Post Content

Route 2 Irene Damage 1

MassDOT Secretary Richard A. Davey announced today that work to reconstruct the six-mile section of Route 2 devastated by Tropical Storm Irene will begin early next week.

The roadway linking the communities of North Adams, Florida, Savoy, and Charlemont suffered major damage from the storm and flooding, making it impassable to traffic. Reconstruction is expected to cost $34.5 million and work under an accelerated bidding process will begin early next week.  The roadway is expected to re-open to traffic by mid-December.  

MassDOT has assembled a map showing the closed portion of Route 2 that suffered significant damage due to flooding from Tropical Storm Irene and outlining the current posted detour.

Route 2 is closed from Mile Marker 21.6 in Florida to Mile Marker 27.5 in Charlemont.

“Governor Patrick has been clear: reopening Route 2 is a top priority.  We are working as quickly as possible to open the road again for safety and connectivity reasons, but also to reopen a popular area for tourism,” said Secretary Davey.

Route 2 is a critical roadway for affected communities and businesses, connecting residents to key arteries including I-91 and to Albany, New York.

Highway Administrator DePaola said the combination of roadway washout and substantial damage to retaining walls, and man-made slopes, will require an innovative approach to re-opening the road.

“What we’ll be doing is breaking down the repairs into separate jobs so that contractors can get out there and begin work simultaneously in order to get this road back open to traffic,” said Administrator DePaola. 

The work is being done under an expedited bidding process, with designs completed, bids solicited, and contracts signed in a span of three weeks.  Two areas of slope repairs and road reconstruction in North Adams and Florida will begin immediately at a total cost of approximately $11.5 million.  

A separate $7.5 million expedited contract early in October will include reconstruction of Route 2 farther east in the towns of Savoy and Charlemont.  A final estimated $15.5 million contract this fall will include reconstruction of portions of retaining walls between Savoy and Charlemont, which can occur with the road re-opened to traffic.  MassDOT will seek federal reimbursement for costs associated with these repairs. 

Written By:

Recent Posts

North Side Commuter Rail Schedule Implementation Postponed posted on Nov 25

North Side Commuter Rail Schedule Implementation Postponed

  MassDOT and the MBTA announced the recently revised North Side Commuter Rail schedules will not be implemented until spring 2016. The revision of Commuter Rail schedules is a critical element of MassDOT and the MBTA’s efforts to deliver safe, reliable, on-time service to Commuter   …Continue Reading North Side Commuter Rail Schedule Implementation Postponed

Travel Safely for Thanksgiving! posted on Nov 24

Travel Safely for Thanksgiving!

MassDOT encourages Thanksgiving holiday travelers to plan ahead with high traffic volume on our highways and at Boston Logan International Airport expected again this year. Highways are typically busiest on the Tuesday and Wednesday before and on the Sunday after the holiday.  Heavy traffic congestion   …Continue Reading Travel Safely for Thanksgiving!

Springfield: I-91 Viaduct Project Public Meeting Set posted on Nov 23

Springfield: I-91 Viaduct Project Public Meeting Set

MassDOT has scheduled a Public Information Meeting for the I-91 Viaduct Rehabilitation Project as follows: Tuesday, December 8, 6:30 PM to 8:30 PM, Basketball Hall of Fame, Theater, 1000 Hall of Fame Avenue, Springfield Please join MassDOT for an update on the major construction and   …Continue Reading Springfield: I-91 Viaduct Project Public Meeting Set