Photo 4(5)MassDOT’s contractor, White-Skanska-Consigli (WSC), anticipates setting up the final configuration of Stage 3 construction for the Longfellow Bridge Rehabilitation Project by Thursday, February 11, 2016. The shift of the tracks to their temporary positions was completed over a series of MBTA Red Line Weekend Diversions. The relocation of the large barrier fence along the tracks will be completed February 1.

The installation of the upstream “Salt and Pepper” towers, hampered by the cold temperatures of mid-January, is complete with the last stones installed. Now that the towers are complete, removal of the staging is underway, followed by the placement of concrete sidewalks and curbs adjacent to the towers. Once the sidewalks and curbs are in place, the final sections of temporary fence needed for the new upstream bicycle lane can be installed.

WSC anticipates the final set up for the upstream bicycle lane will be complete by the end of the day on Thursday, February 11, 2016, when inbound and outbound bike travel is shifted. Stage 3 work will take approximately eight months to complete.

Travel Configuration

All bike travel, both inbound and outbound, will be shifted to the sidewalk on the upstream side of the bridge on February 11. During this stage, inbound vehicles and all pedestrians will continue to use the downstream side of the bridge.

MBTA Red Line Configuration

The construction of the temporary outbound Red Line track (called a “shoo-fly”) on the roadway is complete. The outbound trains were shifted to the shoo-fly track and the inbound trains were shifted to the old outbound track in mid-January. This shift allows WSC to rehabilitate the bridge under the current location of the MBTA inbound tracks.

The Cambridge-bound detour remains in place using the existing signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway (Route 28)/Charles River Dam Road and Land Boulevard.

For more information, visit the project website at www.mass.gov/massdot/longfellowbridge. For questions or issues and concerns related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us. View construction progress photos on MassDOT’s Longfellow Bridge Flickr Album.

Written By:

Tags: ,

Recent Posts

Methuen Rotary: New I-93 Northbound Ramp Opens July 30 posted on Jul 25

Methuen Rotary: New I-93 Northbound Ramp Opens July 30

MassDOT’s Methuen Rotary Interchange Reconstruction Project reaches a major milestone on Saturday, July 30, when the first new ramp of the reconstructed interchange opens to traffic. The new I-93 northbound on-ramp is located approximately 400 feet east of the current ramp. A new signal will   …Continue Reading Methuen Rotary: New I-93 Northbound Ramp Opens July 30

Longfellow Bridge: Next Stage of Construction to Begin in August posted on Jul 22

Longfellow Bridge: Next Stage of Construction to Begin in August

MassDOT’s contractor is scheduled to begin the next stage of construction on the Longfellow Bridge in August 2016 now that the MBTA Red Line trains have been moved to their new locations. In this stage, bridge rehabilitation work will occur under the MBTA outbound track.   …Continue Reading Longfellow Bridge: Next Stage of Construction to Begin in August

Maynard: Assabet River Rail Trail to Connect with MBTA Station posted on Jul 21

Maynard: Assabet River Rail Trail to Connect with MBTA Station

MassDOT Highway Administrator Tom Tinlin today joined local legislators to break ground on the Assabet River Rail Trail construction project in Maynard. The $6.7 million project links the Assabet River National Wildlife Refuge with the downtown Maynard business district as well as the MBTA South   …Continue Reading Maynard: Assabet River Rail Trail to Connect with MBTA Station