Post Content

93Fast14_500_Wide
MassDOT's "93Fast14" project achieved an historic success this weekend as work crews erected the final of 14 prefabricated bridge superstructures on I-93 in Medford.  The 14 deteriorated bridges that carry Interstate 93 over seven local roads in Medford have been replaced at a rate of at least one bridge per weekend this summer.  In every case, the work was completed and all roads reopened several hours ahead of schedule, well in advance of the Monday morning commute.

Federal Highway Administrator Victor Mendez called the 93Fast14 project the most ambitious bridge project in the country.  The project under normal circumstances would require at least 4 years of construction and lane closures.  MassDOT used cutting-edge techniques to safely complete the project much more quickly, including:

•    Design/Build: one joint venture team (J.F. White/Kiewit) is responsible for both design and construction.
•    Pre-fabricated bridge element system (PBES): a total of 252 prefabricated panels made of two steel I-beams with a concrete deck replace the old superstructures. They are prefabricated in a controlled, factory setting which results in high-quality concrete.  Once at the construction site, they are lifted into place using cranes.
•    Special “closure pour” concrete mix: This project uses a special rapid-set concrete for the “closure pours”— areas of poured concrete which connect the prefabricated panels.
•    “Zipper Lane” crossover: provides a safe work zone for drivers and workers and allows for the bridge demolition and replacement to occur in just 55 hours (or less).

The $98.1 million project to replace the fourteen bridge superstructures in Medford is funded through the Patrick-Murray Administration’s historic Accelerated Bridge Program, a $3 billion recovery effort to reduce the Commonwealth’s backlog of structurally-deficient bridges.

Completing the final superstructure erection this weekend is a major milestone for the project team, but work will continue.  During the last two weekends of August, MassDOT will perform weekend work requiring lane restrictions. Construction activities will also continue to occur during off-peak hours during weekdays and weekends after August.

For more information on the project, visit the 93Fast14 website.

Written By:

Recent Posts

Cambridge: Kendall Square Mobility Task Force posted on Apr 17

Cambridge: Kendall Square Mobility Task Force

The first meeting of MassDOT’s Kendall Square Mobility Task Force is scheduled as follows: Tuesday, April 28, 2015 from 4:00 PM – 6:00 PM at 600 Technology Square (corner of Main and Portland) – 3rd floor in Cambridge.  MassDOT’s Kendall Square Mobility Task Force process   …Continue Reading Cambridge: Kendall Square Mobility Task Force

MassDOT Receives Excellence in Transportation Award posted on Apr 16

MassDOT Receives Excellence in Transportation Award

The Massachusetts Department of Transportation (MassDOT) was recognized this week with an Excellence in Transportation Demand Management Award at the Association for Commuter Transportation’s (ACT) Regional Patriot Chapter Conference in Newport, Rhode Island. MassDOT was presented with an award for their Safe Streets Smart Trips   …Continue Reading MassDOT Receives Excellence in Transportation Award

MassDOT Approves Contract for Springfield I-91 Viaduct Project posted on Apr 15

MassDOT Approves Contract for Springfield I-91 Viaduct Project

MassDOT today awarded a contract for the rehabilitation of the I-91 viaduct structure in Springfield. The lowest responsible bid was submitted by the joint venture of JF White-Schiavone, $148,000,150. There were three bids in total. The total project cost of $183,325,172 includes railroad flaggers, traffic   …Continue Reading MassDOT Approves Contract for Springfield I-91 Viaduct Project