Post Content

Route 2 Charlemont-Savoy Repairs, October 18, 2011MassDOT's Route 2 Hurricane Irene Emergency Repairs Project has been named a 2012 Public Works Project of the Year by the American Public Works Association (APWA), a not-for-profit, international organization of more than 28,500 members involved in the field of public works.

MassDOT's Highway Division and primary contractors JX Maxymillian, Inc., Northern Construction, ET&L Corp., and R. Bates & Sons received the honors.  MassDOT's Project of the Year award is in the Disasters/Emergency Construction/Repair category.  

The 2011 Hurricane Irene Repairs Project reconstructed Route 2 following floodwaters’ extreme damage in the towns of North Adams, Florida, Savoy, and Charlemont.  The storm damaged bridges, destabilized embankments, washed out pavement, and covered roads with dirt and storm debris.   Route 2 was closed from mile marker 21.6 in Florida to mile marker 27.4 in Charlemont, and portions were reduced to one lane with only a temporary signal that allowed alternating traffic.

MassDOT engineers mobilized immediately by assessing damage, designing repairs, and developing emergency repair work orders. The first contractor, J.H. Maxymillian, began to clear the roadway and within weeks contractors were working to stabilize and repair slopes and retaining walls. By mid-November, MassDOT had advanced the bridge project, including slope repairs adjacent to the bridge.

Just 110 days after the storm, all portions of Route 2 were reopened to traffic. MassDOT provided frequent public outreach activities to keep the public informed of road conditions and the construction schedule.

According to APWA, "the outstanding accomplishment of the Hurricane Irene Repairs Project was its completion in a short amount of time. MassDOT had accelerated the design of repairs and the procurement to get crews started right away. Four crews worked around the clock as needed to get the work done as soon as possible. MassDOT and the contractors completed the work on schedule despite an unusual October snowstorm that dumped two feet of heavy snow on the area."

The APWA Public Works Projects of the Year awards are presented each year to promote excellence in the management and administration of public works projects.

Written By:

Recent Posts

MBTA: Weekend Commuter Boat Service Returns May 28 posted on May 26

MBTA: Weekend Commuter Boat Service Returns May 28

MassDOT weekend commuter boat service will be provided for the third year between Hingham, Hull, Georges Island, Grape Island and Boston. The service begins Memorial Day weekend and will continue through the Labor Day weekend. “Commuter ferry service on the weekends during the two previous   …Continue Reading MBTA: Weekend Commuter Boat Service Returns May 28

Boston: Commonwealth Avenue Bridge Project Community Meeting posted on May 26

Boston: Commonwealth Avenue Bridge Project Community Meeting

MassDOT has scheduled a community meeting for the Commonwealth Avenue Bridge Reconstruction Project as follows:   Thursday, June 2, 6:00 PM to 8:00 PM, Jacob Sleeper Auditorium (CGS 129), Boston University, 871 Commonwealth Avenue. The Commonwealth Avenue Bridge Reconstruction Project will replace the existing superstructure   …Continue Reading Boston: Commonwealth Avenue Bridge Project Community Meeting

Plan Ahead for Memorial Day Weekend Travel posted on May 24

Plan Ahead for Memorial Day Weekend Travel

MassDOT encourages travelers to plan ahead and travel safely during the Memorial Day holiday weekend.  The heaviest traffic is observed during Thursday, Friday, and Monday afternoons and early evenings.  Drivers are encouraged to make travel plans accordingly and if possible avoid peak traffic volumes between   …Continue Reading Plan Ahead for Memorial Day Weekend Travel