Post Content

Tobin Bridge AerialMassDOT reminds motorists that work on the Tobin Bridge is set to resume as scheduled next week.

The three-year steel preservation and painting project began in spring 2012.

Beginning next week, the contractor will begin to deploy a combination of both day and night time lane closures to install platforms along the bridge. 

The lane closures will affect both the northbound/lower deck, and the southbound/upper deck of the bridge. 

Permanent lane restrictions will begin the week of April 8.  Lane restrictions will reduce the roadway from three lanes to two on both decks of the bridge. 

Motorists should expect this setup to remain in place until November 2013. The third and final year of work will begin in the spring of 2014.

A public meeting to update the project has been scheduled:

Monday, April 8, 6 p.m., Chelsea City Hall, 500 Broadway.

We invite you to stay informed by visiting the Tobin Project website.

The current work schedule, week-by-week, subject to change due to the weather, is available after the break.



Week of March 25 & April 1

The contractor will install platforms, rigging and touch-up work from last season. Lane closures will take effect on both the northbound/lower deck and southbound/upper deck of the bridge.

Week of April 8

The contractor will begin to set up barrels to get motorists accustomed to the lane restrictions that will reduce the roadway from three lanes to two on both decks of the bridge. The restriction will allow the contractor to complete the installation of rigging and shielding.

Week of April 15

The contractor will begin installing barriers along both sides of the bridge and install side shielding around the two travel lanes to provide additional safety for the public. Work to install the shielding will continue. Shielding will be installed throughout the length of the project to limit any possible inconvenience to the public. The contractor will begin setting up a fully encapsulating containment system inside the existing shielding providing redundancy to ensure none of the removed paint escapes

Week of April 22

Once the containment has been fully installed, tested and approved, the contractor may begin sandblasting off the existing paint, repairing necessary steel bridge appurtenances, and painting.

Written By:

Recent Posts

Whittier Bridge/I-95 Project Traffic Update posted on Sep 19

Whittier Bridge/I-95 Project Traffic Update

Work on the Whittier Bridge/I-95 Project in Newburyport and Amesbury will require extended lane closure hours beginning next week. Beginning on Monday, September 22, the hours of daytime construction will extend the I-95 Northbound right lane closure the associated right lane closure on I-95 Northbound   …Continue Reading Whittier Bridge/I-95 Project Traffic Update

Take the Clean Air Challenge! Join Us September 22-26 posted on Sep 18

Take the Clean Air Challenge! Join Us September 22-26

Massachusetts travelers will improve air-quality by choosing more sustainable transportation options during the Massachusetts Clean Air Challenge (formerly Car-Free Week). This year, Massachusetts challenges you to explore your commuting options and Shift Your Mode from September 22nd-26th. By trying greener modes including carpooling, vanpooling, bicycling,   …Continue Reading Take the Clean Air Challenge! Join Us September 22-26

MBTA Silver Line to Chelsea Approved posted on Sep 17

MBTA Silver Line to Chelsea Approved

The MassDOT Board of Directors today approved a construction contract to extend the MBTA’s increasingly popular Silver Line from East Boston to Chelsea. A project funded entirely by Governor Deval Patrick’s 2013 Transportation Finance Plan, the Silver Line will be extended past the Seaport to   …Continue Reading MBTA Silver Line to Chelsea Approved