Post Content

Whittier Bridge/I-95 Improvement Project

MassDOT’s design/build contractor for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of November 10 and 17. The work will require day and night lane closures on I-95 northbound and southbound throughout the project limits. Daytime closures will be limited to single lanes. Nighttime closures may be single or multiple lanes, depending on the location. Lane closures related to specific activities are listed in the schedule below, as appropriate. Some work may occur on weekends.

Please note: No work will be performed on Veteran’s Day, November 11. There will be a single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west for most of the remainder of the year. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday and 7 AM to 3 PM on Fridays and Saturdays.

The activities and schedule are as follows:

Week of November 10:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM
  • Drain line installation – 7 AM to 5 PM
  • Excavate and grade – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile installation – 7 AM to 5 PM
  • Equipment and materials mobilization (crane, steel, etc.) – 7 AM to 5 PM

Week of November 17:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile and footing concrete installation – 7 AM to 5 PM

 

Written By:

Recent Posts

Whittier Bridge I-95 Update: River Boaters Notice posted on Apr 18

Whittier Bridge I-95 Update: River Boaters Notice

The Whittier Bridge/I-95 Improvement Project continues through the 2014 boating season. Much of the work this season to construct the new northbound span of the Whittier Bridge is taking place from the Merrimack River to the immediate east of the existing bridge. Several large barges,   …Continue Reading Whittier Bridge I-95 Update: River Boaters Notice

Route 79/Braga Bridge Project Public Meeting Set posted on Apr 17

Route 79/Braga Bridge Project Public Meeting Set

Please join MassDOT at a public meeting for an update on construction progress on the Route 79/Braga Bridge Improvements Project, as follows: Wednesday, April 30, 6:30 pm to 8:30 pm, Heritage State Park Auditorium, 200 Davol Street, Fall River The meeting will include an opportunity   …Continue Reading Route 79/Braga Bridge Project Public Meeting Set

MBTA: New Locomotive Now in Service posted on Apr 16

MBTA: New Locomotive Now in Service

MBTA General Manager Dr. Beverly Scott today at Boston North Station welcomed the first of 40 new Commuter Rail locomotives as it was placed into service on the Haverhill Line.   To replace existing locomotives between 35 and 40 years old, the MBTA is procuring forty   …Continue Reading MBTA: New Locomotive Now in Service