Post Content

Tobin Bridge AerialMassDOT reminds motorists that work on the Tobin Bridge is set to resume as scheduled next week.

The three-year steel preservation and painting project began in spring 2012.

Beginning next week, the contractor will begin to deploy a combination of both day and night time lane closures to install platforms along the bridge. 

The lane closures will affect both the northbound/lower deck, and the southbound/upper deck of the bridge. 

Permanent lane restrictions will begin the week of April 8.  Lane restrictions will reduce the roadway from three lanes to two on both decks of the bridge. 

Motorists should expect this setup to remain in place until November 2013. The third and final year of work will begin in the spring of 2014.

A public meeting to update the project has been scheduled:

Monday, April 8, 6 p.m., Chelsea City Hall, 500 Broadway.

We invite you to stay informed by visiting the Tobin Project website.

The current work schedule, week-by-week, subject to change due to the weather, is available after the break.



Week of March 25 & April 1

The contractor will install platforms, rigging and touch-up work from last season. Lane closures will take effect on both the northbound/lower deck and southbound/upper deck of the bridge.

Week of April 8

The contractor will begin to set up barrels to get motorists accustomed to the lane restrictions that will reduce the roadway from three lanes to two on both decks of the bridge. The restriction will allow the contractor to complete the installation of rigging and shielding.

Week of April 15

The contractor will begin installing barriers along both sides of the bridge and install side shielding around the two travel lanes to provide additional safety for the public. Work to install the shielding will continue. Shielding will be installed throughout the length of the project to limit any possible inconvenience to the public. The contractor will begin setting up a fully encapsulating containment system inside the existing shielding providing redundancy to ensure none of the removed paint escapes

Week of April 22

Once the containment has been fully installed, tested and approved, the contractor may begin sandblasting off the existing paint, repairing necessary steel bridge appurtenances, and painting.

Written By:

Recent Posts

MBTA: New Customer Service Enhancements posted on Apr 24

The MBTA this week rolled out customer service enhancements that make public transit even easier to use: real-time arrival information for the Red, Orange & Blue Lines is now available at mbta.com, the Bus Countdown Clock system has been activated at Dudley station and the   …Continue Reading MBTA: New Customer Service Enhancements

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition