Post Content

93Fast14_500_Wide
MassDOT's "93Fast14" project achieved an historic success this weekend as work crews erected the final of 14 prefabricated bridge superstructures on I-93 in Medford.  The 14 deteriorated bridges that carry Interstate 93 over seven local roads in Medford have been replaced at a rate of at least one bridge per weekend this summer.  In every case, the work was completed and all roads reopened several hours ahead of schedule, well in advance of the Monday morning commute.

Federal Highway Administrator Victor Mendez called the 93Fast14 project the most ambitious bridge project in the country.  The project under normal circumstances would require at least 4 years of construction and lane closures.  MassDOT used cutting-edge techniques to safely complete the project much more quickly, including:

•    Design/Build: one joint venture team (J.F. White/Kiewit) is responsible for both design and construction.
•    Pre-fabricated bridge element system (PBES): a total of 252 prefabricated panels made of two steel I-beams with a concrete deck replace the old superstructures. They are prefabricated in a controlled, factory setting which results in high-quality concrete.  Once at the construction site, they are lifted into place using cranes.
•    Special “closure pour” concrete mix: This project uses a special rapid-set concrete for the “closure pours”— areas of poured concrete which connect the prefabricated panels.
•    “Zipper Lane” crossover: provides a safe work zone for drivers and workers and allows for the bridge demolition and replacement to occur in just 55 hours (or less).

The $98.1 million project to replace the fourteen bridge superstructures in Medford is funded through the Patrick-Murray Administration’s historic Accelerated Bridge Program, a $3 billion recovery effort to reduce the Commonwealth’s backlog of structurally-deficient bridges.

Completing the final superstructure erection this weekend is a major milestone for the project team, but work will continue.  During the last two weekends of August, MassDOT will perform weekend work requiring lane restrictions. Construction activities will also continue to occur during off-peak hours during weekdays and weekends after August.

For more information on the project, visit the 93Fast14 website.

Written By:

Recent Posts

I-90 Toll Plaza Demolition Construction Updates posted on Feb 24

I-90 Toll Plaza Demolition Construction Updates

The MassDOT I-90 Toll Demolition and Road Reconstruction Project continues with work at all 23 locations trending on or ahead of schedule. Each work location has its own unique traffic management and construction management plans. All work is contingent upon the weather. Please check the   …Continue Reading I-90 Toll Plaza Demolition Construction Updates

MassDOT Freight Plan Second Open House Set posted on Feb 22

MassDOT Freight Plan Second Open House Set

MassDOT is hosting the second Open House for the Massachusetts Freight Plan as follows: Thursday, March 9, 4:00 PM to 5:30 PM, The Conference Center at Bentley University, Room 325ABC (Third Floor), 175 Forest Street, LaCava Campus Center #300, Waltham The second Freight Advisory Committee   …Continue Reading MassDOT Freight Plan Second Open House Set

MBTA Names Design-Build Firms Interested in Green Line Extension Project posted on Feb 21

MBTA Names Design-Build Firms Interested in Green Line Extension Project

The MBTA has announced that an important step has been achieved for the Green Line Extension Project. The evaluation of the Statements of Qualifications (SOQ) for the project has been completed and three highly-qualified teams have been selected for the short list of firms that   …Continue Reading MBTA Names Design-Build Firms Interested in Green Line Extension Project