Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

Cambridge: Kendall Square Mobility Task Force posted on Apr 17

Cambridge: Kendall Square Mobility Task Force

The first meeting of MassDOT’s Kendall Square Mobility Task Force is scheduled as follows: Tuesday, April 28, 2015 from 4:00 PM – 6:00 PM at 600 Technology Square (corner of Main and Portland) – 3rd floor in Cambridge.  MassDOT’s Kendall Square Mobility Task Force process   …Continue Reading Cambridge: Kendall Square Mobility Task Force

MassDOT Receives Excellence in Transportation Award posted on Apr 16

MassDOT Receives Excellence in Transportation Award

The Massachusetts Department of Transportation (MassDOT) was recognized this week with an Excellence in Transportation Demand Management Award at the Association for Commuter Transportation’s (ACT) Regional Patriot Chapter Conference in Newport, Rhode Island. MassDOT was presented with an award for their Safe Streets Smart Trips   …Continue Reading MassDOT Receives Excellence in Transportation Award

MassDOT Approves Contract for Springfield I-91 Viaduct Project posted on Apr 15

MassDOT Approves Contract for Springfield I-91 Viaduct Project

MassDOT today awarded a contract for the rehabilitation of the I-91 viaduct structure in Springfield. The lowest responsible bid was submitted by the joint venture of JF White-Schiavone, $148,000,150. There were three bids in total. The total project cost of $183,325,172 includes railroad flaggers, traffic   …Continue Reading MassDOT Approves Contract for Springfield I-91 Viaduct Project