Callahan Tunnel WorkMassDOT’s Callahan Tunnel Project begins with a full tunnel closure for rehabilitation on December 27, 2013. We invite you to visit the new Callahan Tunnel Project web page to learn more.  The web page includes trip planning tools during the duration of the closure and a one-page Printable Fact Sheet also translated into Chinese, Portuguese and Spanish. Detour route maps and descriptions will be posted on the web page later in November.

The $34.9 million project includes rehabilitation of the 52-year old tunnel’s deck, curb line, gutters and replacement of the tunnel’s wall panels.  The original deteriorated wall panels were removed in December 2012 as a safety measure due to significant corrosion to the panel wall anchor system.

The proposed work schedule includes the full tunnel closure in early 2014 with detours in place, followed by an additional 4-5 months of work requiring overnight closures between 11p.m. and 5a.m. The complete closure of the tunnel will reduce the overall duration of the project, provide enhanced public safety by minimizing changes to traffic flow, and better coordinate with other local projects including Tobin Bridge work, which is scheduled to resume in spring 2014.

For project details, visit: www.mass.gov/massdot/CallahanTunnelRehab

To sign up for the project email list or communicate with the project team, email: callahan.tunnel@state.ma.us

Written By:

Recent Posts

Methuen Rotary Project: Travel Impacts posted on Jul 22

Methuen Rotary Project: Travel Impacts

MassDOT has scheduled upcoming lane closures as part of the Methuen Rotary Reconstruction Project.  Beginning on Monday, July 28, 2014 until further notice, the I-93 breakdown lane will be closed from Exit 46 – Routes 110/113 to Exit 47 – Pelham St. on I-93 Northbound   …Continue Reading Methuen Rotary Project: Travel Impacts

Tobin Bridge: All-Electronic Tolling Begins Monday, July 21 posted on Jul 18

Tobin Bridge: All-Electronic Tolling Begins Monday, July 21

Effective Monday, July 21, prior to the morning commute, tolling on the Tobin Bridge will convert to the all-electronic format. The new toll system will eliminate the need for customers to pay the toll in cash. The system is equipped to read E-ZPass transponders for   …Continue Reading Tobin Bridge: All-Electronic Tolling Begins Monday, July 21

MassDOT Berkshire Rail Line Purchase posted on Jul 17

MassDOT Berkshire Rail Line Purchase

The MassDOT Board of Directors has authorized MassDOT Secretary and CEO Richard A. Davey to execute an agreement to purchase the Berkshire Line from the Housatonic Railroad Company, a major step toward delivering passenger rail service between New York City and the Berkshires. The agreement   …Continue Reading MassDOT Berkshire Rail Line Purchase