Post Content

Whittier Bridge/I-95 Improvement Project

MassDOT’s design/build contractor for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of November 10 and 17. The work will require day and night lane closures on I-95 northbound and southbound throughout the project limits. Daytime closures will be limited to single lanes. Nighttime closures may be single or multiple lanes, depending on the location. Lane closures related to specific activities are listed in the schedule below, as appropriate. Some work may occur on weekends.

Please note: No work will be performed on Veteran’s Day, November 11. There will be a single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west for most of the remainder of the year. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday and 7 AM to 3 PM on Fridays and Saturdays.

The activities and schedule are as follows:

Week of November 10:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM
  • Drain line installation – 7 AM to 5 PM
  • Excavate and grade – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile installation – 7 AM to 5 PM
  • Equipment and materials mobilization (crane, steel, etc.) – 7 AM to 5 PM

Week of November 17:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile and footing concrete installation – 7 AM to 5 PM

 

Written By:

Recent Posts

RMV New Steps: More Customers Eligible for Online Transactions posted on Dec 11

RMV New Steps: More Customers Eligible for Online Transactions

The Massachusetts Registry of Motor Vehicles (RMV) is taking steps to allow more customers the opportunity to renew a driver’s license or ID card online. The RMV has extended the length of time a customer can use a license photo from 9 years to 14   …Continue Reading RMV New Steps: More Customers Eligible for Online Transactions

MassDOT Continuing Snow and Ice Operations posted on Dec 9

MassDOT Continuing Snow and Ice Operations

MassDOT is continuing its snow and ice removal operations throughout Saturday evening and into the overnight hours and is continuing to remind members of the public to minimize travel if possible, exercise safe driving behavior, and make safe and informed decisions before heading out onto   …Continue Reading MassDOT Continuing Snow and Ice Operations

MassDOT Weekend Winter Weather Preparations posted on Dec 8

MassDOT Weekend Winter Weather Preparations

MassDOT advises the public that with snowfall expected Saturday, motorists are advised to minimize travel where possible, consider public transportation, and make informed and safe decisions before heading out onto the roadways. “The weather forecast is calling for snow to begin on Saturday morning, mix   …Continue Reading MassDOT Weekend Winter Weather Preparations