Medford 93Fast14_250
On Friday night, May 6th through early Saturday morning, May 7th, MassDOT will execute a full test deployment of the median crossover operation on I-93 between Stoneham and Somerville that will be used on weekends this summer to replace 14 bridges on I-93 in Medford. 

The test deployment will bring the existing interstate highway from four-lanes in each direction to two-lanes in each direction, running in counter-flow operation on the southbound barrel of the highway.
The median crossover test is necessary to model the traffic management plan and will be fully coordinated with the Massachusetts State Police and the Fast 14 contractor. 

I-93 directional traffic will be separated by a moveable “zipper lane” barrier throughout the 4.5 mile length of the crossover.  One local access lane will be provided on the closed section of I-93 northbound to provide access to all of the ramps for Exits 31 through 33.  The test deployment will also execute the procedures established by MassDOT for re-opening the interstate highway to full lane capacity by 5 AM on Saturday, May 7th. Specific details on the test deployment follow below:

Route I-93 Southbound –
•    On Friday May 6th, I-93 SB will be restricted to two lanes south of Exit 35 (Winchester Highlands/Melrose) beginning with a single lane closure at 8 PM to initiate the movable “zipper lane” barrier setup. The second lane closure will follow to complete the installation of the movable barrier for use of the crossover by 10 PM. 
I-93 SB will remain restricted to 2 travel lanes from south of Exit 35 to north of Exit 28 (Sullivan Square) between 10 PM Friday, May 6th and 5 AM Saturday, May 7th.
•    All of the southbound entrance and exit ramps on I-93 between Exit 33 (Roosevelt Circle – Route 28/Fellsway) and Exit 28 (Sullivan Square) will remain open.  The entrance ramp from Route 28/Fellsway West in Stoneham to I-93 southbound will be closed between 8 PM Friday, May 6th and 5 AM Saturday, May 7th.
•    Through traffic travelling south on I-93 will be restricted to the right two travel lanes with the northbound traffic located in the adjacent left lanes separated by the movable barrier. All I-93 through traffic will be located within the southbound barrel of the highway in a counter-flow operation. The shoulder lane will not be used as a travel lane, but will be available for emergency vehicle access and disabled vehicles.
•    Three lanes will be provided on I-93 SB just north of Exit 28 (Sullivan Square/ Charlestown) and adjacent to the start of the HOV lane. 

Route I-93 Northbound –
•    On Friday May 6th, I-93 NB will be restricted to two lanes north of Exit 29 (Route 28/38 – Somerville/Everett) beginning with a single lane closure at 8 PM to initiate the crossover implementation.  The second lane closure will follow thereafter to complete the installation of the median crossover by 10 PM.  Through traffic on I-93 NB will remain restricted to 2 travel lanes from north of Exit 29 (Route 28/38 – Somerville/Everett) to north of Exit 33 (Roosevelt Circle – Route 28/Fellsway) between 10 PM Friday, May 6th and 5 AM Saturday, May 7th.
•    Beyond the crossover point, one lane of local ramp access will be provided on I-93 northbound to service all of the ramps between Exits 31 (Mystic Valley Parkway/ Arlington) and Exit 33 (Roosevelt Circle – Route 28/Fellsway).  Traffic in the local access lane will be restricted to one travel lane.  Any traffic entering I-93 NB from the on ramps between Exits 31 and 33 will merge back with I-93 NB through traffic exiting the northerly crossover in the area prior to Exit 34 (Route 28 North – Stoneham/Melrose).            
•    Through traffic travelling north on I-93 will be restricted to two lanes which will cross over the median and travel in the southbound side of the highway, separated from the SB traffic by the movable barrier. There will not be a shoulder lane available for the northbound direction between 8 PM Friday, May 6th and Saturday, May 7th. 

MassDOT encourages drivers to allow extra time for their trips and to reduce speed and use caution when travelling through all work zones.  For more information or to sign up to receive future updates and schedule information, visit the project’s website at www.mass.gov/massdot/93fast14.     

Written By:

Recent Posts

Boston: I-90 Eastbound 4th Lane Reopens at Commonwealth Avenue Bridge posted on Jun 26

Boston: I-90 Eastbound 4th Lane Reopens at Commonwealth Avenue Bridge

MassDOT today announced the restoration of a fourth lane on I-90 Eastbound from the Commonwealth Avenue bridge to the Prudential Tunnel in Boston. The restoration of four travel lanes comes after MassDOT completed safety upgrades by replacing the median system with a new jersey barrier   …Continue Reading Boston: I-90 Eastbound 4th Lane Reopens at Commonwealth Avenue Bridge

RMV: 2016 Low Number Plate Lottery Applications Now Accepted posted on Jun 25

RMV: 2016 Low Number Plate Lottery Applications Now Accepted

MassDOT Registrar of Motor Vehicles Erin Deveney announced that applications for the 2016 Low Number Plate Lottery are now being accepted online or by U.S. mail. Starting this year, for the first time ever, customers will be able to enter the lottery online by visiting:    …Continue Reading RMV: 2016 Low Number Plate Lottery Applications Now Accepted

Casey Arborway Project Public Meeting Set posted on Jun 24

Casey Arborway Project Public Meeting Set

MassDOT has scheduled a fourth Casey Arborway Project Construction Update Meeting as follows: Wednesday, June 29, 6:30-8:30 PM, Boston English High School Auditorium 144 McBride Street, Jamaica Plain The purpose of this meeting will be to provide the community with an update on the progress   …Continue Reading Casey Arborway Project Public Meeting Set