Post Content

MBTA Govt Center StationThe MBTA Government Center Station Project construction is scheduled to begin in spring 2013 with site preparation and work zone set up in support of the full station closure in late summer.

The $91 million, three-year Government Center Station Project will bring the new station, seen at left, into compliance with the Americans with Disabilities Act and combines improvements to the Green Line Station, Blue Line Station, and Cambridge Street/Government Center Plaza.

The project includes reconstruction of both the Green Line and Blue Line platforms, new elevators from the surface to the Green Line level and from the Green Line level to the Blue Line level, a new headhouse structure as the primary entrance to the Station, and reconstruction of Cambridge Street and City Hall plaza in the vicinity of the station. 

The result will be a new station fully accessible, customer-friendly and efficient, that creates an accessible route to Boston City Hall and surrounding public sidewalks.  The reconfiguration of the plaza is consistent with the City’s initiative of greening City Hall plaza.

The project will close Government Center Station to patrons for 24 months during the construction period by diverting passengers to other nearby stations.  Temporary closure of the station to patrons eliminates the need for a temporary headhouse, avoids numerous weekend and nightly closures, and allows construction to proceed more rapidly, reducing the overall construction schedule.

Written By:

Recent Posts

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th posted on Jul 26

Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

This is a reminder that the 2017 Construction Shutdown for the Commonwealth Avenue Bridge Replacement Project is beginning at 9:00 PM today, Wednesday July 26, and will continue through 5:00 AM on Monday, August 14. Please note the construction-related impacts below: For Pedestrians and Bicyclists:   …Continue Reading Commonwealth Avenue Bridge: Shutdown Steps Begin Tonight, July 26th

Springfield: I-91 Viaduct Rehabilitation Progress Continues posted on Jul 24

Springfield: I-91 Viaduct Rehabilitation Progress Continues

MassDOT and its contractor, the Joint Venture of White-Schiavone (JV), continue to make progress on rehabilitation of the Interstate 91 Viaduct (I-91) through Springfield. The contractor completed reconstruction of the center lanes of the highway last fall, and began Stage 2 of construction in November   …Continue Reading Springfield: I-91 Viaduct Rehabilitation Progress Continues

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts posted on Jul 23

Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts

MassDOT is reminding the public that travel impacts will begin next week throughout the Boston University/Saint Paul Street neighborhood of Boston along Commonwealth Avenue due to the Commonwealth Avenue Bridge Replacement Project. Drivers on Commonwealth Avenue, the BU Bridge and I-90 will see lane closings   …Continue Reading Commonwealth Avenue Bridge Project: MBTA, Traffic Impacts