Post Content

Whittier Bridge/I-95 Improvement Project

MassDOT’s design/build contractor for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of November 10 and 17. The work will require day and night lane closures on I-95 northbound and southbound throughout the project limits. Daytime closures will be limited to single lanes. Nighttime closures may be single or multiple lanes, depending on the location. Lane closures related to specific activities are listed in the schedule below, as appropriate. Some work may occur on weekends.

Please note: No work will be performed on Veteran’s Day, November 11. There will be a single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west for most of the remainder of the year. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday and 7 AM to 3 PM on Fridays and Saturdays.

The activities and schedule are as follows:

Week of November 10:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM
  • Drain line installation – 7 AM to 5 PM
  • Excavate and grade – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile installation – 7 AM to 5 PM
  • Equipment and materials mobilization (crane, steel, etc.) – 7 AM to 5 PM

Week of November 17:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile and footing concrete installation – 7 AM to 5 PM

 

Written By:

Recent Posts

MBTA: Weekend Commuter Boat Service Returns May 28 posted on May 26

MBTA: Weekend Commuter Boat Service Returns May 28

MassDOT weekend commuter boat service will be provided for the third year between Hingham, Hull, Georges Island, Grape Island and Boston. The service begins Memorial Day weekend and will continue through the Labor Day weekend. “Commuter ferry service on the weekends during the two previous   …Continue Reading MBTA: Weekend Commuter Boat Service Returns May 28

Boston: Commonwealth Avenue Bridge Project Community Meeting posted on May 26

Boston: Commonwealth Avenue Bridge Project Community Meeting

MassDOT has scheduled a community meeting for the Commonwealth Avenue Bridge Reconstruction Project as follows:   Thursday, June 2, 6:00 PM to 8:00 PM, Jacob Sleeper Auditorium (CGS 129), Boston University, 871 Commonwealth Avenue. The Commonwealth Avenue Bridge Reconstruction Project will replace the existing superstructure   …Continue Reading Boston: Commonwealth Avenue Bridge Project Community Meeting

Plan Ahead for Memorial Day Weekend Travel posted on May 24

Plan Ahead for Memorial Day Weekend Travel

MassDOT encourages travelers to plan ahead and travel safely during the Memorial Day holiday weekend.  The heaviest traffic is observed during Thursday, Friday, and Monday afternoons and early evenings.  Drivers are encouraged to make travel plans accordingly and if possible avoid peak traffic volumes between   …Continue Reading Plan Ahead for Memorial Day Weekend Travel