Post Content

Route 2 Repairs, Slope Stabilization, October 12, 2011Repairs are moving forward along the section of Route 2 damaged significantly by Tropical Storm Irene. 

As seen at left in North Adams and below in Florida, work is well underway to repair the man-made roadway slopes, including excavation and relocation of utilities. 

MassDOT Secretary Richard A. Davey at the end of September announced that work to reconstruct the six-mile section of Route 2 linking North Adams, Florida, Savoy, and Charlemont would proceed on an expedited schedule under an accelerated bidding process.

The roadway is expected to re-open to traffic by mid-December. Route 2 Repairs, Florida, October 12, 2011

MassDOT has assembled a map showing the closed portion of Route 2 that suffered significant damage due to flooding from Tropical Storm Irene and outlining the current posted detour.

Route 2 is closed from Mile Marker 21.6 in Florida to Mile Marker 27.5 in Charlemont.

MassDOT Highway Administrator Frank DePaola said that because of the combination of roadway washout and substantial damage to retaining walls and man-made slopes, MassDOT is using an innovative approach by separating the repairs into multiple jobs that can proceed simultaneously to safely reduce the work timeline.

 

 

Written By:

Recent Posts

July 4th Holiday Services Update posted on Jun 30

July 4th Holiday Services Update

MassDOT encourages safe travel during the upcoming July 4 holiday weekend.  Before you drive, check our live Traffic Cameras web page to view current conditions. Traffic is especially heavy at the I-84 interchange at Exit 9 in Sturbridge on the day before the holiday and   …Continue Reading July 4th Holiday Services Update

MassDOT Board Approves Contract for 325 New MBTA Buses posted on Jun 29

MassDOT Board Approves Contract for 325 New MBTA Buses

The MassDOT Board of Directors today approved a contract for the manufacture and delivery of 325 new state-of-the-art replacement buses for the MBTA fleet. “This is a major step in the process in modernizing the MBTA’s bus fleet and provides an important resource for millions   …Continue Reading MassDOT Board Approves Contract for 325 New MBTA Buses

Medford Cradock Bridge: I-93 Route 16 Westbound Ramp Closure posted on Jun 26

MassDOT is scheduled to close the I-93 Route 16 Westbound off ramp on Monday, June 29, at 7:00 AM to begin construction on the Cradock Bridge Project in Medford. The off ramp is scheduled to be closed for the duration of the project through approximately   …Continue Reading Medford Cradock Bridge: I-93 Route 16 Westbound Ramp Closure