Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

Governor Baker, Mayor Walsh Announce Joint Community Redevelopment Venture in Downtown Boston posted on Feb 9

Governor Baker, Mayor Walsh Announce Joint Community Redevelopment Venture in Downtown Boston

Today as part of the Baker-Polito Administration’s “Open for Business” Real Estate Asset Leveraging (REAL) Strategy, Governor Charlie Baker and Boston Mayor Martin J. Walsh announced a joint state and city venture with Veolia North America to explore the strategic redevelopment of the Massachusetts Department   …Continue Reading Governor Baker, Mayor Walsh Announce Joint Community Redevelopment Venture in Downtown Boston

MBTA: Green Line Service Temporary Suspension between Park and Haymarket posted on Feb 9

MBTA: Green Line Service Temporary Suspension between Park and Haymarket

On selected weekends and nights, MBTA Green Line service will be suspended in both directions between Park and Haymarket stations to allow for platform work as part of the Government Center Station project. The diversion will allow personnel access to the Government Center Green Line   …Continue Reading MBTA: Green Line Service Temporary Suspension between Park and Haymarket

MassDOT Prepares for Winter Storm posted on Feb 7

MassDOT Prepares for Winter Storm

  The Massachusetts Department of Transportation (MassDOT) is preparing for a significant winter storm which is scheduled to arrive in some areas of the state overnight tonight and early Monday morning and which will bring blizzard conditions to areas along the South Shore as well   …Continue Reading MassDOT Prepares for Winter Storm