Post Content

Route 2 Irene Damage 1

MassDOT Secretary Richard A. Davey announced today that work to reconstruct the six-mile section of Route 2 devastated by Tropical Storm Irene will begin early next week.

The roadway linking the communities of North Adams, Florida, Savoy, and Charlemont suffered major damage from the storm and flooding, making it impassable to traffic. Reconstruction is expected to cost $34.5 million and work under an accelerated bidding process will begin early next week.  The roadway is expected to re-open to traffic by mid-December.  

MassDOT has assembled a map showing the closed portion of Route 2 that suffered significant damage due to flooding from Tropical Storm Irene and outlining the current posted detour.

Route 2 is closed from Mile Marker 21.6 in Florida to Mile Marker 27.5 in Charlemont.

“Governor Patrick has been clear: reopening Route 2 is a top priority.  We are working as quickly as possible to open the road again for safety and connectivity reasons, but also to reopen a popular area for tourism,” said Secretary Davey.


Route 2 is a critical roadway for affected communities and businesses, connecting residents to key arteries including I-91 and to Albany, New York.

Highway Administrator DePaola said the combination of roadway washout and substantial damage to retaining walls, and man-made slopes, will require an innovative approach to re-opening the road.

“What we’ll be doing is breaking down the repairs into separate jobs so that contractors can get out there and begin work simultaneously in order to get this road back open to traffic,” said Administrator DePaola. 

The work is being done under an expedited bidding process, with designs completed, bids solicited, and contracts signed in a span of three weeks.  Two areas of slope repairs and road reconstruction in North Adams and Florida will begin immediately at a total cost of approximately $11.5 million.  

A separate $7.5 million expedited contract early in October will include reconstruction of Route 2 farther east in the towns of Savoy and Charlemont.  A final estimated $15.5 million contract this fall will include reconstruction of portions of retaining walls between Savoy and Charlemont, which can occur with the road re-opened to traffic.  MassDOT will seek federal reimbursement for costs associated with these repairs. 

Written By:

Recent Posts

Chelsea: Silver Line Gateway Project Bridge Closure posted on May 22

Chelsea: Silver Line Gateway Project Bridge Closure

MassDOT will close the Washington Avenue Bridge in Chelsea on Tuesday, May 26 at 10:00 AM as part of the Silver Line Gateway Project.  Appropriate detour signs will be in place to redirect traffic and pedestrians, and identify relocated bus stops.  The bridge closure is   …Continue Reading Chelsea: Silver Line Gateway Project Bridge Closure

MBTA: Refurbished Green Line Trolleys Returning to Service posted on May 22

MBTA: Refurbished Green Line Trolleys Returning to Service

The first MBTA Green Line refurbished trolley car was returned to service this week. T personnel are completing test runs on the next refurbished car to return to service in the coming days. These are the first of 86 that are being refurbished. All 86   …Continue Reading MBTA: Refurbished Green Line Trolleys Returning to Service

Travel Safely Memorial Day Weekend! posted on May 20

Travel Safely Memorial Day Weekend!

MassDOT encourages travelers to plan ahead and travel safely during the Memorial Day holiday weekend.  The heaviest traffic is expected Thursday, Friday, and Monday afternoons and early evenings.  Drivers are encouraged to make travel plans accordingly and if possible avoid peak traffic volumes between 1pm   …Continue Reading Travel Safely Memorial Day Weekend!