MBTA Orient Heights Construction, November 2013A vivid example of collaboration and cost savings characterized by the 2009 Transportation Reform Law has played out this year in and around the MBTA Blue Line Orient Heights Station.  Three transportation agencies managing three different projects worked closely together to save a total of more than $4.1 million while completing the work and limiting disruptions to subway service.

As the MBTA rebuilt Orient Heights Station, MassDOT’s Highway Division replaced a Revere Beach Parkway Bridge over the MBTA and State Road and Massport constructed the Logan Greenway Connector project.  All three projects required work on or next to the Blue Line right-of-way. Significant portions of that work were “piggybacked” together and completed during several Blue Line weekend service diversions, which were necessary to allow work crews to perform critical infrastructure work on track and signals.

Piggybacking construction work on the three projects during 13 weekends allowed the MBTA to schedule fewer weekend service diversions, each with an estimated cost of $147,899. MassDOT’s bridge project saved a total of an estimated $1,665,495 by piggybacking and completing the work in less time.

“This is truly transportation reform in action as the T, MassDOT, and Massport worked together on three important projects and saved millions of dollars,” said MassDOT Secretary and CEO Richard A. Davey. “I applaud the planning and coordination that not only saved money but also minimized inconvenience for our customers.”

The projects and work accomplished include the following:

The $27.8 million Orient Heights Station Project will make the station fully accessible to all passengers and modernize the station, including installation of a new overhead pedestrian bridge, four elevators and two escalators, new mechanical and power systems, a renovated Train Operations Building, new platforms, and improvements to the bus access areas. The station will reopen tomorrow, Tuesday, November 26, after being closed since March 2013 for construction.

State Road Bridge Construction, Sept. 21, 2013MassDOT Highway’s Revere Beach Parkway Bridge Project work piggybacked with six Blue Line weekend closures, allowing MassDOT to replace the bridge superstructure in two weekends using accelerated bridge construction methods.

Massport’s Logan Greenway Connector Project work piggybacked with seven Blue Line weekend closures to construct a dual use bicycle/pedestrian path in East Boston that will extend Bremen Street park use to Marsh Island. Completion is expected in summer 2014.

The Logan Greenway Connector Project also provided the MBTA with a 1700 foot section of new fencing, retaining walls, tree and brush clearing along with removal of the Neptune Road Bridge.

Written By:

Recent Posts

MassDOT, Mapfre Insurance Encourage Safe Summer Driving posted on May 24

MassDOT, Mapfre Insurance Encourage Safe Summer Driving

In time for Memorial Day, the kick-off to the summer driving season, MassDOT Acting Highway Administrator Thomas Tinlin joined MAPFRE Insurance in reminding motorists to adhere to speed limits, obey traffic laws and avoid distracted driving when traveling during the summer months. According to data   …Continue Reading MassDOT, Mapfre Insurance Encourage Safe Summer Driving

Chelsea: Silver Line Gateway Project Bridge Closure posted on May 22

Chelsea: Silver Line Gateway Project Bridge Closure

MassDOT will close the Washington Avenue Bridge in Chelsea on Tuesday, May 26 at 10:00 AM as part of the Silver Line Gateway Project.  Appropriate detour signs will be in place to redirect traffic and pedestrians, and identify relocated bus stops.  The bridge closure is   …Continue Reading Chelsea: Silver Line Gateway Project Bridge Closure

MBTA: Refurbished Green Line Trolleys Returning to Service posted on May 22

MBTA: Refurbished Green Line Trolleys Returning to Service

The first MBTA Green Line refurbished trolley car was returned to service this week. T personnel are completing test runs on the next refurbished car to return to service in the coming days. These are the first of 86 that are being refurbished. All 86   …Continue Reading MBTA: Refurbished Green Line Trolleys Returning to Service