Waltham, Winter Street Bridge over I-95, October 19, 2011The $23 million project to reconstruct and expand the Route 128/I-95 Exit 27A-B interchange with Winter Street/Totten Pond Road in Waltham enters a new phase with a new exit ramp traffic pattern beginning Monday, October 24.

The new Winter Street Bridge, left, reopened to traffic in August.  A temporary bridge has been removed and final construction is underway on the connections between the northbound on and off ramps and the new collector road along Route 128/I-95 NB.  This new collector road will reduce the conflict points where traffic enters and exits Route 128/I-95 NB.

The overall project is expected to be substantially completed and fully opened to traffic in mid November.  The traffic pattern changes are below:

Beginning on Monday, October 24th at 5:00 AM, a new traffic pattern will be implemented for drivers travelling on Route 128/I-95 North seeking access to areas served by Exit 27A (Totten Pond Road) and Exit 27B (Wyman Street/Winter Street).  A new collector roadway located parallel to Route 128/I-95 North will be opened to traffic. 

At the beginning of the collector roadway, a single exit point located south of Winter Street will be available for drivers travelling on Route 128/I-95 North destined to Exit 27A or 27B.  At the end of the roadway, a single entry point located north of Winter Street will be available for drivers accessing Route 128/I-95 North. 

MassDOT encourages drivers on Route 128/I-95 North to check portable changeable message signs and follow directional guide signs to access Exits 27A–B.

Written By:

Recent Posts

Braintree: Route 3 Bridge Replacement Completed Ahead of Schedule posted on Oct 16

Braintree: Route 3 Bridge Replacement Completed Ahead of Schedule

The Massachusetts Department of Transportation has announced that its accelerated replacement of the Route 3 southbound bridge in Braintree was completed at approximately 1:00 a.m. on Monday, October 16, several hours ahead of schedule. Accelerated operations began at 10 p.m., on Friday, October 13, and   …Continue Reading Braintree: Route 3 Bridge Replacement Completed Ahead of Schedule

State Officials Announce Transportation Sector Emissions Listening Sessions posted on Oct 13

State Officials Announce Transportation Sector Emissions Listening Sessions

The Baker-Polito Administration today announced dates for a series of listening sessions across the Commonwealth to discuss solutions to the challenge of reducing greenhouse gas emissions from the transportation sector. The public forums, to be hosted by the Executive Office of Energy and Environmental Affairs   …Continue Reading State Officials Announce Transportation Sector Emissions Listening Sessions

MassRMV, EOPSS Release Video for Parents of Teenage Drivers posted on Oct 13

The Executive Office of Public Safety and Security (EOPSS) in partnership with the Massachusetts Department of Transportation Registry of Motor Vehicles (RMV) today unveiled an educational video for parents to help them prepare their teens to become safe, smart drivers.  “Tips for Parents, A Common   …Continue Reading MassRMV, EOPSS Release Video for Parents of Teenage Drivers