Post Content

Medford_I_93_Map_March_2011Beginning on Monday, March 14th, work crews will begin construction activities in preparation for the upcoming replacement of 14 deteriorated bridge superstructures on I-93 in Medford. 

The $98.1 million project is funded through the Patrick-Murray Administration’s historic $3 billion Accelerated Bridge Program to reduce the Commonwealth’s backlog of structurally-deficient bridges.  The project known as “93Fast14” is using an innovative approach that will expedite the work, with major construction in June-August and completion in 2011.

The preliminary work commencing next week will focus on the construction of temporary median crossovers at the northern and southern limits of the project.  These crossovers will be used during the majority of weekends this summer to allow the bridge replacement activities to occur. 

The following overnight lane restrictions are scheduled for next week:

I-93 Northbound

Monday evening, March 14th- Thursday morning, March 17th, 8:00pm-5:00am– The left lane will be closed in the area beyond Exit 29 (Routes 28/38) near the Somerville/Medford line.
 
Thursday evening, March 17th- Saturday morning, March 19th, 8:00pm-5:00am-  The left lane will be closed in the area beyond Exit 33 (Route 28) near the Medford/Stoneham line.
 
I-93 Southbound

Monday evening, March 14th- Wednesday morning, March 16th, 8:00pm-5:00am– The left lane will be closed in the area beyond Exit 30 (Route 38) near the Medford/Somerville line.
 
Wednesday evening, March 16th- Saturday morning, March 19th, 8:00pm-5:00am-  The left lane will be closed in the area near Exit 30 (Route 38) near the Medford/Somerville line.  A second left lane will be closed on these evenings in this same area between 9:00 PM and 5:00 AM.

Thursday evening, March 17th- Saturday morning, March 19th, 8:00pm-5:00am– The left lane will be closed in the area prior to Exit 33 (Route 28) near the Medford/Stoneham line.
 
Appropriate signs, channelizing devices and traffic control measures will be used to guide drivers through the work zone.  MassDOT encourages drivers to allow extra time for their trips and to reduce speed and use caution when travelling through the work zone.

The “93Fast14” is using an innovative design-build procurement process to accelerate project development, enabling construction to begin quickly.  To minimize traffic impacts and streamline construction, the project features modular bridge technology, enabling much of the work to be performed off-site.  The bridge replacement units will be built at remote fabrication facilities and then shipped to the site. During a series of ten weekends between June and August, the replacement units will be put into place using heavy lifting equipment. In order to demolish the existing bridges and replace them with the new units, MassDOT will close the necessary bridge location and cross traffic from one side of I-93 to the other, maintaining two lanes of traffic in each direction at all times. The rapid construction techniques employed by MassDOT will allow all travel lanes to be fully reopened each Monday morning.

For more information or to sign up to receive future updates and schedule information, visit the project’s website at www.mass.gov/massdot/93fast14

Written By:

Recent Posts

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th posted on Jul 26

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

This is a reminder that the 2017 Construction Shutdown for the Commonwealth Avenue Bridge Replacement Project is beginning at 9:00 PM today, Wednesday July 26, and will continue through 5:00 AM on Monday, August 14. Please note the construction-related impacts below: For Pedestrians and Bicyclists:   …Continue Reading Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

Springfield: I-91 Viaduct Rehabilitation Progress Continues posted on Jul 24

Springfield: I-91 Viaduct Rehabilitation Progress Continues

MassDOT and its contractor, the Joint Venture of White-Schiavone (JV), continue to make progress on rehabilitation of the Interstate 91 Viaduct (I-91) through Springfield. The contractor completed reconstruction of the center lanes of the highway last fall, and began Stage 2 of construction in November   …Continue Reading Springfield: I-91 Viaduct Rehabilitation Progress Continues

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts posted on Jul 23

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts

MassDOT is reminding the public that travel impacts will begin next week throughout the Boston University/Saint Paul Street neighborhood of Boston along Commonwealth Avenue due to the Commonwealth Avenue Bridge Replacement Project. Drivers on Commonwealth Avenue, the BU Bridge and I-90 will see lane closings   …Continue Reading Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts