Photo 4(5)MassDOT’s contractor, White-Skanska-Consigli (WSC), anticipates setting up the final configuration of Stage 3 construction for the Longfellow Bridge Rehabilitation Project by Thursday, February 11, 2016. The shift of the tracks to their temporary positions was completed over a series of MBTA Red Line Weekend Diversions. The relocation of the large barrier fence along the tracks will be completed February 1.

The installation of the upstream “Salt and Pepper” towers, hampered by the cold temperatures of mid-January, is complete with the last stones installed. Now that the towers are complete, removal of the staging is underway, followed by the placement of concrete sidewalks and curbs adjacent to the towers. Once the sidewalks and curbs are in place, the final sections of temporary fence needed for the new upstream bicycle lane can be installed.

WSC anticipates the final set up for the upstream bicycle lane will be complete by the end of the day on Thursday, February 11, 2016, when inbound and outbound bike travel is shifted. Stage 3 work will take approximately eight months to complete.

Travel Configuration

All bike travel, both inbound and outbound, will be shifted to the sidewalk on the upstream side of the bridge on February 11. During this stage, inbound vehicles and all pedestrians will continue to use the downstream side of the bridge.

MBTA Red Line Configuration

The construction of the temporary outbound Red Line track (called a “shoo-fly”) on the roadway is complete. The outbound trains were shifted to the shoo-fly track and the inbound trains were shifted to the old outbound track in mid-January. This shift allows WSC to rehabilitate the bridge under the current location of the MBTA inbound tracks.

The Cambridge-bound detour remains in place using the existing signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway (Route 28)/Charles River Dam Road and Land Boulevard.

For more information, visit the project website at www.mass.gov/massdot/longfellowbridge. For questions or issues and concerns related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us. View construction progress photos on MassDOT’s Longfellow Bridge Flickr Album.

Written By:

Tags: ,

Recent Posts

MassDOT: Federal Emergency Management Agency Reimbursements posted on Feb 18

MassDOT: Federal Emergency Management Agency Reimbursements

MassDOT has succeeded in recovering more than $21 million dollars from the Federal Emergency Management Agency (FEMA) in 2016 for past disaster events. These are reimbursements for MassDOT operations and logistics during past federal government disaster declarations and the reimbursements have been deposited into the   …Continue Reading MassDOT: Federal Emergency Management Agency Reimbursements

MassDOT to Expand Pothole Tracking Program posted on Feb 17

MassDOT to Expand Pothole Tracking Program

MassDOT has announced that it is in the process of expanding its new, innovative pothole information program which was piloted in areas of Central and Western Massachusetts over the past year and includes an online MassDOT Potholes Dashboard that provides data to the public. This   …Continue Reading MassDOT to Expand Pothole Tracking Program

Baker-Polito Administration Announces First Municipal Small Bridge Program Awards posted on Feb 16

Baker-Polito Administration Announces First Municipal Small Bridge Program Awards

Lieutenant Governor Karyn Polito, municipal leaders, and MassDOT officials today announced the first two awards through the Baker-Polito Administration’s Municipal Small Bridge Program. A ceremony was held in Lenox to award a total of $750,000 to the towns of Washington and Blandford for small bridge   …Continue Reading Baker-Polito Administration Announces First Municipal Small Bridge Program Awards