Post Content

93Fast14_500_Wide
MassDOT's "93Fast14" project achieved an historic success this weekend as work crews erected the final of 14 prefabricated bridge superstructures on I-93 in Medford.  The 14 deteriorated bridges that carry Interstate 93 over seven local roads in Medford have been replaced at a rate of at least one bridge per weekend this summer.  In every case, the work was completed and all roads reopened several hours ahead of schedule, well in advance of the Monday morning commute.

Federal Highway Administrator Victor Mendez called the 93Fast14 project the most ambitious bridge project in the country.  The project under normal circumstances would require at least 4 years of construction and lane closures.  MassDOT used cutting-edge techniques to safely complete the project much more quickly, including:

•    Design/Build: one joint venture team (J.F. White/Kiewit) is responsible for both design and construction.
•    Pre-fabricated bridge element system (PBES): a total of 252 prefabricated panels made of two steel I-beams with a concrete deck replace the old superstructures. They are prefabricated in a controlled, factory setting which results in high-quality concrete.  Once at the construction site, they are lifted into place using cranes.
•    Special “closure pour” concrete mix: This project uses a special rapid-set concrete for the “closure pours”— areas of poured concrete which connect the prefabricated panels.
•    “Zipper Lane” crossover: provides a safe work zone for drivers and workers and allows for the bridge demolition and replacement to occur in just 55 hours (or less).

The $98.1 million project to replace the fourteen bridge superstructures in Medford is funded through the Patrick-Murray Administration’s historic Accelerated Bridge Program, a $3 billion recovery effort to reduce the Commonwealth’s backlog of structurally-deficient bridges.

Completing the final superstructure erection this weekend is a major milestone for the project team, but work will continue.  During the last two weekends of August, MassDOT will perform weekend work requiring lane restrictions. Construction activities will also continue to occur during off-peak hours during weekdays and weekends after August.

For more information on the project, visit the 93Fast14 website.

Written By:

Recent Posts

Route 79/Braga Bridge Project Traffic Update posted on Oct 30

Route 79/Braga Bridge Project Traffic Update

MassDOT will begin implementing traffic changes for the next stage of construction for the Route 79/Braga Bridge Project on Wednesday, November 12. The following changes will be implemented in a phased approach through the middle of December: Vehicles on Route 79/138 (Broadway) bound for Interstate   …Continue Reading Route 79/Braga Bridge Project Traffic Update

RMV: Promise to Customers posted on Oct 28

RMV: Promise to Customers

Today, MassDOT Secretary & CEO Richard A. Davey and MassDOT Registrar of Motor Vehicles Celia J. Blue offered a 10 point promise to RMV customers. The reimagining effort comprises current, ongoing and future initiatives that the RMV has in development to better the Registry experience.   …Continue Reading RMV: Promise to Customers

November E-ZPass Sign Up: Chelsea, Everett posted on Oct 28

November E-ZPass Sign Up: Chelsea, Everett

MassDOT is encouraging motorists to join E-ZPass with All-Electronic Tolling now in place on the Tobin Bridge and expanding statewide within the next two years. The E-ZPass Street Team will be enrolling new customers in the E-ZPass throughout the Fall season. The E-ZPass Van schedule   …Continue Reading November E-ZPass Sign Up: Chelsea, Everett