Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

MassDOT, MAPFRE Insurance Reminder: Avoid “Blackout Wednesday” and Buckle Up This Thanksgiving posted on Nov 12

MassDOT, MAPFRE Insurance Reminder: Avoid “Blackout Wednesday” and Buckle Up This Thanksgiving

The two most traveled holidays are upon us, with the first being Thanksgiving weekend. From Wednesday, November 27th through Monday, December 2nd, all drivers should be aware of the factors that make this holiday one of the deadliest for our roadways. According to the National   …Continue Reading MassDOT, MAPFRE Insurance Reminder: Avoid “Blackout Wednesday” and Buckle Up This Thanksgiving

I-90 Allston Multimodal Project: Document Online, Public Comments Encouraged posted on Nov 6

I-90 Allston Multimodal Project: Document Online, Public Comments Encouraged

MassDOT is inviting the public to an informational meeting on Thursday, November 7, between 6:30 p.m. and 8:30 p.m. which is being hosted by the Federal Highway Administration (FHWA) to introduce the National Environmental Policy Act (NEPA) Scoping Document for MassDOT’s I-90 Allston Multimodal Project.    …Continue Reading I-90 Allston Multimodal Project: Document Online, Public Comments Encouraged

Worcester: Kelley Square Public Meeting November 20th posted on Nov 6

Worcester: Kelley Square Public Meeting November 20th

A Public Information Meeting for the Worcester Kelley Square Improvement Project has been scheduled as follows: Wednesday, November 20, 6PM, Crompton Collective White Room, 138 Green Street. MassDOT and its general contractor for the project, J.H. Lynch, will discuss the project’s overall construction phasing, key   …Continue Reading Worcester: Kelley Square Public Meeting November 20th