Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

A First in the State: MassDOT Uses New Construction Technique on Route 2/I-95 Project posted on Aug 28

A First in the State: MassDOT Uses New Construction Technique on Route 2/I-95 Project

From smaller projects to the largest, MassDOT uses the latest, proven innovative techniques. For the first time in the state, MassDOT is using precast, modular concrete abutments on the Route 2/I-95 Bridge Replacement Project. Accelerated Bridge Construction technologies, such as this one, reduce project duration   …Continue Reading A First in the State: MassDOT Uses New Construction Technique on Route 2/I-95 Project

Route 107 Corridor Public Meetings Scheduled posted on Aug 26

Route 107 Corridor Public Meetings Scheduled

Public Information Meetings for the Route 107 Corridor Study have been scheduled as follows: Wednesday, September 7, 6:00 PM to 8:00 PM, Lynn English High School, Auditorium, 50 Goodridge Street Tuesday, September 13, 6:00 PM to 8:00 PM, Collins Middle School, Auditorium, 29 Highland Avenue,   …Continue Reading Route 107 Corridor Public Meetings Scheduled

Gill-Montague Bridge Rehabilitation Celebrated posted on Aug 25

Gill-Montague Bridge Rehabilitation Celebrated

MassDOT Secretary and CEO Stephanie Pollack and Highway Administrator Thomas J. Tinlin joined Director of Governor Charlie Baker’s Western Massachusetts Office Michael Knapik, Senate President Stanley C. Rosenberg, state and local officials today in Turners Falls to celebrate the complete rehabilitation of the Avenue A   …Continue Reading Gill-Montague Bridge Rehabilitation Celebrated