Post Content

Whittier Bridge/I-95 Improvement Project

MassDOT’s design/build contractor for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of November 10 and 17. The work will require day and night lane closures on I-95 northbound and southbound throughout the project limits. Daytime closures will be limited to single lanes. Nighttime closures may be single or multiple lanes, depending on the location. Lane closures related to specific activities are listed in the schedule below, as appropriate. Some work may occur on weekends.

Please note: No work will be performed on Veteran’s Day, November 11. There will be a single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west for most of the remainder of the year. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday and 7 AM to 3 PM on Fridays and Saturdays.

The activities and schedule are as follows:

Week of November 10:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM
  • Drain line installation – 7 AM to 5 PM
  • Excavate and grade – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile installation – 7 AM to 5 PM
  • Equipment and materials mobilization (crane, steel, etc.) – 7 AM to 5 PM

Week of November 17:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile and footing concrete installation – 7 AM to 5 PM

 

Written By:

Recent Posts

Boston: Plan Ahead for I-90 Lane Restrictions posted on Jul 23

Boston: Plan Ahead for I-90 Lane Restrictions

MassDOT on Sunday, July 27 at 9:00pm will begin work to improve the median and Commonwealth Avenue Bridge substructure on Interstate 90 in Boston. Beginning Sunday night at 9:00pm and lasting for approximately six months, the left lanes in both Eastbound and Westbound directions on   …Continue Reading Boston: Plan Ahead for I-90 Lane Restrictions

Methuen Rotary Project: Travel Impacts posted on Jul 22

Methuen Rotary Project: Travel Impacts

MassDOT has scheduled upcoming lane closures as part of the Methuen Rotary Reconstruction Project.  Beginning on Monday, July 28, 2014 until further notice, the I-93 breakdown lane will be closed from Exit 46 – Routes 110/113 to Exit 47 – Pelham St. on I-93 Northbound   …Continue Reading Methuen Rotary Project: Travel Impacts

Tobin Bridge: All-Electronic Tolling Begins Monday, July 21 posted on Jul 18

Tobin Bridge: All-Electronic Tolling Begins Monday, July 21

Effective Monday, July 21, prior to the morning commute, tolling on the Tobin Bridge will convert to the all-electronic format. The new toll system will eliminate the need for customers to pay the toll in cash. The system is equipped to read E-ZPass transponders for   …Continue Reading Tobin Bridge: All-Electronic Tolling Begins Monday, July 21