Post Content

Whittier Bridge/I-95 Improvement Project

MassDOT’s design/build contractor for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of November 10 and 17. The work will require day and night lane closures on I-95 northbound and southbound throughout the project limits. Daytime closures will be limited to single lanes. Nighttime closures may be single or multiple lanes, depending on the location. Lane closures related to specific activities are listed in the schedule below, as appropriate. Some work may occur on weekends.

Please note: No work will be performed on Veteran’s Day, November 11. There will be a single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west for most of the remainder of the year. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday and 7 AM to 3 PM on Fridays and Saturdays.

The activities and schedule are as follows:

Week of November 10:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM
  • Drain line installation – 7 AM to 5 PM
  • Excavate and grade – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile installation – 7 AM to 5 PM
  • Equipment and materials mobilization (crane, steel, etc.) – 7 AM to 5 PM

Week of November 17:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile and footing concrete installation – 7 AM to 5 PM

 

Written By:

Recent Posts

Route 79/Braga Bridge Project Traffic Update posted on Oct 30

Route 79/Braga Bridge Project Traffic Update

MassDOT will begin implementing traffic changes for the next stage of construction for the Route 79/Braga Bridge Project on Wednesday, November 12. The following changes will be implemented in a phased approach through the middle of December: Vehicles on Route 79/138 (Broadway) bound for Interstate   …Continue Reading Route 79/Braga Bridge Project Traffic Update

RMV: Promise to Customers posted on Oct 28

RMV: Promise to Customers

Today, MassDOT Secretary & CEO Richard A. Davey and MassDOT Registrar of Motor Vehicles Celia J. Blue offered a 10 point promise to RMV customers. The reimagining effort comprises current, ongoing and future initiatives that the RMV has in development to better the Registry experience.   …Continue Reading RMV: Promise to Customers

November E-ZPass Sign Up: Chelsea, Everett posted on Oct 28

November E-ZPass Sign Up: Chelsea, Everett

MassDOT is encouraging motorists to join E-ZPass with All-Electronic Tolling now in place on the Tobin Bridge and expanding statewide within the next two years. The E-ZPass Street Team will be enrolling new customers in the E-ZPass throughout the Fall season. The E-ZPass Van schedule   …Continue Reading November E-ZPass Sign Up: Chelsea, Everett