Post Content

Whittier Bridge/I-95 Improvement Project

MassDOT’s design/build contractor for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of November 10 and 17. The work will require day and night lane closures on I-95 northbound and southbound throughout the project limits. Daytime closures will be limited to single lanes. Nighttime closures may be single or multiple lanes, depending on the location. Lane closures related to specific activities are listed in the schedule below, as appropriate. Some work may occur on weekends.

Please note: No work will be performed on Veteran’s Day, November 11. There will be a single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west for most of the remainder of the year. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday and 7 AM to 3 PM on Fridays and Saturdays.

The activities and schedule are as follows:

Week of November 10:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM
  • Drain line installation – 7 AM to 5 PM
  • Excavate and grade – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile installation – 7 AM to 5 PM
  • Equipment and materials mobilization (crane, steel, etc.) – 7 AM to 5 PM

Week of November 17:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile and footing concrete installation – 7 AM to 5 PM

 

Written By:

Recent Posts

Lexington: Route 2 Bridges Project Update posted on Aug 21

Lexington: Route 2 Bridges Project Update

MassDOT next week will begin preparations to replace the Route 2 Bridges over I-95 in Lexington by implementing a traffic shift on Route 2 east and westbound. The work to prepare for the shift requires lane closures from 8:00 PM each night to 5:00 AM   …Continue Reading Lexington: Route 2 Bridges Project Update

Governor Patrick Announces Knowledge Corridor Line Purchase posted on Aug 20

Governor Patrick Announces Knowledge Corridor Line Purchase

Governor Deval Patrick today announced an agreement in principle allowing the Commonwealth to purchase the Knowledge Corridor rail line between East Northfield and Springfield from Pan Am Southern, a joint venture of Pan Am and Norfolk Southern. The 49-mile segment of rail is currently undergoing   …Continue Reading Governor Patrick Announces Knowledge Corridor Line Purchase

Morton Street Bridge Opens Ahead of Schedule posted on Aug 19

Morton Street Bridge Opens Ahead of Schedule

MassDOT announced the successful opening of the new Morton Street Bridge in Mattapan more than a full day ahead of the already accelerated schedule. The original structurally deficient bridge carrying Morton Street over the MBTA commuter rail tracks closed on Friday, August 8 for final   …Continue Reading Morton Street Bridge Opens Ahead of Schedule