Photo 4(5)MassDOT’s contractor, White-Skanska-Consigli (WSC), anticipates setting up the final configuration of Stage 3 construction for the Longfellow Bridge Rehabilitation Project by Thursday, February 11, 2016. The shift of the tracks to their temporary positions was completed over a series of MBTA Red Line Weekend Diversions. The relocation of the large barrier fence along the tracks will be completed February 1.

The installation of the upstream “Salt and Pepper” towers, hampered by the cold temperatures of mid-January, is complete with the last stones installed. Now that the towers are complete, removal of the staging is underway, followed by the placement of concrete sidewalks and curbs adjacent to the towers. Once the sidewalks and curbs are in place, the final sections of temporary fence needed for the new upstream bicycle lane can be installed.

WSC anticipates the final set up for the upstream bicycle lane will be complete by the end of the day on Thursday, February 11, 2016, when inbound and outbound bike travel is shifted. Stage 3 work will take approximately eight months to complete.

Travel Configuration

All bike travel, both inbound and outbound, will be shifted to the sidewalk on the upstream side of the bridge on February 11. During this stage, inbound vehicles and all pedestrians will continue to use the downstream side of the bridge.

MBTA Red Line Configuration

The construction of the temporary outbound Red Line track (called a “shoo-fly”) on the roadway is complete. The outbound trains were shifted to the shoo-fly track and the inbound trains were shifted to the old outbound track in mid-January. This shift allows WSC to rehabilitate the bridge under the current location of the MBTA inbound tracks.

The Cambridge-bound detour remains in place using the existing signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway (Route 28)/Charles River Dam Road and Land Boulevard.

For more information, visit the project website at www.mass.gov/massdot/longfellowbridge. For questions or issues and concerns related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us. View construction progress photos on MassDOT’s Longfellow Bridge Flickr Album.

Written By:

Tags: ,

Recent Posts

Baker-Polito Administration Awards $16 Million for 36 Municipal Small Bridge Projects posted on Mar 29

Baker-Polito Administration Awards $16 Million for 36 Municipal Small Bridge Projects

The Baker-Polito Administration today awarded $16 million to 36 communities for the funding of preservation, repair or replacement of bridges with spans of 10 to 20 feet. The funding is the first round of awards through the administration’s Municipal Small Bridge Program, and was announced   …Continue Reading Baker-Polito Administration Awards $16 Million for 36 Municipal Small Bridge Projects

MassDOT Announces Quaboag Connector Van Service Pilot posted on Mar 28

MassDOT Announces Quaboag Connector Van Service Pilot

MassDOT announced today that a new “Quaboag Connector” van transportation service is available for residents in the Quaboag Valley region which includes the towns of Belchertown, Brookfield, Hardwick, Monson, Palmer, Ware, Warren and West Brookfield. The curb-to-curb service has begun as a 12-month pilot that   …Continue Reading MassDOT Announces Quaboag Connector Van Service Pilot

Aeronautics: Baker-Polito Administration Awards Funding to Minute Man Air Field posted on Mar 28

Aeronautics: Baker-Polito Administration Awards Funding to Minute Man Air Field

The Baker-Polito Administration’s Department of Transportation (MassDOT) has announced an award of $850,000 to Minute Man Air Field in Stow for a project to make necessary repairs and reconstruction improvements. MassDOT Aeronautics Administrator Jeffrey DeCarlo joined State Representative Kate Hogan, elected and local officials, municipal   …Continue Reading Aeronautics: Baker-Polito Administration Awards Funding to Minute Man Air Field