Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

Boston: I-90 Eastbound 4th Lane Reopens at Commonwealth Avenue Bridge posted on Jun 26

Boston: I-90 Eastbound 4th Lane Reopens at Commonwealth Avenue Bridge

MassDOT today announced the restoration of a fourth lane on I-90 Eastbound from the Commonwealth Avenue bridge to the Prudential Tunnel in Boston. The restoration of four travel lanes comes after MassDOT completed safety upgrades by replacing the median system with a new jersey barrier   …Continue Reading Boston: I-90 Eastbound 4th Lane Reopens at Commonwealth Avenue Bridge

RMV: 2016 Low Number Plate Lottery Applications Now Accepted posted on Jun 25

RMV: 2016 Low Number Plate Lottery Applications Now Accepted

MassDOT Registrar of Motor Vehicles Erin Deveney announced that applications for the 2016 Low Number Plate Lottery are now being accepted online or by U.S. mail. Starting this year, for the first time ever, customers will be able to enter the lottery online by visiting:    …Continue Reading RMV: 2016 Low Number Plate Lottery Applications Now Accepted

Casey Arborway Project Public Meeting Set posted on Jun 24

Casey Arborway Project Public Meeting Set

MassDOT has scheduled a fourth Casey Arborway Project Construction Update Meeting as follows: Wednesday, June 29, 6:30-8:30 PM, Boston English High School Auditorium 144 McBride Street, Jamaica Plain The purpose of this meeting will be to provide the community with an update on the progress   …Continue Reading Casey Arborway Project Public Meeting Set