Post Content

Route 2 Charlemont-Savoy Repairs, October 18, 2011MassDOT's Route 2 Hurricane Irene Emergency Repairs Project has been named a 2012 Public Works Project of the Year by the American Public Works Association (APWA), a not-for-profit, international organization of more than 28,500 members involved in the field of public works.

MassDOT's Highway Division and primary contractors JX Maxymillian, Inc., Northern Construction, ET&L Corp., and R. Bates & Sons received the honors.  MassDOT's Project of the Year award is in the Disasters/Emergency Construction/Repair category.  

The 2011 Hurricane Irene Repairs Project reconstructed Route 2 following floodwaters’ extreme damage in the towns of North Adams, Florida, Savoy, and Charlemont.  The storm damaged bridges, destabilized embankments, washed out pavement, and covered roads with dirt and storm debris.   Route 2 was closed from mile marker 21.6 in Florida to mile marker 27.4 in Charlemont, and portions were reduced to one lane with only a temporary signal that allowed alternating traffic.

MassDOT engineers mobilized immediately by assessing damage, designing repairs, and developing emergency repair work orders. The first contractor, J.H. Maxymillian, began to clear the roadway and within weeks contractors were working to stabilize and repair slopes and retaining walls. By mid-November, MassDOT had advanced the bridge project, including slope repairs adjacent to the bridge.

Just 110 days after the storm, all portions of Route 2 were reopened to traffic. MassDOT provided frequent public outreach activities to keep the public informed of road conditions and the construction schedule.

According to APWA, "the outstanding accomplishment of the Hurricane Irene Repairs Project was its completion in a short amount of time. MassDOT had accelerated the design of repairs and the procurement to get crews started right away. Four crews worked around the clock as needed to get the work done as soon as possible. MassDOT and the contractors completed the work on schedule despite an unusual October snowstorm that dumped two feet of heavy snow on the area."

The APWA Public Works Projects of the Year awards are presented each year to promote excellence in the management and administration of public works projects.

Written By:

Recent Posts

Fore River Bridge Project Milestone posted on Jul 29

Fore River Bridge Project Milestone

The Fore River Bridge Replacement Project in Quincy-Weymouth continues during the summer of 2014 with installation of the permanent bridge components along with a new milestone: arrival of the new bridge steel sections. The view above shows the progress made at the Quincy tower location.   …Continue Reading Fore River Bridge Project Milestone

Green Line Extension: Public Meeting July 31 posted on Jul 28

Green Line Extension: Public Meeting July 31

A City of Somerville and MBTA Green Line Extension Public Meeting regarding Medford Street Bridge construction has been scheduled for the following: Thursday, July 31, 6:00pm, Public Safety Building, 220 Washington Street, Somerville. Green Line Extension construction is underway and will involve periodic traffic impacts   …Continue Reading Green Line Extension: Public Meeting July 31

MBTA: New WiFi System Announced posted on Jul 24

MBTA: New WiFi System Announced

Under a new license agreement signed today by MBTA General Manager Beverly Scott, a state-of-the-art WiFi system will be installed throughout the MBTA’s sprawling network of fourteen Commuter Rail lines. At no cost to the MBTA or its customers, inMOTION Wireless, Inc. will build a   …Continue Reading MBTA: New WiFi System Announced