Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

MBTA: New Customer Service Enhancements posted on Apr 24

The MBTA this week rolled out customer service enhancements that make public transit even easier to use: real-time arrival information for the Red, Orange & Blue Lines is now available at mbta.com, the Bus Countdown Clock system has been activated at Dudley station and the   …Continue Reading MBTA: New Customer Service Enhancements

I-90 Pru Tunnel Work Scheduled: April 26-27 posted on Apr 22

I-90 Pru Tunnel Work Scheduled: April 26-27

Today, the Massachusetts Convention Center Authority (MCCA) and MassDOT announced the fourth and final weekend of lane restrictions on the Massachusetts Turnpike associated with the removal of the I-90 Prudential Tunnel ceiling in Boston.  Due to the faster-than-anticipated progress on the ceiling removal, the fourth   …Continue Reading I-90 Pru Tunnel Work Scheduled: April 26-27

Fall River: Route 79/Braga Bridge Project Demolition posted on Apr 22

Fall River: Route 79/Braga Bridge Project Demolition

MassDOT contractors beginning today as part of the Route 79/Braga Bridge Improvements Project will remove the portion of the elevated Route 79 over the intersection of Anawan Street/Pocasset Street and Davol Street. The work will take place today, Tuesday, April 22 through Friday, April 25.   …Continue Reading Fall River: Route 79/Braga Bridge Project Demolition