Post Content

Route 2 Charlemont-Savoy Repairs, October 18, 2011MassDOT's Route 2 Hurricane Irene Emergency Repairs Project has been named a 2012 Public Works Project of the Year by the American Public Works Association (APWA), a not-for-profit, international organization of more than 28,500 members involved in the field of public works.

MassDOT's Highway Division and primary contractors JX Maxymillian, Inc., Northern Construction, ET&L Corp., and R. Bates & Sons received the honors.  MassDOT's Project of the Year award is in the Disasters/Emergency Construction/Repair category.  

The 2011 Hurricane Irene Repairs Project reconstructed Route 2 following floodwaters’ extreme damage in the towns of North Adams, Florida, Savoy, and Charlemont.  The storm damaged bridges, destabilized embankments, washed out pavement, and covered roads with dirt and storm debris.   Route 2 was closed from mile marker 21.6 in Florida to mile marker 27.4 in Charlemont, and portions were reduced to one lane with only a temporary signal that allowed alternating traffic.

MassDOT engineers mobilized immediately by assessing damage, designing repairs, and developing emergency repair work orders. The first contractor, J.H. Maxymillian, began to clear the roadway and within weeks contractors were working to stabilize and repair slopes and retaining walls. By mid-November, MassDOT had advanced the bridge project, including slope repairs adjacent to the bridge.

Just 110 days after the storm, all portions of Route 2 were reopened to traffic. MassDOT provided frequent public outreach activities to keep the public informed of road conditions and the construction schedule.

According to APWA, "the outstanding accomplishment of the Hurricane Irene Repairs Project was its completion in a short amount of time. MassDOT had accelerated the design of repairs and the procurement to get crews started right away. Four crews worked around the clock as needed to get the work done as soon as possible. MassDOT and the contractors completed the work on schedule despite an unusual October snowstorm that dumped two feet of heavy snow on the area."

The APWA Public Works Projects of the Year awards are presented each year to promote excellence in the management and administration of public works projects.

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour