Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

RMV: New Boston Branch Location, Low Number Lottery Drawing posted on Aug 28

RMV: New Boston Branch Location, Low Number Lottery Drawing

MassDOT Registrar of Motor Vehicles Celia J. Blue announced the annual low number license plate lottery drawing will be held on September 10 at the RMV’s soon-to-open new Boston branch, Haymarket Center at 136 Blackstone Street. “As we move our operations to a new Boston   …Continue Reading RMV: New Boston Branch Location, Low Number Lottery Drawing

Labor Day Weekend Travel: Plan Ahead! posted on Aug 27

Labor Day Weekend Travel: Plan Ahead!

MassDOT encourages motorists to plan ahead for safe travel during the upcoming Labor Day holiday weekend. Heaviest Labor Day traffic on I-90 is expected Thursday and Friday westbound and Monday afternoon-evening eastbound.  The number of toll transactions on the Turnpike from Weston to the New   …Continue Reading Labor Day Weekend Travel: Plan Ahead!

Boston: I-90 Construction Update posted on Aug 26

Boston: I-90 Construction Update

MassDOT contractors in August and September continue the preparation work to improve the median and Commonwealth Avenue Bridge substructure on Interstate 90 in Boston. The left lanes in both Eastbound and Westbound directions on I-90 from west of the Prudential tunnel to the Commonwealth Avenue   …Continue Reading Boston: I-90 Construction Update