Post Content

Route 2 Irene Damage 1

MassDOT Secretary Richard A. Davey announced today that work to reconstruct the six-mile section of Route 2 devastated by Tropical Storm Irene will begin early next week.

The roadway linking the communities of North Adams, Florida, Savoy, and Charlemont suffered major damage from the storm and flooding, making it impassable to traffic. Reconstruction is expected to cost $34.5 million and work under an accelerated bidding process will begin early next week.  The roadway is expected to re-open to traffic by mid-December.  

MassDOT has assembled a map showing the closed portion of Route 2 that suffered significant damage due to flooding from Tropical Storm Irene and outlining the current posted detour.

Route 2 is closed from Mile Marker 21.6 in Florida to Mile Marker 27.5 in Charlemont.

“Governor Patrick has been clear: reopening Route 2 is a top priority.  We are working as quickly as possible to open the road again for safety and connectivity reasons, but also to reopen a popular area for tourism,” said Secretary Davey.


Route 2 is a critical roadway for affected communities and businesses, connecting residents to key arteries including I-91 and to Albany, New York.

Highway Administrator DePaola said the combination of roadway washout and substantial damage to retaining walls, and man-made slopes, will require an innovative approach to re-opening the road.

“What we’ll be doing is breaking down the repairs into separate jobs so that contractors can get out there and begin work simultaneously in order to get this road back open to traffic,” said Administrator DePaola. 

The work is being done under an expedited bidding process, with designs completed, bids solicited, and contracts signed in a span of three weeks.  Two areas of slope repairs and road reconstruction in North Adams and Florida will begin immediately at a total cost of approximately $11.5 million.  

A separate $7.5 million expedited contract early in October will include reconstruction of Route 2 farther east in the towns of Savoy and Charlemont.  A final estimated $15.5 million contract this fall will include reconstruction of portions of retaining walls between Savoy and Charlemont, which can occur with the road re-opened to traffic.  MassDOT will seek federal reimbursement for costs associated with these repairs. 

Written By:

Recent Posts

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition

Green Line Extension: Medford Detour posted on Apr 21

Green Line Extension: Medford Detour

The Green Line Extension team would like to inform you of upcoming Phase 1 project work on Harvard Street in Medford. On the weekend of April 26th, it will be necessary for the GLX Phase 1 Contractor, Barletta Heavy Division, Inc., to close Harvard Street   …Continue Reading Green Line Extension: Medford Detour