Worcester, Burns Bridge, April 2013The $89.9 million Kenneth F. Burns Memorial Bridge Replacement Project will continue through summer 2013 with advisories for boat traffic on the lake in the area.  

The Burns Bridge Project is part of the Patrick-Murray Administration’s historic Accelerated Bridge Program to repair or replace structurally deficient bridges throughout the Commonwealth.

The project will widen the bridge from two to three travel lanes in each direction and include accessible sidewalks and dedicated bicycle lanes on both sides of the bridge. 

Summertime construction will result in a change from normal conditions on Lake Quinsigamond with certain arches of the existing bridge closed to all boat traffic. A safe passage will be maintained beneath the existing bridge, and the new one as it begins to take shape.  Boaters, please note:

  • No Wake Zones have been extended for 300 feet to the north and south of the bridge. These are marked by lighted warning signs and buoys.
  • During this summer, the spans which are safe to use will not always be the same. A system of roadway traffic signals suspended over the arches of the existing bridge will mark the safe passage for boaters. A green light shows a safe passage, a red light indicates a closed arch. Often, only a single span will be available.
  • Under conditions when only a single span is available, power boats shall yield to non-motorized craft. Northbound boats will yield to those going south.
  • Tying up to or climbing on work barges is strictly prohibited. Local police will be monitoring boater compliance. Work barges are not safe for non-construction personnel.

To learn more, visit www.mass.gov/massdot/kenburnsbridge.

Written By:

Recent Posts

MassDOT Announces Completion of Trapelo Road Reconstruction Project posted on Sep 28

MassDOT Announces Completion of Trapelo Road Reconstruction Project

Transportation Secretary and CEO Stephanie Pollack, Highway Administrator Thomas J. Tinlin, State Senator Will Brownsberger and state and local officials today announced the completion of the Trapelo Road Reconstruction project. A ribbon cutting ceremony was held today in Belmont to celebrate the project’s conclusion. “The   …Continue Reading MassDOT Announces Completion of Trapelo Road Reconstruction Project

Martha’s Vineyard Drawbridge Nationally Recognized as Top 10 Project posted on Sep 28

Martha’s Vineyard Drawbridge Nationally Recognized as Top 10 Project

MassDOT announced that ROADS & BRIDGES magazine has named the Lagoon Pond Drawbridge on Martha’s Vineyard to its list of Top 10 Bridge Projects for 2016. A $43.7 million project, the Lagoon Pond Drawbridge is a 350-foot bascule bridge that it is opened and closed   …Continue Reading Martha’s Vineyard Drawbridge Nationally Recognized as Top 10 Project

MassDOT Activates Real Time Traffic Displays on Interstate 195 posted on Sep 27

MassDOT Activates Real Time Traffic Displays on Interstate 195

MassDOT announced the expansion of its Real Time Traffic System (Go-Time) with additional displays along 40 miles of Interstate 195, from Seekonk to Wareham. This expansion will include 10 signs, providing travel times to 20 destinations, (12 of these 20 destinations will be displaying travel   …Continue Reading MassDOT Activates Real Time Traffic Displays on Interstate 195