Post Content

Whittier Bridge/I-95 Improvement Project

MassDOT’s design/build contractor for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of November 10 and 17. The work will require day and night lane closures on I-95 northbound and southbound throughout the project limits. Daytime closures will be limited to single lanes. Nighttime closures may be single or multiple lanes, depending on the location. Lane closures related to specific activities are listed in the schedule below, as appropriate. Some work may occur on weekends.

Please note: No work will be performed on Veteran’s Day, November 11. There will be a single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west for most of the remainder of the year. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday and 7 AM to 3 PM on Fridays and Saturdays.

The activities and schedule are as follows:

Week of November 10:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM
  • Drain line installation – 7 AM to 5 PM
  • Excavate and grade – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile installation – 7 AM to 5 PM
  • Equipment and materials mobilization (crane, steel, etc.) – 7 AM to 5 PM

Week of November 17:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile and footing concrete installation – 7 AM to 5 PM

 

Written By:

Recent Posts

MBTA: Fitchburg Line Weekend Service Suspension posted on Mar 27

MBTA: Fitchburg Line Weekend Service Suspension

The MBTA has issued a Service Alert:  No Weekend Service on the commuter rail Fitchburg Main Line for the period from April 25th, 2015 through November 22nd, 2015. The suspension of weekend service will allow construction of major improvements on the Fitchburg Main Line to   …Continue Reading MBTA: Fitchburg Line Weekend Service Suspension

Employers Honored for Excellence in Commuter Options posted on Mar 26

Employers Honored for Excellence in Commuter Options

The efforts of more than 170 Massachusetts businesses, colleges, and universities, who promote active, healthy, and sustainable commute options, were celebrated today for helping Massachusetts to reduce traffic congestion, to promote healthy lifestyles, and benefit the environment. The Massachusetts Excellence in Commuter Options (ECO) Awards   …Continue Reading Employers Honored for Excellence in Commuter Options

Longfellow Bridge: “Salt and Pepper” Towers Work posted on Mar 26

Longfellow Bridge: “Salt and Pepper” Towers Work

MassDOT on Saturday, March 28 will begin preparing to dismantle the downstream “salt and pepper” towers as part of the Longfellow Bridge Restoration Project. MassDOT’s contractor, White-Skanska-Consigli JV (WSC), coordinated with the cities of Cambridge and Boston as well as the MBTA to begin dismantling   …Continue Reading Longfellow Bridge: “Salt and Pepper” Towers Work