Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

MBTA Silver Line vehicles will test ramp from South Boston to I-90 East posted on Aug 23

MBTA Silver Line vehicles will test ramp from South Boston to I-90 East

MassDOT and the MBTA today announced that there will be a limited test of MBTA Silver Line buses using a ramp from MassPort’s Haul Road in South Boston’s Seaport District to I-90 eastbound. The three-day test will take place during afternoon peak travel periods to   …Continue Reading MBTA Silver Line vehicles will test ramp from South Boston to I-90 East

Tobin Bridge/Chelsea Curves Rehabilitation Project Update posted on Aug 15

Tobin Bridge/Chelsea Curves Rehabilitation Project Update

MassDOT has announced that the lane closures and roadway configuration on Route 1 northbound in Chelsea will shift on Monday, August 19 so that the center lane on this section of highway will be closed 24/7. Both the right and left travel lanes will be   …Continue Reading Tobin Bridge/Chelsea Curves Rehabilitation Project Update

First New MBTA Orange Line Cars Enter Passenger Service posted on Aug 14

First New MBTA Orange Line Cars Enter Passenger Service

Governor Charlie Baker, MassDOT Secretary and CEO Stephanie Pollack, and MBTA General Manager Steve Poftak today introduced the first new Orange Line train comprised of six brand new cars into regular service from Wellington Station. These six new cars entering passenger service today are the   …Continue Reading First New MBTA Orange Line Cars Enter Passenger Service