Post Content

93Fast14_500_Wide
MassDOT's "93Fast14" project achieved an historic success this weekend as work crews erected the final of 14 prefabricated bridge superstructures on I-93 in Medford.  The 14 deteriorated bridges that carry Interstate 93 over seven local roads in Medford have been replaced at a rate of at least one bridge per weekend this summer.  In every case, the work was completed and all roads reopened several hours ahead of schedule, well in advance of the Monday morning commute.

Federal Highway Administrator Victor Mendez called the 93Fast14 project the most ambitious bridge project in the country.  The project under normal circumstances would require at least 4 years of construction and lane closures.  MassDOT used cutting-edge techniques to safely complete the project much more quickly, including:

•    Design/Build: one joint venture team (J.F. White/Kiewit) is responsible for both design and construction.
•    Pre-fabricated bridge element system (PBES): a total of 252 prefabricated panels made of two steel I-beams with a concrete deck replace the old superstructures. They are prefabricated in a controlled, factory setting which results in high-quality concrete.  Once at the construction site, they are lifted into place using cranes.
•    Special “closure pour” concrete mix: This project uses a special rapid-set concrete for the “closure pours”— areas of poured concrete which connect the prefabricated panels.
•    “Zipper Lane” crossover: provides a safe work zone for drivers and workers and allows for the bridge demolition and replacement to occur in just 55 hours (or less).

The $98.1 million project to replace the fourteen bridge superstructures in Medford is funded through the Patrick-Murray Administration’s historic Accelerated Bridge Program, a $3 billion recovery effort to reduce the Commonwealth’s backlog of structurally-deficient bridges.

Completing the final superstructure erection this weekend is a major milestone for the project team, but work will continue.  During the last two weekends of August, MassDOT will perform weekend work requiring lane restrictions. Construction activities will also continue to occur during off-peak hours during weekdays and weekends after August.

For more information on the project, visit the 93Fast14 website.

Written By:

Recent Posts

Concord: New MBTA Commuter Rail Bridge to Roll into Place This Weekend posted on Aug 28

Concord: New MBTA Commuter Rail Bridge to Roll into Place This Weekend

As part of the ongoing rehabilitation of the Fitchburg Commuter Rail Line, the MBTA is replacing the old railroad bridge over Route 62/Main Street in Concord with a new bridge to be rolled into place Saturday, August 29. The current bridge has low clearance and   …Continue Reading Concord: New MBTA Commuter Rail Bridge to Roll into Place This Weekend

Knowledge Corridor: New Holyoke Train Station Celebrated posted on Aug 27

Knowledge Corridor: New Holyoke Train Station Celebrated

Lt. Governor Karyn Polito and MassDOT Secretary and CEO Stephanie Pollack today joined Holyoke Mayor Alex Morse along with state and local officials to celebrate the opening of the new $4.3 million Holyoke Train Station on the Knowledge Corridor and restoration of Amtrak Vermonter Line   …Continue Reading Knowledge Corridor: New Holyoke Train Station Celebrated

MBTA Winter Resiliency Update: Red Line, Orange Line posted on Aug 26

MBTA Winter Resiliency Update: Red Line, Orange Line

Beginning Saturday, August 29th, and continuing on selected weekends through the remainder of the summer, Red Line service between JFK/UMass and Quincy will be temporarily suspended to allow workers to make the subway more resilient to harsh winter weather conditions. On weekends when workers will   …Continue Reading MBTA Winter Resiliency Update: Red Line, Orange Line