Post Content

Morton Street Bridge A MassDOT Public Information Meeting to discuss the proposed Morton Street Bridge Replacement Project over the MBTA Railroad in the City of Boston is scheduled as follows:

Monday, December 13, 6:30pm, Mildred Avenue Community Center, 5 Mildred Avenue, Mattapan

The meeting will provide the public with a follow up to the previous public meeting, with issues to be discussed to include the auto, bus and pedestrian routes during the 10-day Rapid Construction closure. All views and comments made at this meeting will be carefully reviewed and considered.

The Morton Street Bridge project funded by Governor Patrick's Accelerated Bridge Program will replace the bridge carrying Morton Street over the MBTA Railroad. Rapid bridge construction techniques will allow two-way traffic to be maintained over the bridge during construction, except for a 10-day period when the bridge superstructure demolition and installation will take place. Access to local businesses and residences will be maintained during this 10-day period.The work will include complete replacement of the superstructure and construction of new abutments in front of the existing abutments and behind the existing piers, along with roadway approaches.

A secure right-of-way is necessary for this project. Acquisitions in fee and permanent or temporary easements may be required. MassDOT’s policy concerning land acquisitions will be discussed at the meeting.

 Plans will be on display one-half hour before the meeting begins, with an engineer in attendance to answer questions.  Learn more about the Accelerated Bridge Program.

Written By:

Recent Posts

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th posted on Jul 26

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

This is a reminder that the 2017 Construction Shutdown for the Commonwealth Avenue Bridge Replacement Project is beginning at 9:00 PM today, Wednesday July 26, and will continue through 5:00 AM on Monday, August 14. Please note the construction-related impacts below: For Pedestrians and Bicyclists:   …Continue Reading Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

Springfield: I-91 Viaduct Rehabilitation Progress Continues posted on Jul 24

Springfield: I-91 Viaduct Rehabilitation Progress Continues

MassDOT and its contractor, the Joint Venture of White-Schiavone (JV), continue to make progress on rehabilitation of the Interstate 91 Viaduct (I-91) through Springfield. The contractor completed reconstruction of the center lanes of the highway last fall, and began Stage 2 of construction in November   …Continue Reading Springfield: I-91 Viaduct Rehabilitation Progress Continues

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts posted on Jul 23

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts

MassDOT is reminding the public that travel impacts will begin next week throughout the Boston University/Saint Paul Street neighborhood of Boston along Commonwealth Avenue due to the Commonwealth Avenue Bridge Replacement Project. Drivers on Commonwealth Avenue, the BU Bridge and I-90 will see lane closings   …Continue Reading Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts