Post Content

Whittier Bridge/I-95 Improvement Project

MassDOT’s design/build contractor for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of November 10 and 17. The work will require day and night lane closures on I-95 northbound and southbound throughout the project limits. Daytime closures will be limited to single lanes. Nighttime closures may be single or multiple lanes, depending on the location. Lane closures related to specific activities are listed in the schedule below, as appropriate. Some work may occur on weekends.

Please note: No work will be performed on Veteran’s Day, November 11. There will be a single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west for most of the remainder of the year. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday and 7 AM to 3 PM on Fridays and Saturdays.

The activities and schedule are as follows:

Week of November 10:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM
  • Drain line installation – 7 AM to 5 PM
  • Excavate and grade – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile installation – 7 AM to 5 PM
  • Equipment and materials mobilization (crane, steel, etc.) – 7 AM to 5 PM

Week of November 17:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile and footing concrete installation – 7 AM to 5 PM

 

Written By:

Recent Posts

New Bedford-Fairhaven Bridge Public Meeting Set posted on Jan 29

New Bedford-Fairhaven Bridge Public Meeting Set

MassDOT is conducting a study of the New Bedford-Fairhaven Bridge Corridor, a bridge that spans New Bedford Harbor. The swing bridge connecting the communities of New Bedford and Fairhaven is functionally obsolete, constrains marine traffic, and its opening results in extensive vehicle delays. This study   …Continue Reading New Bedford-Fairhaven Bridge Public Meeting Set

Winter Storm Update: Travel Ban Lifted, MBTA Open posted on Jan 28

Winter Storm Update: Travel Ban Lifted, MBTA Open

The statewide travel ban has been lifted as of midnight.  Motorists, especially those in the City of Boston and Eastern counties, are asked to use caution as MassDOT crews continue to plow and clear state roadways and ramps. Parking bans are still in effect in   …Continue Reading Winter Storm Update: Travel Ban Lifted, MBTA Open

Winter Storm Update: Statewide Travel Ban, MBTA Closed Tuesday, January 27 posted on Jan 26

Winter Storm Update: Statewide Travel Ban, MBTA Closed Tuesday, January 27

Governor Charlie Baker has signed an Executive Order allowing for the enforcement of a statewide travel ban effective at midnight, Monday, January 26. The following exceptions shall exist for the ban and all drivers are encouraged to remain safe and use their best judgment:     …Continue Reading Winter Storm Update: Statewide Travel Ban, MBTA Closed Tuesday, January 27