Post Content

Route 2 Irene Damage 1

MassDOT Secretary Richard A. Davey announced today that work to reconstruct the six-mile section of Route 2 devastated by Tropical Storm Irene will begin early next week.

The roadway linking the communities of North Adams, Florida, Savoy, and Charlemont suffered major damage from the storm and flooding, making it impassable to traffic. Reconstruction is expected to cost $34.5 million and work under an accelerated bidding process will begin early next week.  The roadway is expected to re-open to traffic by mid-December.  

MassDOT has assembled a map showing the closed portion of Route 2 that suffered significant damage due to flooding from Tropical Storm Irene and outlining the current posted detour.

Route 2 is closed from Mile Marker 21.6 in Florida to Mile Marker 27.5 in Charlemont.

“Governor Patrick has been clear: reopening Route 2 is a top priority.  We are working as quickly as possible to open the road again for safety and connectivity reasons, but also to reopen a popular area for tourism,” said Secretary Davey.


Route 2 is a critical roadway for affected communities and businesses, connecting residents to key arteries including I-91 and to Albany, New York.

Highway Administrator DePaola said the combination of roadway washout and substantial damage to retaining walls, and man-made slopes, will require an innovative approach to re-opening the road.

“What we’ll be doing is breaking down the repairs into separate jobs so that contractors can get out there and begin work simultaneously in order to get this road back open to traffic,” said Administrator DePaola. 

The work is being done under an expedited bidding process, with designs completed, bids solicited, and contracts signed in a span of three weeks.  Two areas of slope repairs and road reconstruction in North Adams and Florida will begin immediately at a total cost of approximately $11.5 million.  

A separate $7.5 million expedited contract early in October will include reconstruction of Route 2 farther east in the towns of Savoy and Charlemont.  A final estimated $15.5 million contract this fall will include reconstruction of portions of retaining walls between Savoy and Charlemont, which can occur with the road re-opened to traffic.  MassDOT will seek federal reimbursement for costs associated with these repairs. 

Written By:

Recent Posts

MassDOT Secretary Announces MBTA Leadership Team posted on Jul 30

MassDOT Secretary Announces MBTA Leadership Team

Today, MassDOT Secretary Stephanie Pollack announced Brian Shortsleeve will serve as the Chief Administrator for the MBTA, working alongside the newly appointed Fiscal and Management Control Board (FMCB), interim General Manager Frank DePaola, who will continue in his current role focusing solely on operations and   …Continue Reading MassDOT Secretary Announces MBTA Leadership Team

MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2 posted on Jul 29

MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2

The MBTA has scheduled necessary track maintenance activities on the Orange Line for this weekend, Saturday, August 1st and Sunday, August 2nd. Weekend service will be suspended between Forest Hills and Ruggles Stations. During the suspension of service, work crews will remove and replace rail   …Continue Reading MBTA Orange Line Service Alert: Suspension of Weekend Service August 1-2

Longfellow Bridge: August Closures Update posted on Jul 29

Longfellow Bridge: August Closures Update

The Longfellow Bridge Rehabilitation Project moves forward with demolition work that will require bridge closures. MassDOT’s contractor, White-Skanska-Consigli JV (WSC), will periodically close the Longfellow Bridge to all vehicular traffic beginning on Saturday, August 1 through Friday, August 21. The closures are necessary to safely   …Continue Reading Longfellow Bridge: August Closures Update