Post Content

93Fast14_500_Wide
MassDOT's "93Fast14" project achieved an historic success this weekend as work crews erected the final of 14 prefabricated bridge superstructures on I-93 in Medford.  The 14 deteriorated bridges that carry Interstate 93 over seven local roads in Medford have been replaced at a rate of at least one bridge per weekend this summer.  In every case, the work was completed and all roads reopened several hours ahead of schedule, well in advance of the Monday morning commute.

Federal Highway Administrator Victor Mendez called the 93Fast14 project the most ambitious bridge project in the country.  The project under normal circumstances would require at least 4 years of construction and lane closures.  MassDOT used cutting-edge techniques to safely complete the project much more quickly, including:

•    Design/Build: one joint venture team (J.F. White/Kiewit) is responsible for both design and construction.
•    Pre-fabricated bridge element system (PBES): a total of 252 prefabricated panels made of two steel I-beams with a concrete deck replace the old superstructures. They are prefabricated in a controlled, factory setting which results in high-quality concrete.  Once at the construction site, they are lifted into place using cranes.
•    Special “closure pour” concrete mix: This project uses a special rapid-set concrete for the “closure pours”— areas of poured concrete which connect the prefabricated panels.
•    “Zipper Lane” crossover: provides a safe work zone for drivers and workers and allows for the bridge demolition and replacement to occur in just 55 hours (or less).

The $98.1 million project to replace the fourteen bridge superstructures in Medford is funded through the Patrick-Murray Administration’s historic Accelerated Bridge Program, a $3 billion recovery effort to reduce the Commonwealth’s backlog of structurally-deficient bridges.

Completing the final superstructure erection this weekend is a major milestone for the project team, but work will continue.  During the last two weekends of August, MassDOT will perform weekend work requiring lane restrictions. Construction activities will also continue to occur during off-peak hours during weekdays and weekends after August.

For more information on the project, visit the 93Fast14 website.

Written By:

Recent Posts

Fall River Route 79 Project: Ramp Closures May 28 posted on May 26

Fall River Route 79 Project: Ramp Closures May 28

MassDOT will close the on-ramps to I-195 east and westbound from Route 79/138 and Broadway northbound, and from Central Street at Durfee Street/Milliken Boulevard on Thursday, May 28. The closures are necessary to demolish and reconstruct the last two elevated bridges as part of the   …Continue Reading Fall River Route 79 Project: Ramp Closures May 28

MassDOT, Mapfre Insurance Encourage Safe Summer Driving posted on May 24

MassDOT, Mapfre Insurance Encourage Safe Summer Driving

In time for Memorial Day, the kick-off to the summer driving season, MassDOT Acting Highway Administrator Thomas Tinlin joined MAPFRE Insurance in reminding motorists to adhere to speed limits, obey traffic laws and avoid distracted driving when traveling during the summer months. According to data   …Continue Reading MassDOT, Mapfre Insurance Encourage Safe Summer Driving

Chelsea: Silver Line Gateway Project Bridge Closure posted on May 22

Chelsea: Silver Line Gateway Project Bridge Closure

MassDOT will close the Washington Avenue Bridge in Chelsea on Tuesday, May 26 at 10:00 AM as part of the Silver Line Gateway Project.  Appropriate detour signs will be in place to redirect traffic and pedestrians, and identify relocated bus stops.  The bridge closure is   …Continue Reading Chelsea: Silver Line Gateway Project Bridge Closure