Post Content

93Fast14_500_Wide
MassDOT's "93Fast14" project achieved an historic success this weekend as work crews erected the final of 14 prefabricated bridge superstructures on I-93 in Medford.  The 14 deteriorated bridges that carry Interstate 93 over seven local roads in Medford have been replaced at a rate of at least one bridge per weekend this summer.  In every case, the work was completed and all roads reopened several hours ahead of schedule, well in advance of the Monday morning commute.

Federal Highway Administrator Victor Mendez called the 93Fast14 project the most ambitious bridge project in the country.  The project under normal circumstances would require at least 4 years of construction and lane closures.  MassDOT used cutting-edge techniques to safely complete the project much more quickly, including:

•    Design/Build: one joint venture team (J.F. White/Kiewit) is responsible for both design and construction.
•    Pre-fabricated bridge element system (PBES): a total of 252 prefabricated panels made of two steel I-beams with a concrete deck replace the old superstructures. They are prefabricated in a controlled, factory setting which results in high-quality concrete.  Once at the construction site, they are lifted into place using cranes.
•    Special “closure pour” concrete mix: This project uses a special rapid-set concrete for the “closure pours”— areas of poured concrete which connect the prefabricated panels.
•    “Zipper Lane” crossover: provides a safe work zone for drivers and workers and allows for the bridge demolition and replacement to occur in just 55 hours (or less).

The $98.1 million project to replace the fourteen bridge superstructures in Medford is funded through the Patrick-Murray Administration’s historic Accelerated Bridge Program, a $3 billion recovery effort to reduce the Commonwealth’s backlog of structurally-deficient bridges.

Completing the final superstructure erection this weekend is a major milestone for the project team, but work will continue.  During the last two weekends of August, MassDOT will perform weekend work requiring lane restrictions. Construction activities will also continue to occur during off-peak hours during weekdays and weekends after August.

For more information on the project, visit the 93Fast14 website.

Written By:

Recent Posts

Governor Patrick: Recommendation to Build MBTA Subway Cars in Massachusetts posted on Oct 21

Governor Patrick: Recommendation to Build MBTA Subway Cars in Massachusetts

Governor Deval Patrick today announced that the MBTA will present to the MassDOT Board of Directors the recommended company to manufacture and deliver 284 new subway cars for the Red and Orange Lines, replacing decades-old vehicles. Joined by MassDOT Secretary & CEO Richard A. Davey   …Continue Reading Governor Patrick: Recommendation to Build MBTA Subway Cars in Massachusetts

Students Restore Historic Massachusetts Public Works Truck posted on Oct 21

Students Restore Historic Massachusetts Public Works Truck

A 1947 Ford dump truck with the proud historic logo “Massachusetts Department of Public Works” is now being restored by students at Bristol/Plymouth Regional Technical School in Taunton. MassDOT Secretary of Transportation Richard Davey visited the school to check on the students’ work and the   …Continue Reading Students Restore Historic Massachusetts Public Works Truck

Celtics Forward Jared Sullinger Says: Sign Up for a Celtics Plate! posted on Oct 20

Celtics Forward Jared Sullinger Says: Sign Up for a Celtics Plate!

The Registry of Motor Vehicles’ new Boston Haymarket Center received a special visitor today: Boston Celtics forward Jared Sullinger.  “Sully” joined Registrar Celia Blue to greet visitors, meet the staff, and encourage customers to sign up for the Boston Celtics Specialty License Plate. The Celtics   …Continue Reading Celtics Forward Jared Sullinger Says: Sign Up for a Celtics Plate!