Post Content

Whittier Bridge/I-95 Improvement Project

MassDOT’s design/build contractor for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of November 10 and 17. The work will require day and night lane closures on I-95 northbound and southbound throughout the project limits. Daytime closures will be limited to single lanes. Nighttime closures may be single or multiple lanes, depending on the location. Lane closures related to specific activities are listed in the schedule below, as appropriate. Some work may occur on weekends.

Please note: No work will be performed on Veteran’s Day, November 11. There will be a single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west for most of the remainder of the year. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday and 7 AM to 3 PM on Fridays and Saturdays.

The activities and schedule are as follows:

Week of November 10:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM
  • Drain line installation – 7 AM to 5 PM
  • Excavate and grade – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile installation – 7 AM to 5 PM
  • Equipment and materials mobilization (crane, steel, etc.) – 7 AM to 5 PM

Week of November 17:

I-95 at northern end of project

  • Median topsoil and detention pond excavation – 7 AM to 3:30 PM

Evans Place Bridge/Main Street

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM

I-95 at southern end of project

  • Newburyport water line installation – 7 AM to 3:30 PM

Whittier Bridge

  • Continue work at Piers 2 and 3 – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Footing forms and concrete installation – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Pile and footing concrete installation – 7 AM to 5 PM

 

Written By:

Recent Posts

Springfield: I-91 Viaduct Public Meeting Set posted on Aug 18

Springfield: I-91 Viaduct Public Meeting Set

MassDOT has scheduled a Public Information Meeting for the I-91 Viaduct Rehabilitation Project in Springfield as follows: Wednesday, September 13, 6:30 PM to 8:30 PM, One Financial Plaza, 3rd Floor Conference Room, 1350 Main Street, Springfield Please join MassDOT at a public information meeting for   …Continue Reading Springfield: I-91 Viaduct Public Meeting Set

Baker-Polito Administration Celebrates Framingham Commuter Rail Lot Ribbon Cutting posted on Aug 17

Baker-Polito Administration Celebrates Framingham Commuter Rail Lot Ribbon Cutting

The Baker-Polito Administration along with state and regional transit officials today celebrated the ribbon cutting of the Framingham Commuter Rail Station Parking Lot. Management of Framingham Commuter Rail Station, including the station’s parking areas, was transferred to the MetroWest Regional Transit Authority (MWRTA) in a   …Continue Reading Baker-Polito Administration Celebrates Framingham Commuter Rail Lot Ribbon Cutting

Commonwealth Avenue Bridge: Bridges Open, MBTA Green Line Resumes posted on Aug 16

Commonwealth Avenue Bridge: Bridges Open, MBTA Green Line Resumes

MassDOT has announced that the current phase of major work on the Commonwealth Avenue Bridge finished during the overnight hours. As of 5:00 AM on Wednesday, August 16: Commonwealth Avenue between Packard’s Corner and Kenmore Square will reopen to through vehicular traffic. Boston University (BU) Bridge will   …Continue Reading Commonwealth Avenue Bridge: Bridges Open, MBTA Green Line Resumes