Photo 4(5)MassDOT’s contractor, White-Skanska-Consigli (WSC), anticipates setting up the final configuration of Stage 3 construction for the Longfellow Bridge Rehabilitation Project by Thursday, February 11, 2016. The shift of the tracks to their temporary positions was completed over a series of MBTA Red Line Weekend Diversions. The relocation of the large barrier fence along the tracks will be completed February 1.

The installation of the upstream “Salt and Pepper” towers, hampered by the cold temperatures of mid-January, is complete with the last stones installed. Now that the towers are complete, removal of the staging is underway, followed by the placement of concrete sidewalks and curbs adjacent to the towers. Once the sidewalks and curbs are in place, the final sections of temporary fence needed for the new upstream bicycle lane can be installed.

WSC anticipates the final set up for the upstream bicycle lane will be complete by the end of the day on Thursday, February 11, 2016, when inbound and outbound bike travel is shifted. Stage 3 work will take approximately eight months to complete.

Travel Configuration

All bike travel, both inbound and outbound, will be shifted to the sidewalk on the upstream side of the bridge on February 11. During this stage, inbound vehicles and all pedestrians will continue to use the downstream side of the bridge.

MBTA Red Line Configuration

The construction of the temporary outbound Red Line track (called a “shoo-fly”) on the roadway is complete. The outbound trains were shifted to the shoo-fly track and the inbound trains were shifted to the old outbound track in mid-January. This shift allows WSC to rehabilitate the bridge under the current location of the MBTA inbound tracks.

The Cambridge-bound detour remains in place using the existing signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway (Route 28)/Charles River Dam Road and Land Boulevard.

For more information, visit the project website at www.mass.gov/massdot/longfellowbridge. For questions or issues and concerns related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us. View construction progress photos on MassDOT’s Longfellow Bridge Flickr Album.

Written By:

Tags: ,

Recent Posts

A First in the State: MassDOT Uses New Construction Technique on Route 2/I-95 Project posted on Aug 28

A First in the State: MassDOT Uses New Construction Technique on Route 2/I-95 Project

From smaller projects to the largest, MassDOT uses the latest, proven innovative techniques. For the first time in the state, MassDOT is using precast, modular concrete abutments on the Route 2/I-95 Bridge Replacement Project. Accelerated Bridge Construction technologies, such as this one, reduce project duration   …Continue Reading A First in the State: MassDOT Uses New Construction Technique on Route 2/I-95 Project

Route 107 Corridor Public Meetings Scheduled posted on Aug 26

Route 107 Corridor Public Meetings Scheduled

Public Information Meetings for the Route 107 Corridor Study have been scheduled as follows: Wednesday, September 7, 6:00 PM to 8:00 PM, Lynn English High School, Auditorium, 50 Goodridge Street Tuesday, September 13, 6:00 PM to 8:00 PM, Collins Middle School, Auditorium, 29 Highland Avenue,   …Continue Reading Route 107 Corridor Public Meetings Scheduled

Gill-Montague Bridge Rehabilitation Celebrated posted on Aug 25

Gill-Montague Bridge Rehabilitation Celebrated

MassDOT Secretary and CEO Stephanie Pollack and Highway Administrator Thomas J. Tinlin joined Director of Governor Charlie Baker’s Western Massachusetts Office Michael Knapik, Senate President Stanley C. Rosenberg, state and local officials today in Turners Falls to celebrate the complete rehabilitation of the Avenue A   …Continue Reading Gill-Montague Bridge Rehabilitation Celebrated