the westbound approach into Worcester. The bridge will accommodate projected increases in traffic and includes bicycle lanes and sidewalks in both directions of the bridge. The project also included improvements on Lake Avenue to the north and south of Route 9 to improve bicycle and pedestrian accommodations. The roadway profile has been raised in order to provide improved vertical under-clearance for recreational users of the Lake Quinsigamond.

Written By:

Tags:

Recent Posts

1.5 Million Massachusetts Residents Have Federally-Compliant REAL ID Credentials Issued by the Registry of Motor Vehicles Since 2018 posted on Feb 25

1.5 Million Massachusetts Residents Have Federally-Compliant REAL ID Credentials Issued by the Registry of Motor Vehicles Since 2018

The Massachusetts Registry of Motor Vehicles (RMV) is announcing that more than 1.5 million customers have secured a federally-compliant Massachusetts REAL ID credential from the RMV since the state’s March 2018 implementation date. While not everyone will need a REAL ID, obtaining one requires an   …Continue Reading 1.5 Million Massachusetts Residents Have Federally-Compliant REAL ID Credentials Issued by the Registry of Motor Vehicles Since 2018

MBTA Brings Real-Time Info to Eighteen High-Ridership Bus Stops posted on Feb 24

MBTA Brings Real-Time Info to Eighteen High-Ridership Bus Stops

The MBTA launched a first-of-its-kind pilot that brings real-time bus information beyond major transit hubs, to individual bus stops. The solar-powered electronic ink (E Ink) signs are located at eighteen bus stops in several Boston neighborhoods as well as stops in Chelsea, Everett, Cambridge, Watertown,   …Continue Reading MBTA Brings Real-Time Info to Eighteen High-Ridership Bus Stops

Southborough: I-90 Bridges Project Public Hearing February 27 posted on Feb 21

Southborough: I-90 Bridges Project Public Hearing February 27

MassDOT will hold a Design Public Hearing to discuss the replacement of several bridges in Southborough and Westborough as follows: Thursday, February 27, 6:30 p.m., Mary E. Finn Elementary School, 60 Richards Road, Southborough. The purpose of this hearing is to inform the public of   …Continue Reading Southborough: I-90 Bridges Project Public Hearing February 27