North Adams, Hadley Overpass Truss, January 23, 2013MassDOT's Hadley Overpass project in North Adams is moving into later stages of construction this winter with steel repairs underneath the bridge.

The $34.5 million project is reconstructing the Hadley Overpass bridge carrying Route 8/State Street over the Hoosic River and the B&M Railroad.  The project has been completed in stages to maintain two-way travel over the bridge during construction.  Current work is focused on steel repairs underneath the bridge deck on the west side of the center span.

Beginning next week, crews will begin replacing the bridge deck on the west side of the bridge, with the existing traffic configuration in place.

In early summer 2013, traffic will be relocated to the west side of the bridge to allow the contractor to continue steel repairs and begin deck replacement on the east side of the bridge.

Traffic is expected to shift again in early fall, with northbound traffic shifted to the east side of the bridge and southbound traffic shifted to the west side.  This will allow crews to perform steel repairs underneath the bridge and replace the center bridge deck. 

Most construction is expected to be completed in late 2013, allowing full use of the bridge for motorists.  Final painting of the bridge truss is scheduled for the spring of 2014, with no traffic impact. 

MassDOT encourages drivers to reduce speed when traveling through the area and watch for traffic configuration changes.

Written By:

Recent Posts

MassDOT Freight Plan Second Open House Set posted on Feb 22

MassDOT Freight Plan Second Open House Set

MassDOT is hosting the second Open House for the Massachusetts Freight Plan as follows: Thursday, March 9, 4:00 PM to 5:30 PM, The Conference Center at Bentley University, Room 325ABC (Third Floor), 175 Forest Street, LaCava Campus Center #300, Waltham The second Freight Advisory Committee   …Continue Reading MassDOT Freight Plan Second Open House Set

MBTA Names Design-Build Firms Interested in Green Line Extension Project posted on Feb 21

MBTA Names Design-Build Firms Interested in Green Line Extension Project

The MBTA has announced that an important step has been achieved for the Green Line Extension Project. The evaluation of the Statements of Qualifications (SOQ) for the project has been completed and three highly-qualified teams have been selected for the short list of firms that   …Continue Reading MBTA Names Design-Build Firms Interested in Green Line Extension Project

MassDOT: Federal Emergency Management Agency Reimbursements posted on Feb 18

MassDOT: Federal Emergency Management Agency Reimbursements

MassDOT has succeeded in recovering more than $21 million dollars from the Federal Emergency Management Agency (FEMA) in 2016 for past disaster events. These are reimbursements for MassDOT operations and logistics during past federal government disaster declarations and the reimbursements have been deposited into the   …Continue Reading MassDOT: Federal Emergency Management Agency Reimbursements