Route 2 Irene Damage 1 MassDOT has assembled a map showing the closed portion of Route 2 that suffered significant damage due to flooding from Tropical Storm Irene and outlining the current posted detour.

Route 2 is closed from Mile Marker 21.6 in Florida to Mile Marker 27.5 in Charlemont, with damage including severe slope failures, roadway undermining and instability, eroded bridge approaches, mud slides, and culvert and retaining wall damage.

The significant damage and necessary repairs require an extended period of time to restore the roadway, and MassDOT is committed to an accelerated repair process. 

Please review the Route 2 damage and detour route map to learn more and view photos of the damage.

The Detour Route is also listed below.

From North Adams: 

Route 8, Adams, to Route 116 through Adams, Savoy, Plainfield, and Ashfield,

to Route 112 through Ashfield and Buckland,

to Route 2, East Charlemont.

Written By:

Recent Posts

Casey Arborway Project Public Meeting Set posted on Jun 24

Casey Arborway Project Public Meeting Set

MassDOT has scheduled a fourth Casey Arborway Project Construction Update Meeting as follows: Wednesday, June 29, 6:30-8:30 PM, Boston English High School Auditorium 144 McBride Street, Jamaica Plain The purpose of this meeting will be to provide the community with an update on the progress   …Continue Reading Casey Arborway Project Public Meeting Set

Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration posted on Jun 23

Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration

MassDOT announced that the restoration of the iconic “salt and pepper” towers of the historic Longfellow Bridge will be complete in late July. The downstream towers have been replaced on the bridge, and barges are transporting the last stones for installation on them. The capstones   …Continue Reading Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration

New Tunnels Gantry Infrastructure to be Installed posted on Jun 22

New Tunnels Gantry Infrastructure to be Installed

MassDOT has announced that new infrastructure for two vertical gantry supports on the East Boston sides of the Sumner and Callahan Tunnels will begin to be installed late tonight, June 22.  Installation work will continue during off-peak hours during the next several days with gantries   …Continue Reading New Tunnels Gantry Infrastructure to be Installed