Photo 4(5)MassDOT’s contractor, White-Skanska-Consigli (WSC), anticipates setting up the final configuration of Stage 3 construction for the Longfellow Bridge Rehabilitation Project by Thursday, February 11, 2016. The shift of the tracks to their temporary positions was completed over a series of MBTA Red Line Weekend Diversions. The relocation of the large barrier fence along the tracks will be completed February 1.

The installation of the upstream “Salt and Pepper” towers, hampered by the cold temperatures of mid-January, is complete with the last stones installed. Now that the towers are complete, removal of the staging is underway, followed by the placement of concrete sidewalks and curbs adjacent to the towers. Once the sidewalks and curbs are in place, the final sections of temporary fence needed for the new upstream bicycle lane can be installed.

WSC anticipates the final set up for the upstream bicycle lane will be complete by the end of the day on Thursday, February 11, 2016, when inbound and outbound bike travel is shifted. Stage 3 work will take approximately eight months to complete.

Travel Configuration

All bike travel, both inbound and outbound, will be shifted to the sidewalk on the upstream side of the bridge on February 11. During this stage, inbound vehicles and all pedestrians will continue to use the downstream side of the bridge.

MBTA Red Line Configuration

The construction of the temporary outbound Red Line track (called a “shoo-fly”) on the roadway is complete. The outbound trains were shifted to the shoo-fly track and the inbound trains were shifted to the old outbound track in mid-January. This shift allows WSC to rehabilitate the bridge under the current location of the MBTA inbound tracks.

The Cambridge-bound detour remains in place using the existing signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway (Route 28)/Charles River Dam Road and Land Boulevard.

For more information, visit the project website at www.mass.gov/massdot/longfellowbridge. For questions or issues and concerns related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us. View construction progress photos on MassDOT’s Longfellow Bridge Flickr Album.

Written By:

Tags: ,

Recent Posts

Baker-Polito Administration Authorizes MBTA Control Board Extension, Board and Staffing Transitions Announced posted on May 25

Baker-Polito Administration Authorizes MBTA Control Board Extension, Board and Staffing Transitions Announced

Acting to maintain momentum toward improving the MBTA for riders, Governor Charlie Baker, Lt. Governor Karyn Polito and Transportation Secretary and CEO Stephanie Pollack today announced that the MBTA’s Fiscal and Management Control Board (FMCB) will extend its governance by two years as allowed under   …Continue Reading Baker-Polito Administration Authorizes MBTA Control Board Extension, Board and Staffing Transitions Announced

Sumner Tunnel Traffic Adjustments posted on May 24

Sumner Tunnel Traffic Adjustments

MassDOT has announced that beginning on Thursday morning, May 25, it will be implementing the following adjustments to the traffic pattern in the area of the entrance of the Sumner Tunnel in order to improve traffic flow as construction activities continue for the ongoing toll   …Continue Reading Sumner Tunnel Traffic Adjustments

MassDOT: Plan Ahead for Memorial Day Travel posted on May 24

MassDOT: Plan Ahead for Memorial Day Travel

MassDOT advises Memorial Day holiday travelers to plan ahead, utilize MassDOT’s many travel “real time” tools and use public transportation if possible to travel between destinations. “We know from past years that travelers can expect heavy traffic volumes during Memorial Day weekend and should accordingly   …Continue Reading MassDOT: Plan Ahead for Memorial Day Travel