Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

Barre: Town Common Project Moves Forward posted on Jul 28

Barre: Town Common Project Moves Forward

MassDOT Highway Administrator Thomas J. Tinlin joined elected officials to celebrate the groundbreaking of the Barre Town Common Improvements Project. Located in the center of Barre, at the junction of Routes 122, 32, and 62, the Barre Town Common Improvement Project will redesign the five   …Continue Reading Barre: Town Common Project Moves Forward

Casey Arborway: Night Work Begins July 26 posted on Jul 24

Casey Arborway: Night Work Begins July 26

As part of the ongoing Casey Arborway Project, night work will resume beginning Sunday, July 26th through Thursday, July 30 and continue for approximately 5 weeks. Night work hours are 8PM to 6AM. Night work is necessary for public safety and will take place with   …Continue Reading Casey Arborway: Night Work Begins July 26

Burns Bridge Update: Traffic Shift posted on Jul 22

Burns Bridge Update: Traffic Shift

The Kenneth F. Burns Memorial Bridge project in Worcester-Shrewsbury continues to move toward completion. A traffic shift will take place tonight, Wednesday, July 22nd, when eastbound traffic will be shifted from the northern half of the Burns Bridge to its permanent location on the bridge’s   …Continue Reading Burns Bridge Update: Traffic Shift