Photo 4(5)MassDOT’s contractor, White-Skanska-Consigli (WSC), anticipates setting up the final configuration of Stage 3 construction for the Longfellow Bridge Rehabilitation Project by Thursday, February 11, 2016. The shift of the tracks to their temporary positions was completed over a series of MBTA Red Line Weekend Diversions. The relocation of the large barrier fence along the tracks will be completed February 1.

The installation of the upstream “Salt and Pepper” towers, hampered by the cold temperatures of mid-January, is complete with the last stones installed. Now that the towers are complete, removal of the staging is underway, followed by the placement of concrete sidewalks and curbs adjacent to the towers. Once the sidewalks and curbs are in place, the final sections of temporary fence needed for the new upstream bicycle lane can be installed.

WSC anticipates the final set up for the upstream bicycle lane will be complete by the end of the day on Thursday, February 11, 2016, when inbound and outbound bike travel is shifted. Stage 3 work will take approximately eight months to complete.

Travel Configuration

All bike travel, both inbound and outbound, will be shifted to the sidewalk on the upstream side of the bridge on February 11. During this stage, inbound vehicles and all pedestrians will continue to use the downstream side of the bridge.

MBTA Red Line Configuration

The construction of the temporary outbound Red Line track (called a “shoo-fly”) on the roadway is complete. The outbound trains were shifted to the shoo-fly track and the inbound trains were shifted to the old outbound track in mid-January. This shift allows WSC to rehabilitate the bridge under the current location of the MBTA inbound tracks.

The Cambridge-bound detour remains in place using the existing signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway (Route 28)/Charles River Dam Road and Land Boulevard.

For more information, visit the project website at www.mass.gov/massdot/longfellowbridge. For questions or issues and concerns related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us. View construction progress photos on MassDOT’s Longfellow Bridge Flickr Album.

Written By:

Tags: ,

Recent Posts

MBTA Future: Focus40 Seeks Your Ideas posted on Dec 2

MBTA Future: Focus40 Seeks Your Ideas

The Focus40 Street Team has been out at stops and stations around the system, collecting your ideas for the MBTA’s future. The Street Team is made up of MassDOT staff, community members, and partner organizations. We have already engaged with over 1,000 MBTA customers and   …Continue Reading MBTA Future: Focus40 Seeks Your Ideas

MassDOT, MAPFRE Insurance Encourage Motorists to Prepare for Winter Driving posted on Dec 1

MassDOT, MAPFRE Insurance Encourage Motorists to Prepare for Winter Driving

MassDOT and MAPFRE Insurance offer helpful tips to ensure that your vehicle is geared up for wintry road conditions: Bring your vehicle in for an inspection. Winter can involve some of the harshest conditions for your vehicle to endure, so have your vehicle checked by   …Continue Reading MassDOT, MAPFRE Insurance Encourage Motorists to Prepare for Winter Driving

RMV, AAA Announce New Service Location in Fairhaven posted on Nov 30

RMV, AAA Announce New Service Location in Fairhaven

The Massachusetts Department of Transportation Registry of Motor Vehicles (RMV), in partnership with AAA Northeast (AAA), announced today that the Fairhaven AAA Branch, located at 32 Fairhaven Commons Way, now offers select RMV license and registration services to AAA members. With the addition of Fairhaven,   …Continue Reading RMV, AAA Announce New Service Location in Fairhaven